C.S.A. Contracting Corp. v. New York City School Construction Authority
Opinions
OPINION OF THE COURT
The issue here is whether plaintiff C.S.A. Contracting Corp. timely filed a notice of claim pursuant to Public Authorities Law § 1744 (2) in this breach of contract action seeking payment from defendant New York City School Construction Authority for work it performed. Under the facts and circumstances of this case, we conclude that the notice of claim was not timely because it was not submitted within three months of the accrual of the claims.
In 1993, the New York City School Construction Authority (SCA) and plaintiff entered into a contract in which SCA agreed to pay plaintiff $1 million to perform asbestos abatement work at various city schools. The project included asbestos removal at PS 29 in Staten Island. On December 3, 1993, plaintiff submitted a request for payment for extra work performed at PS 29 in the amount of $151,994.96. SCA apparently approved the request in February 1994, but two months later informed plaintiff that it would not remit payment for the PS 29 job because it determined that plaintiff had overcharged for abatement work at another work site—Bushwick High School.
On May 9, 1994, plaintiff purportedly served a notice of claim on SCA seeking monies it contended were owed under its contract. Plaintiff subsequently issued a notice of dispute on June 30, 1994 requesting to mediate its payment claim with SCA. After mediation failed to resolve the conflict, plaintiff submitted a notice of claim dated September 21, 1994. This notice of claim sought the payment of $595,850 for three categories of work performed by plaintiff: asbestos abatement at PS 29, additional costs incurred in the removal of asbestos from heights in excess of 14 feet, and wet cleaning and encapsulation expenses.
Plaintiff commenced this breach of contract action against SCA in April 1995 to recover damages for the claims outlined in its notice of claim, alleging that it had furnished SCA with notice in June 1994 and again in September 1994. In its answer, SCA interposed an affirmative defense that plaintiff had failed to properly serve a notice of claim. SCA also counterclaimed for the alleged overpayment for work performed at Bushwick High School.
[192] At trial, plaintiff was unable to submit documentary evidence corroborating the service of a notice of claim in May 1994. Its former corporate president testified that all work at PS 29 was completed before December 1993. At the close of plaintiffs case, SCA moved to dismiss the complaint for failure to present a timely notice of claim. Supreme Court granted the motion and dismissed the complaint, holding that plaintiff did not submit a notice of claim within three months of the accrual of its claims. The court also severed SCA’s counterclaim. The Appellate Division affirmed. We granted plaintiff leave to appeal and now concur that plaintiffs complaint must be dismissed.
Section 1744 (2) of Public Authorities Law provides, in part:
“No action or proceeding for any cause whatever, other than the one for personal injury, death, property damage or tort . . . relating to the design, construction, reconstruction, improvement, rehabilitation, repair, furnishing or equipping of educational facilities, shall be prosecuted or maintained against [SCA] . . . unless (i) it shall appear by and as an allegation in the complaint or moving papers, that a detailed, written, verified notice of each claim upon which any part of such action or proceeding is founded was presented to the board within three months after the accrual of such claim . . . .”
A timely notice of claim is a condition precedent to maintaining an action against SCA, and the plaintiff has the obligation to plead and prove that its notice of claim was served within three months after the accrual of its claim (see generally Parochial Bus Sys. v Board of Educ. of City of N.Y., 60 NY2d 539, 547 [1983]; Rogers v Village of Port Chester, 234 NY 182, 185 [1922]).
It is well settled that a contractor’s claim accrues when its damages are ascertainable (see Matter of Board of Educ. of Enlarged Ogdensburg City School Dist. [Wager Constr. Corp.], 37 NY2d 283, 290 [1975]). Although the determination of the date on which damages are ascertainable may vary based on the facts and circumstances of each particular case, “it generally has been recognized that damages are ascertainable once the work is substantially completed or a detailed invoice of the work performed is submitted” (New York City School Constr. Auth. v Kallen & Lemelson, 290 AD2d 497 [2d Dept 2002] [internal quotation marks and citations omitted]).
Here, plaintiff completed its work at PS 29 some time before December 1993, and finished its rehabilitation project entirely [193] by the close of 1993. Plaintiff also submitted a detailed invoice for work done at PS 29 on December 3, 1993. Therefore, plaintiffs claims were ascertainable and accrued by the end of 1993.
Footnotes
Free access — add to your briefcase to read the full text and ask questions with AI
833 N.E.2d 266 (C.S.A. Contracting Corp. v. New York City School Construction Authority) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.