Crout v. D.E.R. Building Co., Unpublished Decision (11-13-2001)

CourtOhio Court of Appeals
DecidedNovember 13, 2001
DocketCase No. CA2000-12-039.
StatusUnpublished

This text of Crout v. D.E.R. Building Co., Unpublished Decision (11-13-2001) (Crout v. D.E.R. Building Co., Unpublished Decision (11-13-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crout v. D.E.R. Building Co., Unpublished Decision (11-13-2001), (Ohio Ct. App. 2001).

Opinion

OPINION
This case arose from a construction contract that listed as the contracting parties: plaintiff-appellant, Jack Crout d.b.a. MeadowWood Nursing Home, and defendant-appellee, D.E.R. Construction, Inc. ("Construction Company"). Crout appeals the decision of the Brown County Court of Common Pleas to reform the contract and substitute D.E.R. Building Company, Inc. ("Building Company") for Construction Company as the party to the agreement. For the reasons that follow, we affirm the decision of the trial court.

Dale Roe is the president of Building Company. Building Company was incorporated under Ohio law in 1997 to be a general construction business. Roe was also the president of Construction Company, which was also an Ohio corporation engaged in the business of general construction. Construction Company ceased doing business between 1997 and 1998.

Robert Wallace is the architect hired by appellant to design an eighty-six bed expansion of MeadowWood Nursing Home. Wallace solicited a bid for the project from Roe and two other construction companies. Wallace had worked with Roe and Construction Company on past projects.

Roe, using Building Company letterhead, sent Wallace a proposal for the expansion project. Roe later sent a revised proposal on a Building Company proposal form. He signed the proposal "Dale E. Roe, President of D.E.R. Building Company." After Wallace made alterations to the plans, Building Company again sent him a revised quote. Wallace and appellant awarded Building Company the construction contract.

Wallace completed a pre-printed "Standard Form of Agreement between Owner and Contractor" published by the American Institute of Architects. Wallace designated the "Contractor" on the first page of the agreement as "D.E.R. Construction[,] Inc." Although Roe reviewed the pay schedule and the tasks that were part of the contract, he failed to notice that Construction Company rather than Building Company was listed as the contractor. Roe signed the contract above the typed words: "Contractor, Dale Roe, Mr. Dale Roe, President." Although the agreement was technically between appellant and Construction Company, appellant addressed correspondence and made all checks payable to Building Company.

Appellant requested that Roe sign an agreement between appellant and National Bank and Trust Company regarding financing of the project. While reviewing the document, Roe noticed that Construction Company was listed as the contractor. Roe pointed out the error to appellant. Roe corrected the document by crossing out Construction Company and inserting Building Company. Roe initialed the changes and signed the document. Alerted by the error in the financing agreement, Roe reviewed the original agreement prepared by Wallace and found that it also erroneously listed Construction Company as the contractor. Roe notified appellant of the error. However, the parties never amended the original agreement.

At some point during the project, appellant became dissatisfied with Building Company's performance under the construction agreement. Appellant filed a demand for arbitration with the American Arbitration Association against Construction Company alleging a breach of contract. Under Article 4.5.1 of the agreement, the parties agreed to arbitrate any claims arising out of the construction agreement. While the arbitration was pending, appellant filed a complaint against Building Company alleging breach of an oral contract to construct an addition to the nursing home.

Building Company and Roe answered appellant's complaint and then filed a motion to stay proceedings pending arbitration. The trial court denied the motion on the basis that appellant had entered into a construction agreement with Construction Company, not Building Company. In the interim, Construction Company was made a party to the litigation. Building Company later renewed its motion to stay proceedings. The trial court again denied the motion. The trial court found that there had been no change of circumstances or new facts for the court to reconsider the merits of the motion and therefore res judicata and/or waiver applied.

