Cross Continent Development, LLC v. Town of Akron

742 F. Supp. 2d 1179, 2010 WL 3805580
CourtDistrict Court, D. Colorado
DecidedSeptember 23, 2010
DocketCivil Action 09-cv-02413-WYD-KMT
StatusPublished
Cited by10 cases

This text of 742 F. Supp. 2d 1179 (Cross Continent Development, LLC v. Town of Akron) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cross Continent Development, LLC v. Town of Akron, 742 F. Supp. 2d 1179, 2010 WL 3805580 (D. Colo. 2010).

Opinion

ORDER

WILEY Y. DANIEL, Chief Judge.

THIS MATTER is before the Court on Defendants’ Motion to Dismiss. Defendants move, pursuant to Fed.R.CivJP. 12(b)(6), to dismiss Plaintiffs claims asserted under federal law for unlawful taking, deprivation of procedural due process and deprivation of substantive due process. If these claims are dismissed, Defendants *1183 also ask the Court to decline to retain supplemental jurisdiction over the remaining state law claims and dismiss them without prejudice.

I. BACKGROUND

This case arises out of a lease between the Town of Akron [“Akron”] and Cross Continent Development, LLC [“CCD”], a private entity. CCD alleges that on January 5, 2009, with no prior warning or notice, Akron terminated a 49-year old lease (the “Lease”) with CCD, under which CCD leased property adjacent to the Colorado Plains Regional Airport in Akron.

The Lease states that it may be terminated by a party only upon “written notice” of the existence of a breach and after providing the party alleged to be in breach with, at minimum, a one-year opportunity to cure. (Am. Compl., ¶ 19, Ex. A. p. 10.) CCD alleges that in reliance on the Lease, it sought, secured, and entered into agreements with investors and sublessees that would undertake construction and development of the airport facilities. (Id., ¶¶ 17, 21-22.) Pursuant to these agreements, CCD was projected to earn more than $60 million during the Lease term. (Id., ¶ 23.)

Under the Lease, Akron permitted CCD to lease the airport land for a period of 49 years, with five additional ten-year extension options. (Am. Compl., ¶ 15.) In turn, CCD was obligated to develop the leased land. (Id., ¶ 16.) CCD’s development responsibilities under the Lease included preparation of a plan for development of the leased land, to be completed no later than December 31, 2008. (Id., ¶ 16.)

In November 2008, CCD alleges it fulfilled its obligation under the Lease by presenting to Akron a comprehensive development plan that incorporated Akron’s previous suggestions and corrections. (Am. Compl., ¶ 20.) The development plan allegedly satisfied all required elements under the Lease. (Id.) Despite informing CCD that it would provide additional feedback after the November 2008 presentation, Akron failed to do so. (Id.) Instead, it terminated the Lease on January 5, 2009, without providing CCD written notice or a one-year opportunity to cure as required.

II. ANALYSIS

A. Standard of Review

The Federal Rules of Civil Procedure provide that a defendant may move to dismiss a claim for “failure to state a claim upon which relief can be granted.” Fed. R.Civ.P. 12(b)(6). “The court’s function on a Rule 12(b)(6) motion is not to weigh potential evidence that the parties might present at trial, but to assess whether the plaintiffs complaint alone is legally sufficient to state a claim for which relief may be granted.” Dubbs v. Head Start, Inc., 336 F.3d 1194, 1201 (10th Cir.2003) (citations and quotation marks omitted). “A court reviewing the sufficiency of a complaint presumes all of plaintiffs factual allegations are true and construes them in the light most favorable to the plaintiff.” Hall v. Bellmon, 935 F.2d 1106, 1109 (10th Cir.1991).

“To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’ ” Ashcroft v. Iqbal, — U.S. -, 129 S.Ct. 1937, 1949, 173 L.Ed.2d 868 (2009). Plausibility, in the context of a motion to dismiss, means that the plaintiff pled facts which allow “the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Id. If the allegations state a plausible claim for relief, the claim survives the motion to dismiss. Id. at 1950.

*1184 B. Whether Dismissal is Appropriate as to the Federal Claims

1. Unlawful Taking Claim

Defendants assert that the complaint fails to state a claim for an unlawful taking. They argue that a taking claim is only appropriate in connection with a government contract if the plaintiff is foreclosed from bringing a state breach of contract claim. Here, Defendants assert that the rights between the parties were created by contract under the Lease, and that the contract rights are wholly intact. Accordingly, it is argued that Akron has not deprived Plaintiff of the full range of remedies under a breach of contract claim.

Turning to my analysis, it is well established that a plaintiff who is suing in connection with a government contract “is entitled to a takings remedy only if it is foreclosed from bringing a breach of contract action, i.e., if its contract rights have been ‘taken’.” Pi Electronics Corp. v. United, States, 55 Fed.Cl. 279, 285 (Fed. C1.2003); Hughes Communications v. United States, 271 F.3d 1060, 1070 (Fed. C1.2002); Castle v. United States, 301 F.3d 1328, 1342 (Fed.Cir.2002). In other words, “[a] takings claim has limited applicability when a claimant has a viable breach remedy.” Pi Electronics, 55 Fed. Cl. at 285. “This is so because ‘[virtually every contract operates, not as a guarantee of particular future conduct, but as an assumption of liability in the event of nonperformance.’ ” Id.

As explained in Hughes, “[t]akings claims rarely rise under government contracts because the Government acts in its commercial or proprietary capacity in entering contracts, rather than its sovereign capacity. Hughes, 271 F.3d at 1070.” “Accordingly, remedies arise from the contracts themselves, rather than from the constitutional protection of property rights.” Id. The court also noted that if the government’s breach in that case of a launch services agreement with NASA was a taking under the Fifth Amendment, “then nearly all government contract breaches would give rise to compensation under the Fifth Amendment.” Id. It stated that the “court’s predecessor has cautioned against commingling takings compensation and contract damages.” Id. The court then held that the government was acting in its proprietary capacity when it entered the contract as it “ ‘obtained certain rights and incurred certain responsibilities as did plaintiffs.’ ” Id. Accordingly, Hughes could only assert a breach of contract claim.

None of the above cases, however, dealt with leases involving real property. “As a general proposition, a leasehold interest is property, the taking of which entitles the leaseholder to just compensation for value thereof.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Appeal of Port City Air Leasing, Inc.
2024 N.H. 71 (Supreme Court of New Hampshire, 2024)
Shougar v. Jaddou
D. Colorado, 2024
211 Eighth, LLC v. Town of Carbondale
922 F. Supp. 2d 1174 (D. Colorado, 2013)
Building 11 Investors LLC v. City of Seattle
912 F. Supp. 2d 972 (W.D. Washington, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
742 F. Supp. 2d 1179, 2010 WL 3805580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cross-continent-development-llc-v-town-of-akron-cod-2010.