Cross Equipment v. Hyundai Merchant

CourtCourt of Appeals for the Fifth Circuit
DecidedMay 4, 2000
Docket99-30166
StatusUnpublished

This text of Cross Equipment v. Hyundai Merchant (Cross Equipment v. Hyundai Merchant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cross Equipment v. Hyundai Merchant, (5th Cir. 2000).

Opinion

UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT __________________

No. 99-30166 __________________

CROSS EQUIPMENT LTD., WATERMAN SUPPLY CO., INC.,

Plaintiffs-Counter Defendants- Appellees-Cross-Appellants,

versus

HYUNDAI MERCHANT MARINE (AMERICA) INC., HYUNDAI MERCHANT MARINE CO., LTD., HYUNDAI AMERICA SHIPPING AGENCY, TRANSOCEAN TERMINAL OPERATORS INC., In personam,

Defendants-Counter Plaintiffs- Appellants-Cross Appellees. _________________________________________________________________

Appeal from the United States District Court for the Eastern District of Louisiana (97-CV-2569-E) _________________________________________________________________ May 1, 2000

Before BARKSDALE, BENAVIDES, and STEWART, Circuit Judges.

PER CURIAM:*

For this admiralty matter, primarily at issue is whether, and

to what extent, a shipper is liable to a marine terminal operator

for demurrage when: the shipper’s cargo has been offloaded from

the vessel to the operator’s wharf; the shipper and the carrier

dispute, under the bill of lading, responsibility for repairs to

the cargo for offloading by the carrier; as a result, the operator

and carrier refuse to release the cargo to the shipper; the shipper

arrests its cargo; and the carrier and operator assert possessory

* Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. maritime liens against the cargo, continue to refuse to release it,

eventually seize it, and it remains on the wharf, subject to ever

increasing demurrage, until bonded out by the shipper. Also at

issue is whether the costs related to the repairs to the cargo

should be borne by the shipper (necessary to safely offload the

cargo) or by the carrier (offload to be at no cost to shipper). We

AFFIRM.

I.

For its cargo in Thailand, valued in excess of $300,000, Cross

Equipment, Ltd. and Waterman Supply Co., Inc. (Cross), as shipper,

contracted with Hyundai, as carrier, to transport the cargo to New

Orleans, “free in-liner out” (Cross paid loading costs; Hyundai,

unloading costs). Included in the cargo were 12 used winches; each

weighed in excess of 100 tons. The cargo was loaded aboard

Hyundai’s vessel, the M/V CEMRE II. On its bill of lading, Hyundai

did not note any cargo deficiencies. When the vessel arrived in

New Orleans on 6 August 1997, Cross paid Hyundai approximately

$150,000 in freight charges.

The arrival was several days past that scheduled. The vessel

docked at a Port of New Orleans wharf leased by Transocean Terminal

Operators (TTO). Hyundai hired TTO to perform stevedoring.

Originally, Hyundai had contracted for a floating heavy-lift

crane to offload the cargo to a barge. But, because of the

vessel’s late arrival, that crane was not available. As a result,

Hyundai and TTO devised an alternative offloading method using

TTO’s smaller dock-side cranes.

- 2 - As noted, each of the 12 winches in the cargo weighed in

excess of 100 tons. Several were offloaded successfully. But,

when offloading another, one of its vertical lifting pad eyes

broke. The winch fell several inches to the ship’s deck. There

was no damage.

Marine surveyors, hired by Hyundai, inspected the winches and

noted the original pad eyes were one and one-half inches thick;

their replacements, one-half inch. Additionally, some pad eyes

were elongated, and others distorted. The surveyors determined

that, for safe offloading, the lifting pad eyes required repair.

A welding company, hired by Hyundai, repaired/replaced the pad

eyes at a cost of $8,000. While the repairs were being made, the

vessel was delayed in offloading, at a cost to Hyundai of $7,700.

It also incurred approximately $2,300 in standby labor charges.

Offloading was completed on 9 August 1997, three days after

the vessel’s arrival. Therefore, the 30 days of allowed free time

on TTO’s wharf began on 10 August. (No wharf demurrage accumulates

during free time.)

Cross sought possession of its cargo. TTO would not release

it without authorization from Hyundai. And, Hyundai refused

release until Cross paid the repair cost.

Upon expiration of the wharf free time in September 1997,

demurrage began accruing. According to TTO’s tariff, demurrage,

charged per ton per day, was $0.20 for the first seven days; $0.60

for the next seven; and $1.50 for each day thereafter. Demurrage

- 3 - finally reached approximately $216,000, far in excess of the $8,000

repair cost. (Again, each winch weighed in excess of 100 tons.)

Meanwhile, in federal district court on 15 August 1997, Cross

had filed an in personam action against Hyundai and TTO for breach

of maritime contract, and also sought possession of its cargo from

each of them. Pursuant to FED. R. CIV. P. Supplemental Rules For

Certain Admiralty and Maritime Claims D, and in order to gain in

rem jurisdiction, Cross had the cargo arrested. Cross appointed

TTO alternate custodian.

On 5 September, Hyundai and TTO answered, as well as

counterclaiming for the costs related to the repairs. In addition,

they asserted a possessory maritime cargo lien.

The counterclaim was amended on 9 October to add TTO’s

demurrage claim and seek the cargo’s arrest. A week later, Hyundai

and TTO received an order for that purpose. (As discussed infra,

the warrant was not served until 5 December, when Cross released

its 15 August warrant.)

On cross-motions for summary judgment by Cross and Hyundai,

the district court, on 14 November, held Cross liable to Hyundai

for the repair cost. It deferred ruling on the other costs related

to the repairs, and ordered the cargo released, except for that

necessary to secure Hyundai’s lien.

The record does not reflect whether Cross then sought release

of a portion of the cargo and/or whether Hyundai, TTO, or both

refused, such as by claiming the entire cargo was required to

secure their claims. Cross moved to set bond; but that motion was

- 4 - later denied as moot because, before the court ruled on it, Cross

posted bond for the amount claimed by TTO and Hyundai.

On 5 December, Cross released the cargo from arrest. As

noted, Hyundai and TTO then had the cargo arrested. Five days

later, Cross posted bond. It obtained possession of its cargo on

15 December.

In March 1998, the district court granted partial summary

judgment to TTO, holding Cross liable for demurrage. The court

deferred the amount due to the bench trial. (TTO sought

approximately $216,000, based on the charges discussed supra.)

At trial in October 1998, the district court found that “both

sides of the dispute adopted an intractable position”. It held

Cross liable for the other costs related to the repairs. (Earlier,

as discussed, Cross had been held liable for the repair cost.)

And, it held TTO and Hyundai, as well as Cross, had failed to

mitigate damages. In this regard, it ruled that TTO and Hyundai

should have detained only two of the 12 winches.

Therefore, based in part on equitable principles, judgment for

approximately $36,000 was entered against Cross for the demurrage,

two-twelfths of the amount sought. This was in addition to costs

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Cross Equipment v. Hyundai Merchant, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cross-equipment-v-hyundai-merchant-ca5-2000.