Building Company, Construction Company and Roe (collectively, "appellees") moved the trial court for leave to file counterclaims seeking reformation of the contract. The trial court granted the motion. After conducting a hearing on the matter, the trial court ordered the reformation of the written agreement, substituting Building Company for Construction Company as the party to the agreement with appellant. The trial court concluded that Wallace, as appellant's agent, mistakenly listed Construction Company on the agreement when both parties intended Building Company to be the contractor. Appellant appeals the decision of the trial court and raises one assignment of error as follows:

THE TRIAL COURT ERRED TO THE PREJUDICE OF APPELLANT JACK CROUT IN ALLOWING AND ORDERING REFORMATION OF THE CONSTRUCTION CONTRACT BETWEEN APELLANT AND APPELLEE D.E.R. CONSTRUCTION, INC. SO AS TO SUBSTITUTE D.E.R. BUILDING COMPANY IN PLACE AND IN STEAD [SIC] OF D.E.R. CONSTRUCTION AS THE CONTRACTING PARTY TO THE CONSTRUCTION AGREEMENT.

Appellant's assignment of error raises two distinct issues for review. First, appellant argues that the trial court erred by granting appellees leave to amend their pleadings "because of the doctrines of waiver, resjudicata, and the failure of the party requesting the equitable remedy of reformation to have `clean hands'[.]" Second, appellant challenges the trial court's decision to reform the construction agreement. We will address each issue in turn.

Appellant first challenges the trial court's decision to grant appellees leave to file a counterclaim. Appellant argues that the trial court's denials of Building Company's motions to stay proceedings operates as a bar to grant leave to file a counterclaim because of waiver, estoppel and res judicata. Appellant also contends, without argument, that the trial court should not have granted leave to amend pleadings because appellees have "unclean hands."

The grant or denial of leave to amend a pleading is discretionary.Wilmington Steel Products, Inc. v. Cleveland Elec. Illum. Co. (1991),60 Ohio St.3d 120, 122; see, also, Civ.R. 15(A) ("Leave of court [to amend pleadings] shall be freely given when justice so requires.") When a party fails to assert an available counterclaim in a responsive pleading and the time for amending the pleading as a matter of right under Civ.R. 15 has passed, the trial court may permit the party leave of court to include the counterclaim. Civ.R. 13(F); Josselson v. Josselson (1988), 52 Ohio App.3d 60, 61; Nat'l City Bank v. Fleming (1981),2 Ohio App.3d 50, 54. The trial court is vested with discretion to permit leave of court when "justice requires" or when the party has omitted the counterclaim through oversight, inadvertence or excusable neglect. Id. A reviewing court will not reverse a trial court's decision to grant or deny leave to amend a pleading absent an abuse of discretion. See, e.g., Wilmington Steel Products, Inc. at 122. The term "abuse of discretion" connotes more than an error of law or of judgment; it implies that the court's attitude is unreasonable, arbitrary or unconscionable. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Josselson v. Josselson
557 N.E.2d 835 (Ohio Court of Appeals, 1988)
Pharmacia Hepar, Inc. v. City of Franklin
676 N.E.2d 587 (Ohio Court of Appeals, 1996)
Greenfield v. Aetna Casualty & Surety Co.
61 N.E.2d 226 (Ohio Court of Appeals, 1944)
Crestmont Cleveland Partnership v. Ohio Department of Health
746 N.E.2d 222 (Ohio Court of Appeals, 2000)
Merrill v. City of Hamilton
458 N.E.2d 860 (Ohio Court of Appeals, 1982)
Hartman v. Tillett
89 N.E.2d 613 (Ohio Court of Appeals, 1948)
The Fifth Third Bank v. Simpson
730 N.E.2d 406 (Ohio Court of Appeals, 1999)
State v. Watson
710 N.E.2d 340 (Ohio Court of Appeals, 1998)
Henkle v. Henkle
600 N.E.2d 791 (Ohio Court of Appeals, 1991)
National City Bank v. Fleming
440 N.E.2d 590 (Ohio Court of Appeals, 1981)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Shear v. West American Insurance
464 N.E.2d 545 (Ohio Supreme Court, 1984)
Sandusky Properties v. Aveni
473 N.E.2d 798 (Ohio Supreme Court, 1984)
Reilley v. Richards
632 N.E.2d 507 (Ohio Supreme Court, 1994)
Grava v. Parkman Township
653 N.E.2d 226 (Ohio Supreme Court, 1995)
Ameigh v. Baycliffs Corp.
690 N.E.2d 872 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Crout v. D.E.R. Building Co., Unpublished Decision (11-13-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/crout-v-der-building-co-unpublished-decision-11-13-2001-ohioctapp-2001.