Crossley Construction Corp. v. NCI Building Systems

123 F. App'x 687
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 16, 2005
Docket03-6512, 03-6540
StatusUnpublished
Cited by2 cases

This text of 123 F. App'x 687 (Crossley Construction Corp. v. NCI Building Systems) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crossley Construction Corp. v. NCI Building Systems, 123 F. App'x 687 (6th Cir. 2005).

Opinion

OPINION

GILMAN, Circuit Judge.

Crossley Construction Corporation brought a breach-of-contract action against NCI Building Systems, its supplier of roofing materials. NCI cross-claimed, demanding payment of the balance that it was due plus interest. The district court entered judgment in favor of NCI and ordered Crossley to pay the balance due as well as interest accumulated up to the start of the trial. For the reasons set forth below, we AFFIRM the judgment of the district court with regard to the breach-of-contract claims, but REMAND the case for further consideration of NCI’s cross-claims pertaining to prejudgment interest and attorney fees.

I. BACKGROUND

A. Factual background

Crossley is a general contracting firm based in Knoxville, Tennessee. In January of 1997, Crossley entered into an agreement with the owner of the Grey-stone Lodge in Gatlinburg, Tennessee to construct a new registration building as well as to install new roofs on two existing buildings. Crossle/s original roofing supplier was unable to provide the materials in sufficient time, prompting Crossley to contact NCI, a Houston-based metal supplier.

On February 3, 1997, Crossley’s vice president, Don Crise, sent NCI a purchase order (No. 9703-7A) for various roofing materials. In response, an NCI representative, Daniel Stewart, contacted Crise and informed him that NCI’s standard policy was for NCI to work only from its own contract, and not from a customer’s purchase order. Stewart then sent Crise a proposed contract on NCI’s own form on February 4. Crise returned the form the same day with his signature and, in his own handwriting, a notation reading: “See CCC PO # 9703-7A as being made part of this Agreement by executing this proposal. D.C.” Upon receipt, Stewart called Crise and “again reiterat[ed] that his purchase order was not accepted and [would] not be part of [NIC’s] proposal.” Stewart also forwarded Crise, on February 7, another copy of the same NCI proposal that he had *689 sent to Crise three days earlier. This transmission did not reference Crossley’s purchase order. On February 10, Crise signed and returned NCI’s contract without further revisions.

The subsequent chronology of events is greatly disputed. NCI contends that it timely delivered most of the materials and that any delays were attributed to Crossley’s slowness in specifying the choice of a color for the roofing materials. It further claims that 84% of the roofing panels were delivered to the site by May 8 (the contractual date of delivery) and that the remaining panels were delivered by June 3, which allowed Crossley sufficient time to finish the roof installations by the original completion date of July 3, 1997. Moreover, NCI asserts that it provided roofing panels built to the exact specifications as provided by Crossley, and that it was not informed of any alleged shortages or noncomformities until mid-June.

Crossley, in turn, contests each of these assertions. It argues that NCI provided “all the materials more than three months beyond the delivery deadline in the NCI contract.” Furthermore, it contends that “NCI also materially breached the contract by failing to supply panels that were properly cut to fit the buildings under construction.” Crossley also claims that NCI never delivered a needed set of shop drawings, which were crucial to the timely completion of the project. NCI, for its part, contends that the drawings were properly submitted and received.

On June 2,1997, Crossley informed NCI that it considered NCI to be in breach of the contract and gave notice of an intent to withhold further payment. Two weeks later, on June 19, Crossley sent NCI an ambiguous notice that it anticipated a shortage of panels and trim. On July 11, NCI gave Crossley a notice of default for nonpayment and offered to fabricate more material on the condition that Crossley pay its outstanding balance of approximately $86,000.

B. Procedural background

Crossley responded by filing suit against NCI in federal district court on April 3, 1998, claiming breach of contract and negligent misrepresentation. NCI replied with an answer and counterclaim, denying most of Crossley’s factual assertions and demanding that Crossley pay the full outstanding balance plus interest. In a thorough and detailed opinion, the district court determined that NCI had not breached the contract, and that it was entitled to the unpaid balance due plus interest accumulated up to the commencement of trial. This timely appeal followed.

II. ANALYSIS

A. Standard of review

“Because jurisdiction in this case is based upon diversity of citizenship, state law governs matters of substance while federal law dictates procedural issues. Consequently, we look to [state] law to determine whether the issue of whether there was a material breach of contract is one of fact or law.” In re American Casualty Co., 851 F.2d 794, 798 (6th Cir.1988) (citations omitted). In Tennessee, issues regarding the construction of contracts are questions of law. Doe v. HCA Health Sews, of Tenn., Inc., 46 S.W.3d 191, 196 (Tenn.2001) (“The ascertainment of the intention of the parties to a written contract is a question of law, rather than a question of fact.”). Such questions of law are reviewed de novo. Owens-Illinois, Inc. v. Aetna Cas. & Sur. Co., 990 F.2d 865, 871 (6th Cir.1993). The district court in the present case reached three legal conclusions when it determined (1) that the contract between NCI and Crossley came into existence February 10, 1997 as opposed to February 4, 1997, (2) that NCI did not *690 breach its contractual obligations, and (3) that even if NCI did breach its contractual obligations, it was not liable for consequential damages.

B. The date of the contract

Crossley claims that its contractual relationship with NCI came into existence on February 4,1997, when Crise incorporated Crossley’s purchase order on NCI’s contract form, and not on February 10, 1997, as the district court concluded. In support of this argument, Crossley contends that “it was the intent of the parties to form an agreement using a combination of their respective forms. This contract included Crossley’s standard purchase order form, including the delivery schedule deadlines supported by the clear contract provision that ‘Time is of the Essence.’ ” Crossley also points to the Uniform Commercial Code provision contained in Tenn.Code Ann. § 47-2-207, which states that

(1) A definite and seasonable expression of acceptance or a written confirmation which is sent within a reasonable time operates as an acceptance even though it states terms additional to or different from those offered or agreed upon, unless acceptance is expressly made conditional on assent to the additional or different terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Cincom iOutsource, Inc.
398 B.R. 236 (S.D. Ohio, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
123 F. App'x 687, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crossley-construction-corp-v-nci-building-systems-ca6-2005.