Croy v. Poole

3 Va. Cir. 234, 1984 Va. Cir. LEXIS 105
CourtShenandoah County Circuit Court
DecidedOctober 2, 1984
DocketCase No. (Chancery) 2459
StatusPublished

This text of 3 Va. Cir. 234 (Croy v. Poole) is published on Counsel Stack Legal Research, covering Shenandoah County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Croy v. Poole, 3 Va. Cir. 234, 1984 Va. Cir. LEXIS 105 (Va. Super. Ct. 1984).

Opinion

By JUDGE PERRY W. SARYER

Set forth herein is the opinion of the Court after hearing evidence and after consideration of the pleadings filed herein.

Briefly, the evidence shows that Defendants Poole purchased a parcel of real estate in the Town of New Market, Shenandoah County, said real estate being conveyed to them by deed dated June 9, 1983, acknowledged June 10, 1983, (there being two acknowledgements, and the last acknowledgement was June 10, 1983) and was admitted to record on August 9, 1983, in Deed Book 457, page 289, of the Clerk’s office of the Circuit Court of Shenandoah County.

Some time in early June, and perhaps even before Defendants Poole acquired title to said real estate, Mr. Poole met with Plaintiff Croy (herein referred to as Croy) and discussed contracting with Croy to excavate the said property, level it and install footers for the construction of a dwelling house. The testimony is uncontradicted that the parties visited the property and it appears that also from the evidence that the property was covered with a heavy undergrowth and it was impossible to determine the topography of the real estate at that time. Croy testified that he was aware in walking the property that it was not level and Mr. Steven Pizzo, who accompanied the par[235]*235ties to the property, stated that the property was not level while Mr. Poole was of the opinion that the property was almost level. It appears from the testimony that the only level ground was at the top of a hill which was not involved in the construction process. There was also evidence that Mr. Poole was not sure as to exactly where he wanted to locate the house and, during the course of the excavation, the location was changed several times although this did not cause any substantial problems. Mr. Poole had looked at the lot only a few days before the purchase and then met with Croy a few days thereafter and had not made a thorough examination.

After the property was cleared, it was found that there was a grade of approximately 16° and this would result in substantial grading that was not contemplated by the parties, which required substantial blasting and excavation. During the course of the period of time in which the blasting was taking place, rock and dirt being removed, Croy testified that it was realized that, due to the large quantity of dirt and rock not contemplated by the parties, it would be necessary to remove the same from the premises and Croy states that this was also an extra to be paid for by Poole, which is denied by them.

Plaintiff completed the leveling of the area where the house was to be placed, installed the footers agreed upon, after the blasting and excavation took place, and hauled rock, materials and waste from the premises. On July 7, 1983, after the completion of the work, Croy billed Poole a total sum of $6,886.92 for this work less an advance of $1,500.00 paid by Poole to Croy for a net bill of $5,386.92. Said amount was not paid by Poole and Croy filed a Memorandum of Mechanic’s Lien and when payment was not forthcoming instituted this Chancery action to enforce the Mechanic’s Lien. Poole answered by filing a grounds of defense and among other things alleged that the agreement between Croy and Poole was a fixed price agreement in the sum of $1,400.00 and that said amount has been fully paid and that there is an accord and satisfaction. At the same time, Poole cross-claimed alleging that there was a fixed price contract between Croy and Poole to excavate the property and to dig footers for a residential dwelling at a price of $1,400.00 and [236]*236that Poole had paid $1,500.00 pursuant to said contract. Poole further alleged in his cross-claim that Croy did not perform the contract within a reasonable period of time, that such work was done incorrectly and as a direct and approximate result of Croy’s failure to perform properly in accordance with the terms of the contract in a prompt, workmanlike way, Poole suffered damages in the sum of $8,000.00.

The Court finds from the evidence introduced at the trial that the agreement between the parties was that Croy was to excavate the site which would include removal of all undergrowth and install the necessary footers as shown on Poole’s plans. The Court finds that Croy and Poole contemplated that there would be very little removal of soil and rock, and the parties were mutually mistaken in that regard as subsequent events showed, but in any event, any such rock removal and dirt removal was to be an extra and based upon the actual time and material involved and there was no mark up to be charged by Croy in this regard. The Court further finds that since the parties did not contemplate the extensive excavations that were required, they did not contract as to the cost of removing the dirt, rock, and undergrowth from the premises and this too was an extra.

The Court finds that Croy is entitled to recover the cost of all labor and materials connected with the blasting and removal of the dirt, rock and undergrowth from the premises. Plaintiff readily admitted that he was going to charge for the blasting on a straight time and materials basis and there was no mark up for profit and overhead. It is clear to the Court that the parties recognized that the $1,400.00 would not cover the complete job and that this would only cover a portion of the work to be performed by Croy. On June 21, 1983, some 12 days after Croy started his work, Poole made an advance of $1,500.00 to Croy which exceeded the amount of the contract by $100.00 (Plaintiff’s Exhibit H, check signed by Mrs. Poole). There was a notation on the check that it was an "advance on excavation." Poole obviously knew that the $1,500.00 was only a part payment as evidenced by the memorandum, and that there would be additional work billed in connection with the completion of the job.

[237]*237Defendant relies upon Marine Dev. Corp. v. Rodak, 225 Va. 137, 300 S.E.2d 763 (1983), and states that Croy should be allowed to recover the reasonable value of the services performed on a theory of quantum meruit. Marine Dev. reaffirms the theory of quantum meruit as followed in Virginia and as applied by the Supreme Court in Hendrickson v. Meredith, 161 Va. 193, 170 S.E. 602 (1933). In Hendrickson plaintiff was attempting to secure specific performance of an agreement with defendant’s decedent. While the Supreme Court held that the agreement was unenforceable as being too vague and indefinite it further found that plaintiff had rendered valuable services and was entitled to reasonable compensation based upon the reasonable value of the services performed by her, less any compensation already received, whether in money or otherwise. Thus, though the contract between plaintiff and defendant’s decedent was void, she was entitled to be compensated for services rendered pursuant to the contract; and so in the case at hand, while the parties may have been mistaken as to the extent of the services to be performed by Croy, because neither party realized how much grading and excavation would be required because of the condition of the premises when they viewed it, this cannot defeat Croy’s right to recover. Croy has rendered services, furnished material and labor, and Poole (both husband and wife) have profited therefrom thus they must compensate Croy. As was stated in Marine Dev. at pages 140 and 141:

It is a general rule of law that he who gains the labor ... of another must make reasonable compensation for the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marine Development Corp. v. Rodak
300 S.E.2d 763 (Supreme Court of Virginia, 1983)
Hendrickson v. Meredith
170 S.E. 602 (Supreme Court of Virginia, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
3 Va. Cir. 234, 1984 Va. Cir. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/croy-v-poole-vaccshenandoah-1984.