Cuevas Machine v. Calgon Carbon

CourtCourt of Appeals for the Fifth Circuit
DecidedApril 15, 2026
Docket25-60198
StatusPublished

This text of Cuevas Machine v. Calgon Carbon (Cuevas Machine v. Calgon Carbon) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cuevas Machine v. Calgon Carbon, (5th Cir. 2026).

Opinion

Case: 25-60198 Document: 61-1 Page: 1 Date Filed: 04/15/2026

United States Court of Appeals for the Fifth Circuit ____________ United States Court of Appeals Fifth Circuit

No. 25-60198 FILED April 15, 2026 ____________ Lyle W. Cayce Cuevas Machine Company, Clerk

Plaintiff—Appellant,

versus

Calgon Carbon Corporation.

Defendant—Appellee. ______________________________

Appeal from the United States District Court for the Southern District of Mississippi USDC No. 1:24-CV-114 ______________________________

Before Elrod, Chief Judge, and Smith and Wilson, Circuit Judges. Cory T. Wilson, Circuit Judge: This case concerns the requirements for the creation of a valid construction lien under Mississippi law. Cuevas Machine Company sued Calgon Carbon Corporation seeking to foreclose on two construction liens. The district court dismissed Cuevas’s complaint with prejudice under Federal Rule of Civil Procedure 12(b)(6) after making an Erie guess that Cuevas’s liens did not comply with Miss. Code Ann. § 85-7-405(1)(b) and were therefore unenforceable. This appeal followed. Case: 25-60198 Document: 61-1 Page: 2 Date Filed: 04/15/2026

No. 25-60198

It is unclear from state precedent whether the Mississippi Supreme Court would interpret the relevant lien statute flexibly or in strict accordance with its terms. More precisely, we remain uncertain as to whether a lienor may establish the “last date” on which labor, services, or materials were provided—as required to create a valid construction lien—by attaching invoices that do not clearly identify such a “last date.” To avoid misapplying the state’s construction lien statute, we certify the issue to the Mississippi Supreme Court. I. In May 2022, Cuevas Machine Company subcontracted with O’Neal Constructors, a general contractor, to perform fabrication and machining services at a filtration plant owned by Calgon Carbon Corporation in Hancock County, Mississippi. Under the subcontract’s “pay-when-paid” clause, O’Neal was bound to pay Cuevas for its services once Calgon paid O’Neal. By June 2023, O’Neal had stopped paying Cuevas, alleging that Calgon had failed to pay O’Neal for its work. Despite the lack of payment, Cuevas continued to perform the requested work at the Calgon plant. In October 2023, Cuevas timely recorded two separate construction liens against the Calgon property improved by Cuevas’s work. The two liens are for $763,245 and $471,661, totaling roughly $1.23 million. The liens themselves do not explicitly state the “last date [that] labor, services or materials were supplied to the premises”—a requirement to create an “effective or enforceable” construction lien. Miss. Code Ann. § 85-7-405(1)(b). Instead, Cuevas attached dated invoices to the two liens stating what work was performed and the amount owed for each part of Cuevas’s work. But it is unclear from the invoices themselves whether the dates listed reflect the dates that particular services were provided, the dates

2 Case: 25-60198 Document: 61-1 Page: 3 Date Filed: 04/15/2026

on which Cuevas generated the invoices, or some other dates relevant to Cuevas’s accounting practices. Cuevas initially sued Calgon in Mississippi state court to foreclose on its liens. After removing the case to federal court, Calgon moved to dismiss under Rule 12(b)(6), contending that the liens did not comply with the requirements of § 85-7-405(1)(b), rendering them unenforceable. The district court granted the motion and dismissed Cuevas’s complaint with prejudice. In its order, the district court noted the absence of Mississippi precedent on this issue. The court then made an Erie guess 1 that the liens were unenforceable because (1) the lien documents themselves did not specify the “last date [that] labor, services or materials were supplied to the premises,” id. § 85-7-405(1)(b), and (2) the attached invoices did not specify the relevant dates clearly enough to render the liens substantially compliant with state law. Cuevas appealed. II. After reviewing the district court’s decision and the relevant sources of state law, we are uncertain whether the liens recorded by Cuevas comply with state law such that they may properly be enforced. To resolve that uncertainty, it is most prudent to certify the question to the Mississippi Supreme Court. A. We review dismissal under Rule 12(b)(6) de novo, “accept[ing] all facts in the complaint as true” and construing them in the light most favorable to the plaintiff. McKay v. LaCroix, 117 F.4th 741, 746 (5th Cir. 2024). We do not accept a plaintiff’s “unwarranted factual inferences” or

