Cryogenic Vessel Alternatives, Inc. v. Lily and Yvette Construction, LLC

CourtCourt of Appeals of Texas
DecidedJanuary 16, 2015
Docket01-13-00737-CV
StatusPublished

This text of Cryogenic Vessel Alternatives, Inc. v. Lily and Yvette Construction, LLC (Cryogenic Vessel Alternatives, Inc. v. Lily and Yvette Construction, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cryogenic Vessel Alternatives, Inc. v. Lily and Yvette Construction, LLC, (Tex. Ct. App. 2015).

Opinion

Opinion issued January 15, 2015

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-13-00737-CV ——————————— CRYOGENIC VESSEL ALTERNATIVES, INC., Appellant V. LILY AND YVETTE CONSTRUCTION, LLC, Appellee

On Appeal from the 253rd District Court Chambers County, Texas Trial Court Case No. CV-27397-A

MEMORANDUM OPINION

Plaintiff-appellee Lily & Yvette Construction, LLC (Lily) sued defendant-

appellant Cryogenic Vessel Alternatives, Inc. (CVA) and defendant Crestmont

Construction, asserting claims for breach of contract, fraud, fraud in the

inducement, and unjust enrichment. After the trial court severed a partial summary judgment in Lily’s favor against CVA, CVA appealed. Because we conclude that

there is not yet a final and appealable judgment, we dismiss the appeal.

BACKGROUND

Lily, a subcontractor hired by general contractor Crestmont, alleged that it

had not been paid for construction work it performed on CVA’s property and

sought damages and foreclosure of a lien on the property to satisfy the $82,700.00

remaining debt and attorneys’ fees. CVA disputed the validity of the lien and

counterclaimed, seeking to invalidate the lien and attorneys’ fees. On cross-

motions for summary judgment, on May 30, 2013, the trial court denied CVA’s

motion seeking removal of the lien and granted summary judgment in Lily’s favor,

awarding Lily $82,700.00 in damages, as well as prejudgment interest and

attorneys’ fees.

On July 12, 2013, Lily dismissed its non-lien related claims against CVA,

and all of its claims against Crestmont. Later that same day, the trial court severed

the summary judgment against CVA into a new cause, and left pending in the

original cause a cross-claim claim between CVA and Crestmont.

JURISDICTION

The cause number of the original suit was CV-27397. The severed cause

number, containing the summary judgment in Lily’s favor against CVA, was CV-

27397-A. On July 31, 2013, CVA filed a motion for reconsideration of the

2 summary judgment and motion for new trial in the original cause number, CV-

27397. That same day, July 31, 2013, and in the severed cause, Lily filed a Motion

to Foreclose, Order Sale, and Issue Writ of Possession. CVA did not file any post-

judgment motions in the severed cause, CV-27397-A, until August 28, 2013, when

it filed a Motion for Protection regarding post-judgment discovery.

On August 26, 2013—45 days after the severance order—CVA filed a

notice of appeal in the severed cause CV-27397-A, stating it was appealing the

summary judgment “signed on May 30, 2013 and potentially made final and

appealable by the Severance order signed on July 12, 2013.” That same day, CVA

filed a motion for extension of time in the appellant court, stating, in its entirety:

Appellant Cryogenic Vessel Alternatives, Inc. (“CVA”) files this motion seeking an extension of time, until August 26, 2013, to file its Notice of Appeal. CVA believes its Notice of Appeal, filed today in the trial court (and attached hereto), is timely but files this motion out of an abundance of caution. On September 12, 2013, Lily filed a Notice of Inadvertent Filing in

Incomplete Cause Number stating that it inadvertently filed its motion for

reconsideration and new trial in CV-29397 rather than CV-29397-A.

A. Parties’ Arguments

Lily filed a motion to dismiss CVA’s appeal, arguing that—under Philbrook

v. Berry, 683 S.W.2d 378, 379 (Tex. 1985)—CVA’s filing its post-trial motions in

the original cause, i.e., CV 27397, failed to extend plenary power. Moreover, Lily

3 argued, CVA did not meet the requirements for a 15-day extension of time because

it (1) did not file a notice of appeal in the trial court, and (2) did not, in its motion

for extension of time, state “the facts relied on to reasonably explain the need for

an extension.” TEX. R. APP. P. 10.5(b), 26.3.

