Crutcher, Rolfs, Cummings, Inc. v. Big Three Welding Equipment Co.

224 S.W.2d 884, 38 A.F.T.R. (P-H) 1188, 1949 Tex. App. LEXIS 2228
CourtCourt of Appeals of Texas
DecidedNovember 3, 1949
DocketNo. 12098
StatusPublished
Cited by7 cases

This text of 224 S.W.2d 884 (Crutcher, Rolfs, Cummings, Inc. v. Big Three Welding Equipment Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crutcher, Rolfs, Cummings, Inc. v. Big Three Welding Equipment Co., 224 S.W.2d 884, 38 A.F.T.R. (P-H) 1188, 1949 Tex. App. LEXIS 2228 (Tex. Ct. App. 1949).

Opinion

CODY, Justice.

The principal question for determination on this appeal is that of priority of the [886]*886liens claimed by the parties to this appeal as securing their claims against the fund of $21,880.39, which was the amount of the sum which remained unpaid by the Humble Pipe Line Company upon its debt to Lade-wig Engineering Co., at the time a writ of garnishment was served upon said pipe line company at the behest of the Big Three Welding Equipment Co., Inc. The date of the service of said writ of garnishment was October 29, 1947.

There is no contention here made that there was any irregularity of any. kind in the garnishment proceedings. The Humble Pipe Line Company will hereafter be called the garnishee. The Big Three Welding Equipment Co., Inc., will be called the garnisher; the Ladewig Engineering Co., will be called the debtor. The garnishee seasonably filed its answer to the effect that it was indebted to the debtor in the sum of $21,880.39 for work done by debtor as an independent contractor, and further that there were numerous parties asserting the right to claims against the debtor and against said sum of $21,880.39; and garnishee, in its answer to garnisher’s writ of garnishment, asked leave to bring a stakeholder’s suit against all claimants to said sum of $21,880.39. The court granted garnishee’s prayer to require all claimants to interplead, and permitted the fund to be paid into the registry of the court, and, as will hereafter appear, rendered judgment relieving the garnishee from liability in connection with said sum so paid into court.

The parties named as claimants in the garnishee’s stakeholder’s suit, with few exceptions, duly filed pleadings interplead-ing their claims. There is no contention that the amounts of their respective claims were not properly proved, so we will not in every instance state the amount of such claim. (A) The garnisher claimed that its garnishment lien was the prior lien, and that its claim was entitled to be fully satisfied from the fund so paid into court before the fund was subjected to the payment of any other claim. (B) The United States government filed its intervention in said stakeholder’s suit, and it alleged that the debtor owed an unpaid balance of withholding tax in a specified amount, and the United States further alleged that it duly perfected its lien to secure the payment thereof as of November 7, 1947. (C) Appellant, Crutcher, Rolfs, Cummings, Inc. (hereafter called Crutcher, Inc.) asserted its claim for an unpaid balance of $1133.00, for materials and supplies furnished debtor, and which were used in the fulfillment of debtor’s contract with garnishee,- and Crutcher, Inc., further pled that it had duly perfected a statutory mechanics’ and ma-terialmen’s lien, and was entitled to have same paid out of said fund, etc. (D) Appellant, Kane Trucking Company, asserted its claim against debtor for $15,092.42, for hauling and trucking services performed in connection with debtor’s contract with garnishee. Said trucking company further alleged that it had duly perfected its mechanics’ and materialmen’s lien to secure the payment of said sum, etc. (E) Parties too numerous to be here named filed claims for services which they claimed to have performed as laborers, and which they asserted were secured by constitutional liens; and other claimants filed claims.

The court tried the case without a jury. It duly rendered judgment against such of the parties as filed disclaimers, and also against such of the parties as made default in the stakeholder’s suit. In addition the court rendered judgment:

' I. That the garnishee was indebted to debtor, for work done by debtor as an independent contractor, at the time the writ of garnishment was served, in the sum of $21,880.39, and that garnishee has paid.all of said sum into court, and that garnishee was released of all liability in connection with claims against debtor. Garnishee was awarded $500.00 as attorney’s fees.

II. That garnisher had established its claim against debtor in the sum of $2,411.69 and that it had acquired a garnishment lien, and said lien was prior to the lien of any and all other claimants, and the court ordered garnisher’s claim to be paid out of aforesaid sum which had been paid into the registry of the court.

III.. That intervenor, United States, had established its claim against debtor for withholding taxes in the sum of $17,189.07, and has duly perfected its lien to secure [887]*887the payment thereof, and that said lien was prior to the liens of all other parties to the suit except garnisher’s aforesaid garnishment lien.

IV. That claimants Crutcher, Inc., Kane Trucking Company, Humble Oil Refining Company, etc., have established their respective claims against debtor. But that, since neither the mechanics’ and material-men’s and laborers’ liens, sought to be fixed, can be fixed either as statutory or as constitutional liens upon the pipe line belonging to garnisheee, nor fixed upon the fund tendered into court, as aforesaid, said parties have no priority right to the fund so tendered into court. But the court ruled that the said parties, referred to in this paragraph, are entitled to share pro rata in the balance of the fund after the claims of the garnisher and the United States have been satisfied. And the court by its judgment did award such balance of the fund, which had been paid into court, on a pro rata basis, among the claimants other than garnisher and the United States government. The Kane Trucking Company was so awarded $886.04; the Crutcher, Inc. $66.56; the Humble Oil and Refining Co. $291.93, etc. And said parties were awarded judgment against debtor for the full amount of their respective claims, but, as indicated, were denied liens to secure payment of same.

The parties to said stakeholder’s suit other than the garnisher and garnishee excepted to said judgment, and gave notice of appeal. Crutcher, Inc., and Kane Trucking Company excepted to the action of the court in refusing to establish and foreclose their claimed mechanics’ and materialmen’s liens and in refusing to hold same to be first, prior and superior liens which were required to be paid out of the fund in the registry of the court, etc. This brings us to a statement of the controlling facts relating to the mechanics’ and materialmen’s liens:

In June, 1947, the garnishee (the pipe line company) entered into a contract with the debtor (the independent contractor) by which the debtor became obligated to do various things in connection with various portions of garnishee’s pipe line, consisting of 8-inch pipe, and which aggregated about fifty miles. The portions of the pipe line affected are located between Groesbeck and Palestine, 15.55'miles thereof being between Gate Plant “C” and Todd Station; 28.03 miles being located between Gate Plant “K” and Fairfield Station; and 6.67 miles being located between Gate Plant “J” and Groesbeck Station. The contract is lengthy, covering some twenty pages of the statement of facts.

Prior to the time the contract was made and performance was had thereunder, the portions of the pipe line system which were the subject of the contract consisted, as a whole, of duplicate or parallel pipe lines, and in some instances, of triplicate pipe lines. For reasons not developed in the evidence, or not pointed out, it became possible and profitable for garnishee to handle the load carried at these portions of its pipe line system by a single pipe line, and in some instances it allowed parallel pipe lines to remain; but apparently allowed no triplicate pipe lines to remain at said portions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
224 S.W.2d 884, 38 A.F.T.R. (P-H) 1188, 1949 Tex. App. LEXIS 2228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crutcher-rolfs-cummings-inc-v-big-three-welding-equipment-co-texapp-1949.