_____________________ 1 See Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78 (1938).

3 Case: 25-60198 Document: 61-1 Page: 4 Date Filed: 04/15/2026

“legal conclusions.” Id. We likewise review a district court’s Erie guess de novo. Civelli v. J.P. Morgan Sec., L.L.C., 57 F.4th 484, 493 (5th Cir. 2023). In this diversity case, Mississippi substantive law controls. Compliance Source, Inc. v. GreenPoint Mortg. Funding, Inc., 624 F.3d 252, 259 (5th Cir. 2010). Thus, we first “examine Mississippi law to determine whether any final decisions of the Mississippi Supreme Court are dispositive.” Paz v. Brush Engineered Materials, Inc., 555 F.3d 383, 392 (5th Cir. 2009). If “there is no apposite decision, [we] must forecast how the Mississippi Supreme Court would rule.” Id. In making this prediction, “we consider many of the same sources we use when guessing the law of other jurisdictions: decisions and reasoning of the state’s courts; general rules of [state law], such as those governing statutory interpretation; and secondary sources like treatises.” Jorge-Chavelas v. La. Farm Bureau Cas. Ins. Co., 917 F.3d 847, 850–51 (5th Cir. 2019). We “may look to the decisions of intermediate appellate state courts for guidance” as well. Howe v. Scottsdale Ins. Co., 204 F.3d 624, 627 (5th Cir. 2000). The Mississippi Supreme Court has explained that, where “the words of a statute are clear and unambiguous,” the court “applies the plain meaning of the statute and refrains from using principles of statutory construction.” Am. Tower Asset Sub, L.L.C. v. Marshall Cnty., 324 So. 3d 300, 302 (Miss. 2021). “But if the statute is ambiguous or silent on a specific issue, statutory interpretation is appropriate, and the Court must ‘ascertain the intent of the legislature from the statute as a whole and from the language used therein.’” Id. (quoting In re Guardianship of Duckett, 991 So. 2d 1165, 1181–82 (Miss. 2008)). The Mississippi construction lien statute states that a construction lien “must be created and declared in accordance with the [enumerated] provisions, and on failure of any of them the lien shall not be effective or

4 Case: 25-60198 Document: 61-1 Page: 5 Date Filed: 04/15/2026

enforceable.” Miss. Code Ann. § 85-7-405(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howe v. Scottsdale Insurance Co.
204 F.3d 624 (Fifth Circuit, 2000)
Paz v. Brush Engineered Materials, Inc.
555 F.3d 383 (Fifth Circuit, 2009)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Federated Mut. Ins. Co. v. McNeal
943 So. 2d 658 (Mississippi Supreme Court, 2006)
Saul v. Jenkins
963 So. 2d 552 (Mississippi Supreme Court, 2007)
Lawrence v. Rankin
870 So. 2d 673 (Court of Appeals of Mississippi, 2004)
Jones Supply Co. v. Ishee
163 So. 2d 470 (Mississippi Supreme Court, 1964)
Chancellor v. Melvin
52 So. 2d 360 (Mississippi Supreme Court, 1951)
In Re Guardianship of Duckett
991 So. 2d 1165 (Mississippi Supreme Court, 2008)
Wortman & Mann, Inc. v. Frierson Building Supply Co.
184 So. 2d 857 (Mississippi Supreme Court, 1966)
Hart v. Catoe
390 So. 2d 1001 (Mississippi Supreme Court, 1980)
Robert Swindol v. Aurora Flight Sciences Corp.
805 F.3d 516 (Fifth Circuit, 2015)
Land Holdings I, LLC v. GSI Services, LLC
265 So. 3d 147 (Mississippi Supreme Court, 2019)
Jorge-Chavelas v. La. Farm Bureau Cas. Ins. Co.
917 F.3d 847 (Fifth Circuit, 2019)
State v. Jacobs
67 So. 3d 535 (Louisiana Court of Appeal, 2011)
Sharpe v. Spengler
48 Miss. 360 (Mississippi Supreme Court, 1873)
Morris v. Shryock
50 Miss. 590 (Mississippi Supreme Court, 1874)
Strauss v. Baley
58 Miss. 131 (Mississippi Supreme Court, 1880)
Jones v. Alexander
18 Miss. 627 (Mississippi Supreme Court, 1848)

Cite This Page — Counsel Stack

Bluebook (online)
Cuevas Machine v. Calgon Carbon, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cuevas-machine-v-calgon-carbon-ca5-2026.