Cullen v. Town Council of the Lincoln

850 A.2d 900, 2004 R.I. LEXIS 75, 2004 WL 764706
CourtSupreme Court of Rhode Island
DecidedApril 12, 2004
Docket2001-212-M.P.
StatusPublished
Cited by32 cases

This text of 850 A.2d 900 (Cullen v. Town Council of the Lincoln) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cullen v. Town Council of the Lincoln, 850 A.2d 900, 2004 R.I. LEXIS 75, 2004 WL 764706 (R.I. 2004).

Opinion

OPINION

WILLIAMS, Chief Justice.

This case is before the Court on a writ of certiorari directing the respondent, the Town Council of the Town of Lincoln (council) to deliver the record to this Court so that we may review its decision denying the petitioners’, John J. Cullen and Roland Montigny (petitioners), application to tie into the sewer system of the Town of *902 Lincoln (town). Because the council failed to accompany its decision with adequate factual findings and legal conclusions, we remand the record to the council with instructions to make such findings and conclusions.

I

Facts and Travel 1

The petitioners own a tract of land, known as Whipple Cullen Farm, in the town. With hopes of developing the tract into a residential subdivision (subdivision), the petitioners began the approval process outlined in G.L.1956 § 45-23-39(b), which requires people proposing major land developments and major subdivisions to obtain master plan approval, preliminary plan approval, and then final plan approval. 2 After receiving master plan approval from the planning board in 1998, the petitioners sought preliminary plan approval pursuant to § 45-23-41. To that end, petitioners requested approval to connect the proposed subdivision’s sewer line to the town’s sewer system.

By ordinance, application to connect to the town’s sewer system must be made to the town’s director of public works. Lincoln, Code of Ordinances ch. 19, art. II, § 19-96 (1990) (ch. 19, art. II is hereafter referred to as sewer ordinance). If the director of public works rejects the application, the property owner may appeal to the town sewer appeal board (appeal board), which in turn forwards its recommendation to the council for final determination. Id. at § 19-32.

In March 1999, petitioners met with then-director, Robert C. Schultz, P.E. (director), about their request to connect to the town’s sewer system. Their plans proposed a sewer line that would discharge into a town pumping station, known as the Lower River Road pumping station (pumping station). Concerned about the pumping station’s capacity to handle the additional effluent that the subdivision would generate, the director suggested three alternate routes for the subdivision’s sewer lines. Each of the alternate routes would allow petitioners to tie into the sewer system, but would avoid connecting through the pumping station. Although the alternates would allow the subdivision effluent to be propelled by gravity rather than a pump, they apparently would require the lines to traverse designated wetlands. Thus, petitioners met with officials from the Department of Environmental Management (DEM) to discuss the alternates.

In a letter dated April 21, 1999, DEM informed petitioners that the proposed alternate routes would pass through and alter wetlands and, therefore, they would have to apply for DEM approval. The letter explained that “[tjhrough its review of an Application to Alter, the [DEM] would' have to determine if the proposed alteration would result in a random, unnecessary, and/or undesirable alteration of a freshwater wetland * * DEM’s determination would depend on whether and to what extent impacts to the wetlands have been avoided, whether the proposed routes “eliminate[ ] or minimize[ ] probable impacts to freshwater wetland functions and values, and the environmental, health, welfare and general well-being of the po-pulance [szc]” and whether the proposed project would contribute to an adverse cumulative impact on the wetlands. The DEM estimated that the application pro *903 cess would take eight to twelve months, but it did not intimate a likely outcome.

Believing they would not receive the necessary permits from DEM, petitioners moved forward with their application to connect the sewer lines through the pumping station as they originally had planned. The town denied petitioners’ application, citing concerns over esthetics, environmental impacts and the pump station’s ability to handle the subdivision’s sewerage. 3 The denial letter also noted that petitioners still had not submitted a detailed analysis of the alternate routes.

The petitioners appealed the rejection of their application to the appeal board. The appeal board held two days of hearings, during which time various proponents and objectors testified on the matter. Ultimately, the appeal board recommended that the council grant petitioners’ request to lay the sewer lines as they proposed and connect through the pumping station on the condition that petitioners provide certain upgrades to the pumping station. This decision was forwarded to the council for final determination.

The council reviewed petitioners’ application at a town council meeting on February 20, 2001. David McCombs (McCombs), an engineer retained by petitioners, explained that the pumping station route was the best option because it did not require traversing wetlands. He explained that the pumping station was acting only at 34 percent capacity and, after accepting sewage from the subdivision, the capacity would only be at 60 to 65 percent. According to McCombs, the pumping station was designed to handle 280 homes, but only 80 homes were connected to it at the time. Thus, he testified, with appropriate upgrades paid for by petitioners, the pumping station could handle the additional load. The town’s engineer, Larry Smith (Smith), testified that he believed that alternate routes could be explored further. The council also heard testimony from citizens opposing and supporting petitioners’ project due to environmental concerns.

After hearing all the testimony, Councilman Dennis Auclair 4 moved to reject petitioners’ application to tie into the pumping station because “there are other alternate routes” available to petitioners that would allow them to tie into the sewer system without using the pumping station. The council unanimously approved the motion and denied the application. We granted a writ of certiorari to review the decision of the council.

II

Standard of Review

When reviewing a case before this Court on a writ of certiorari, we “scour the record to discern whether any legally competent evidence supports the lower tribunal’s decision and whether the decision[-]maker committed any reversible errors of law in the matter under review.” Kent County Water Authority v. State (Department of Health), 723 A.2d 1132, 1134 (R.I.1999). “If legally competent evidence exists to support that determination, we will affirm it unless one or more errors of law have so infected the validity of the proceedings as to warrant reversal.” Id.

*904 III

Adequacy of the Decision

The petitioners first argue that the council's decision must be quashed because it is lacking sufficient factual findings and legal conclusions. We agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicholas DiBiccari v. State of Rhode Island
Supreme Court of Rhode Island, 2026
Rajmonda Mile v. Kirkbrae Country Club
Supreme Court of Rhode Island, 2025
Asa S. Davis, III v. Town of Exeter
Supreme Court of Rhode Island, 2022
Patrizia Prew v. Employee Retirement System of the City of Providence
139 A.3d 556 (Supreme Court of Rhode Island, 2016)
Michael Morse v. Employees Retirement System of the City of Providence
139 A.3d 385 (Supreme Court of Rhode Island, 2016)
Bonome v. Nott
Superior Court of Rhode Island, 2009
Muschiano v. Travers
973 A.2d 515 (Supreme Court of Rhode Island, 2009)
Pierce v. Providence Retirement Board
962 A.2d 1292 (Supreme Court of Rhode Island, 2009)
Morr-Fitz, Inc. v. Blagojevich
Illinois Supreme Court, 2008
Mutter v. Doyle
Superior Court of Rhode Island, 2008
Kedy v. A.W. Chesterton Co.
946 A.2d 1171 (Supreme Court of Rhode Island, 2008)
City of Providence v. Estate of Tarro
Superior Court of Rhode Island, 2008
State v. Thomas
936 A.2d 1278 (Supreme Court of Rhode Island, 2007)
Jensen v. Alexandre
Superior Court of Rhode Island, 2007
Cunha v. Zoning Board of Review
Superior Court of Rhode Island, 2007
Woodfield Farm, LLC v. Zoning Board, Kc
Superior Court of Rhode Island, 2007

Cite This Page — Counsel Stack

Bluebook (online)
850 A.2d 900, 2004 R.I. LEXIS 75, 2004 WL 764706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cullen-v-town-council-of-the-lincoln-ri-2004.