Cross Equipment v. Hyundai Merchant

Court of Appeals for the Fifth Circuit·Decided May 4, 2000·No. 99-30166·Unpublished

Opinion

UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

No. 99-30166

CROSS EQUIPMENT LTD., WATERMAN SUPPLY CO., INC.,

Plaintiffs-Counter Defendants-

Appellees-Cross-Appellants,

versus

HYUNDAI MERCHANT MARINE (AMERICA) INC., HYUNDAI MERCHANT MARINE CO., LTD., HYUNDAI AMERICA SHIPPING AGENCY, TRANSOCEAN TERMINAL OPERATORS INC., In personam,

Defendants-Counter Plaintiffs-

Appellants-Cross Appellees.

Appeal from the United States District Court for the Eastern District of Louisiana (97-CV-2569-E)

May 1, 2000

Before BARKSDALE, BENAVIDES, and STEWART, Circuit Judges. PER CURIAM:* For this admiralty matter, primarily at issue is whether, and to what extent, a shipper is liable to a marine terminal operator for demurrage when: the shipper’s cargo has been offloaded from the vessel to the operator’s wharf; the shipper and the carrier dispute, under the bill of lading, responsibility for repairs to the cargo for offloading by the carrier; as a result, the operator and carrier refuse to release the cargo to the shipper; the shipper arrests its cargo; and the carrier and operator assert possessory

*

Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.

maritime liens against the cargo, continue to refuse to release it, eventually seize it, and it remains on the wharf, subject to ever increasing demurrage, until bonded out by the shipper. Also at issue is whether the costs related to the repairs to the cargo should be borne by the shipper (necessary to safely offload the cargo) or by the carrier (offload to be at no cost to shipper). We AFFIRM.

I.

For its cargo in Thailand, valued in excess of $300,000, Cross Equipment, Ltd. and Waterman Supply Co., Inc. (Cross), as shipper, contracted with Hyundai, as carrier, to transport the cargo to New Orleans, “free in-liner out” (Cross paid loading costs; Hyundai, unloading costs). Included in the cargo were 12 used winches; each weighed in excess of 100 tons. The cargo was loaded aboard Hyundai’s vessel, the M/V CEMRE II. On its bill of lading, Hyundai did not note any cargo deficiencies. When the vessel arrived in New Orleans on 6 August 1997, Cross paid Hyundai approximately $150,000 in freight charges.

The arrival was several days past that scheduled. The vessel docked at a Port of New Orleans wharf leased by Transocean Terminal Operators (TTO). Hyundai hired TTO to perform stevedoring.

Originally, Hyundai had contracted for a floating heavy-lift crane to offload the cargo to a barge. But, because of the vessel’s late arrival, that crane was not available. As a result, Hyundai and TTO devised an alternative offloading method using TTO’s smaller dock-side cranes.

As noted, each of the 12 winches in the cargo weighed in excess of 100 tons. Several were offloaded successfully. But, when offloading another, one of its vertical lifting pad eyes broke. The winch fell several inches to the ship’s deck. There was no damage.

Marine surveyors, hired by Hyundai, inspected the winches and noted the original pad eyes were one and one-half inches thick; their replacements, one-half inch. Additionally, some pad eyes were elongated, and others distorted. The surveyors determined that, for safe offloading, the lifting pad eyes required repair.

A welding company, hired by Hyundai, repaired/replaced the pad eyes at a cost of $8,000. While the repairs were being made, the vessel was delayed in offloading, at a cost to Hyundai of $7,700. It also incurred approximately $2,300 in standby labor charges.

Offloading was completed on 9 August 1997, three days after the vessel’s arrival. Therefore, the 30 days of allowed free time on TTO’s wharf began on 10 August. (No wharf demurrage accumulates during free time.)

Cross sought possession of its cargo. TTO would not release it without authorization from Hyundai. And, Hyundai refused release until Cross paid the repair cost.

Upon expiration of the wharf free time in September 1997, demurrage began accruing. According to TTO’s tariff, demurrage, charged per ton per day, was $0.20 for the first seven days; $0.60 for the next seven; and $1.50 for each day thereafter. Demurrage

finally reached approximately $216,000, far in excess of the $8,000 repair cost. (Again, each winch weighed in excess of 100 tons.)

Meanwhile, in federal district court on 15 August 1997, Cross had filed an in personam action against Hyundai and TTO for breach of maritime contract, and also sought possession of its cargo from each of them. Pursuant to FED. R. CIV. P. Supplemental Rules For Certain Admiralty and Maritime Claims D, and in order to gain in rem jurisdiction, Cross had the cargo arrested. Cross appointed TTO alternate custodian.

On 5 September, Hyundai and TTO answered, as well as counterclaiming for the costs related to the repairs. In addition, they asserted a possessory maritime cargo lien.

The counterclaim was amended on 9 October to add TTO’s demurrage claim and seek the cargo’s arrest. A week later, Hyundai and TTO received an order for that purpose. (As discussed infra, the warrant was not served until 5 December, when Cross released its 15 August warrant.)

On cross-motions for summary judgment by Cross and Hyundai, the district court, on 14 November, held Cross liable to Hyundai for the repair cost. It deferred ruling on the other costs related to the repairs, and ordered the cargo released, except for that necessary to secure Hyundai’s lien.

The record does not reflect whether Cross then sought release of a portion of the cargo and/or whether Hyundai, TTO, or both refused, such as by claiming the entire cargo was required to secure their claims. Cross moved to set bond; but that motion was

later denied as moot because, before the court ruled on it, Cross posted bond for the amount claimed by TTO and Hyundai.

On 5 December, Cross released the cargo from arrest. As noted, Hyundai and TTO then had the cargo arrested. Five days later, Cross posted bond. It obtained possession of its cargo on 15 December.

In March 1998, the district court granted partial summary judgment to TTO, holding Cross liable for demurrage. The court deferred the amount due to the bench trial. (TTO sought approximately $216,000, based on the charges discussed supra.)

At trial in October 1998, the district court found that “both sides of the dispute adopted an intractable position”. It held Cross liable for the other costs related to the repairs. (Earlier, as discussed, Cross had been held liable for the repair cost.) And, it held TTO and Hyundai, as well as Cross, had failed to mitigate damages. In this regard, it ruled that TTO and Hyundai should have detained only two of the 12 winches.

Therefore, based in part on equitable principles, judgment for approximately $36,000 was entered against Cross for the demurrage, two-twelfths of the amount sought. This was in addition to costs related to the repairs, together with interest and reasonable attorney’s fees (fees were awarded in March 1999), as provided for by the bill of lading.

II.

Cross contests liability for the costs related to the repairs.

It maintains that, instead, it should have been awarded its costs

related to breach of the bill of lading and being refused delivery of its cargo.

Cross also contests liability for demurrage. On the other hand, TTO maintains it should have been awarded the $216,000 demanded.

No authority need be cited for our standards of review. The summary judgments are reviewed de novo. For the bench trial, conclusions of law are reviewed de novo and findings of fact for clear error.

A.

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Cross Equipment v. Hyundai Merchant, (5th Cir. 2000).

Cross Equipment v. Hyundai Merchant (Cross Equipment v. Hyundai Merchant) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related