CVA responded to Lily’s motion to dismiss, arguing that (1) there is no final

judgment in this matter, so the notice of appeal was early, not late, (2) even if the

July 12, 2013 severance order resulted in a final judgment, CVA timely filed a

motion for new trial that extended plenary power even though it was filed in the

wrong cause number, and (3) even if the motion for new trial did not effectively

extend the appellate deadlines, the notice of appeal and the unopposed motion for

extension of time to file the notice of appeal complied with the requirements for

securing a 15-day extension.

B. Is there a Final Judgment?

Lily’s petition seeks from CVA both a money judgment and foreclosure of a

lien to satisfy the amounts that Crestmont did not pay Lily for work on CVA’s

property. Lily’s summary judgment motion “ask[s] th[e] Court to rule in favor of

Plaintiff on its cause of action as no issue of fact exists and Plaintiff is due a

judgment in its favor as a matter of law.” Lily’s motion cited section 53.083 of the

Texas Property Code as the statutory basis for summary judgment, which sets forth

4 circumstances in which a property owner is liable for unpaid amounts due

subcontractors:

§ 53.083. Payment to Claimant on Demand

(a) The claimant may make written demand for payment of the claim to an owner authorized to withhold funds under this subchapter. The demand must give notice to the owner that all or part of the claim has accrued under Section 53.053 or is past due according to the agreement between the parties. (b) The claimant must send a copy of the demand to the original contractor. The original contractor may give the owner written notice that the contractor intends to dispute the claim. The original contractor must give the notice not later than the 30th day after the day he receives the copy of the demand. If the original contractor does not give the owner timely notice, he is considered to have assented to the demand and the owner shall pay the claim. (c) The claimant’s demand may accompany the original notice of nonpayment or of a past-due claim and may be stamped or written in legible form on the face of the notice. (d) Unless the lien has been secured, the demand may not be made after expiration of the time within which the claimant may secure the lien for the claim. Lily’s motion for summary judgment also argues that Lily complied with the

statutory requirements for perfecting a lien under section 53.052 of the Texas

Property Code:

(a) Except as provided by Subsection (b), the person claiming the lien must file an affidavit with the county clerk of the county in which the property is located or into which the railroad extends not later than the 15th day of the fourth calendar month after the day on which the indebtedness accrues. (b) A person claiming a lien arising from a residential construction project must file an affidavit with the county clerk of the county in

5 which the property is located not later than the 15th day of the third calendar month after the day on which the indebtedness accrues.

“Foreclosure” is not mentioned in Lily’s motion for summary judgment,

which requests “summary judgment in the amount of $82,700 for unpaid work

done on Cryogenics property; pre-judgment interest in the amount of $19,848.00;

and reasonable and necessary attorney’s fees in the amount of $13,364.”

The trial court’s May 30, 2013, order granting summary judgment likewise

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Philbrook v. Berry
683 S.W.2d 378 (Texas Supreme Court, 1985)
Mortgage & Trust, Inc. v. Bonner & Co., Inc.
572 S.W.2d 344 (Court of Appeals of Texas, 1978)
Stephens v. LPP MORTGAGE, LTD.
316 S.W.3d 742 (Court of Appeals of Texas, 2010)
Lehmann v. Har-Con Corp.
39 S.W.3d 191 (Texas Supreme Court, 2001)
American Heritage Capital, LP v. Dinah Gonzalez and Alan Gonzalez
436 S.W.3d 865 (Court of Appeals of Texas, 2014)
Long v. Castle Texas Production Ltd. Partnership
426 S.W.3d 73 (Texas Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Cryogenic Vessel Alternatives, Inc. v. Lily and Yvette Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cryogenic-vessel-alternatives-inc-v-lily-and-yvett-texapp-2015.