Crosby Development Corp. v. Laker

630 So. 2d 308, 1993 La. App. LEXIS 4067, 1993 WL 535575
CourtLouisiana Court of Appeal
DecidedDecember 28, 1993
DocketNo. 93-CA-587
StatusPublished

This text of 630 So. 2d 308 (Crosby Development Corp. v. Laker) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crosby Development Corp. v. Laker, 630 So. 2d 308, 1993 La. App. LEXIS 4067, 1993 WL 535575 (La. Ct. App. 1993).

Opinion

DUFRESNE, Judge.

This is an appeal by Yvonne and Leonard Laker, defendants-appellants, from a judgment forfeiting their $33,500.00 deposit on a condominium which they contracted to have built, but upon its completion, refused to purchase. The Lakers asserted at trial that Crosby Development Corporation, (CDC) plaintiff-appellee, did not construct the residence according to the original contract specifications, and did not deliver timely a merchantable title. The trial judge rejected both assertions and found instead that the unit was properly built and that there were no defects in the title tendered. He therefore awarded CDC the deposit as stipulated damages, as well as reasonable attorney fees (fixed at $7,500.00) both of which were provided for in the contract in the event of a breach. Because we find neither legal nor manifest factual error in the judgment of the trial court, we affirm that judgment.

The facts are these. DeLimon Place is a townhouse and condominium development which was begun by Crosby Development Corporation (CDC) in the early 1980⅛. By 1985, some 100 units of various styles had been built and sold. In mid-1985, the Lak-ers approached the developer about having a townhouse built, and on June 22, 1985, the parties reached an agreement for construction of a unit at 300 Rue St. Peter. The original contract price was $350,000.00, all in cash, with no prediction on the buyers’ ability to obtain financing, plus the costs of any extras which the Lakers might subsequently request. Completion of the project was to be on or before June 22, 1986, and the act of sale was to be passed before the Lakers’ notary. The contract further provided the standard 60 day extension of the closing date should curative title work be required. It was also agreed that in the event of a breach, the other party could demand either specific performance of the agreement, or payment of stipulated damages of $33,500.00, plus reasonable attorney fees. Finally, the Lakers were required to place with the developer a deposit of $33,500.00.

As to the actual unit to be built, the contract provided that construction was “to be completed similarly to the model unit at 303 Rue St. Ann.” At trial, John Crosby, Jr., president of CDC, explained that the entire DeLimon Place project had been planned so that each lot would have a particular pre-designed type of unit built upon it. The designation of the unit type for 300 Rue St. Peter was “R-l”, while that for 303 Rue St. Ann was “P”. Both types were, however, three-story units laid out in a similar floor plan, except that the “R-l” was 4,450 square feet, while the “P” was only 4,219 square feet. Crosby further explained that the reference in the contract to the model unit at 303 Rue St. Ann was only for purposes of the finish, quality and style of construction, which included such items as paneling, carpets, etc. Mrs. Laker similarly testified that she knew the contract was for an “R-l” model, with certain modifications that she had requested, and indeed an “R-l” plan, with those requested changes drawn in, was attached to the contract.

There was also general agreement that during the year of construction of the unit, and particularly in the latter months, Mrs. Laker was on the premises at least on a weekly basis. Typically she dealt with Lisa Crosby Forshag, a CDC employee who coordinated with the workers stylistic and design change request made by buyers. Ms. For-shag’s testimony, corroborated by copious notes as well as formal change orders signed by Mrs. Laker, established that the project went forward to Mrs. Laker’s general satisfaction up to the last four or five weeks of construction. During that latter time frame, disputes arose as to three aspects of the building, namely 1) the passage between the kitchen and dining room, 2) the color of the stain on the wood ceiling beams in the den, and 3) certain wallpaper in the master bedroom. The Lakers testified at trial that because of these alleged defects they decided not to buy the house, and on Wednesday, June 18, they so informed Harry Crosby, construction superintendent of CDC. Apparently, because the contract expiration date was Sunday, June 22, Crosby notified the Lakers that he would tender title before his own notary on Friday, June 20, at 4:00 P.M. [310]*310The Lakers showed up for this closing, but declined to go through with the sale, ostensibly on the grounds that there were title defects. Thirty-five days later, on July 29, the Lakers’ attorney, Robert G. Creely, wrote to John Crosby, Jr. a letter in which he demanded return of the $33,500.00 deposit and informed CDC unequivocally that the Lakers would not buy the property because they were not satisfied with the quality of the workmanship.

Suit was filed by CDC against the Lakers for damages for breach of the contract, and the Lakers reconvened alleging a breach on the part of CDC. After a bench trial, judgment was rendered in favor of CDC for the $33,500.00 deposit plus $7,500 in attorney fees. The Lakers now appeal, alleging here, as they did at trial, that the house was improperly constructed and that the title was defective.

As to the question of proper construction of the house, the trial judge found that it was properly built, and further noted that the developer had gone to great lengths to incorporate all post-contractual modifications requested by the Lakers. Those being factual determinations, the issue before this court is therefore whether these findings are manifestly erroneous, Rosell v. ESCO, 549 So.2d 840 (La.1989).

As briefly mentioned above, in the later stages of construction, the Lakers raised questions about the kitchen passage, the col- or of the beams and certain wallpaper. Mr. Laker testified at trial that there were also difficulties with warping in some of the floor underlayments, as well as various other punch-list type items. However, Harry Crosby stated that on June 18, when Mr. Laker informed him that the house was unacceptable, he only mentioned the passage, the beams and the wallpaper.

Of these three matters, Mrs. Laker admitted at trial that the wallpaper was not in fact upside down' as she had previously thought, and that she did not consider that a problem by June 20.

As to the stain on the ceiling beams in the den, there was conflicting testimony. Mrs. Laker stated that the beams were too dark and red for the other light oak panelling. She further said that when she complained in May about the color, she was sent a sample of wood with a different stain which Harry Crosby said could be applied to lighten the beams. She further stated that she found this stain too green and so notified Crosby, after which time he made no further effort to correct the problem. Lisa Forshag, the CDC representative, testified to the contrary that Mrs. Laker never got back in touch with her one way or the other about whether the lighter stain would be acceptable. She also produced a page of notes, identified as having been contemporaneously made, which showed that she had telephoned on June 12, 13, 16 and 17 to inquire about the light stain, and on each occasion was told by Mrs. Laker that she had not decided yet. Harry Crosby corroborated Ms. Forshag’s version of these events. Finally, John Crosby, Jr., in his letter of June 18, 1986, unambiguously reiterated his offer to re-do the beams to the Lakers’ satisfaction and at no additional costs.

Considering the above evidence, it is obvious that the trial judge credited the testimony of Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rabin v. Blazas
537 So. 2d 221 (Louisiana Court of Appeal, 1988)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Taylor v. Roy
499 So. 2d 595 (Louisiana Court of Appeal, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
630 So. 2d 308, 1993 La. App. LEXIS 4067, 1993 WL 535575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crosby-development-corp-v-laker-lactapp-1993.