Crook v. Mortenson-Neal

727 P.2d 297, 1986 Alas. LEXIS 401
CourtAlaska Supreme Court
DecidedOctober 24, 1986
DocketS-951
StatusPublished
Cited by25 cases

This text of 727 P.2d 297 (Crook v. Mortenson-Neal) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crook v. Mortenson-Neal, 727 P.2d 297, 1986 Alas. LEXIS 401 (Ala. 1986).

Opinion

OPINION

BURKE, Justice.

NGC Investment and Development, Inc., d/b/a Window Supply Co., three of its shareholders and its bonding company (hereafter referred to collectively as NGC) appeal from a superior court judgment awarding plaintiff Mortonson-Neal Joint Venture (M-N) $39,745 on M-N's action to enforce NGC’s subcontract bid on glass, windows, and doors for a hospital in Homer. The court ruled that the doctrine of promissory estoppel required enforcement of NGC’s bid. M-N was also awarded $15,000 in attorney’s fees, an award which exceeded the Civil Rule 82(a) schedule and represented 80% of M-N’s actual fees. *299 NGC appeals from the underlying judgment, the personal judgment against one of its shareholders on his purported guarantee, the award of consequential damages for delay, several evidentiary rulings, and the award of attorney’s fees. We affirm.

The events underlying the parties’ dispute all occurred in 1983. On May 5, NGC phoned in a subcontract bid to provide windows, doors, glass, and aluminum storefront for M-N. NGC bid on four sections of the general contract for an addition to a Homer hospital. These four sections each stated that the “CONTRACT REQUIREMENTS of the General Conditions, the Supplementary Conditions and Division 1 apply to all work in this section.” The general conditions specifically applied to all subcontracts and made the subcontractors directly accountable to the owner for any performance failures. Both the general conditions and the specific requirements of the four subcontract sections required warranties on parts and labor. The general conditions also required written approval of the architect before the owner would accept substitute products.

The owner awarded M-N the general contract late that afternoon. M-N promptly notified NGC that NGC was low bidder on the four subcontracts. M-N wanted to complete the project ahead of the architect’s schedule. It needed the glass work completed before winter in order to enclose the building. Since designing and manufacturing windows takes considerable time, M-N asked NGC to start work immediately on the shop drawings. M-N also asked NGC to confirm its bid in writing. On May 19, NGC sent M-N its confirmation; NGC’s form guaranteed that its work would meet contract specifications.

By the middle of June, M-N had received nothing from NGC since its bid confirmation. On June 14, M-N again telephoned NGC and asked it to submit its plans. NGC responded that it first needed either a notice to proceed or a contract from M-N. That afternoon, M-N sent out a letter to NGC specifically stating that NGC was low bidder and that M-N intended to employ NGC as subcontractor. The letter said, “This is notice that we would like you to proceed in an expeditious manner with the shop drawings required in your portion of the project.”

Between the middle of June and the end of July, M-N and NGC communicated several times about the status of the shop drawings and the written subcontract. NGC finally sent M-N shop drawings for doors and storefront on July 29. The submitted drawings contemplated use of unapproved substitute supplies. On September 16, M-N notified NGC that the architect had rejected the drawings.

Throughout the summer, the parties had communicated regularly about problems with the shop drawings for the windows. The formal schedule agreed to in August required window installation by the end of November. Yet by September 13, NGC had submitted only a window manufacturer’s catalog. Although NGC assured M-N as late as September 14 that it would expedite the window delays, it never sent M-N any window shop drawings.

Meanwhile, the parties were negotiating a final, written contract. In late July or early August, M-N sent NGC a form subcontract. That form required NGC to post a bond paid for by M-N at M-N’s own expense. In addition to the bonding requirement, the written subcontract contained other matters “not addressed in the bid, bid confirmation letter of intent or project.” These included provisions on delays, payments, indemnity, lien waivers, change orders, and termination takeover. On August 19, M-N received the subcontract signed but with the bonding requirement deleted. NGC did not want its limited bonding capacity tied up with such a small project. NGC did not object, however, to any of the other provisions.

M-N never signed the contract executed by NGC with the bond requirement deleted. Instead, it proposed that NGC’s principal shareholders personally guarantee NGC’s performance. The phone logs of an M-N manager indicate that NGC’s accountant told him that each of NGC’s principal own *300 ers would personally sign the contract. The accountant, however, denied that she had reported the owners’ agreement; rather, she testified that only one of them, R.J. Braunschweig, had agreed to guarantee NGC’s performance. (George Crook, the named party in this action, and Lou Braun-schweig are the other NGC owners). No one disputes that R.J. Braunschweig expressly told the M-N manager that he would guarantee NGC’s performance.

On September 1, M-N sent NGC a revised contract, with the bond requirement deleted, but with space for the signatures of NGC’s three principal shareholders: R.J. Braunschweig, his brother, Lou, and George Crook. Only R.J. Braunschweig signed in his capacity as an individual. Accompanying the executed subcontract, NGC submitted an addendum limiting its warranty on the storefront and proposing to substitute a different type of window. NGC signed this contract on September 20. M-N received it on September 22 but never signed it.

On September 20, M-N expressed its strong concern over NGC’s delays. On September 21, just one day after signing the agreement, NGC repudiated it by letter. Prior to receiving the repudiation, however, M-N had telegrammed a warning to NGC of the consequences of further delay. On September 22, M-N sent an employee to meet with NGC. NGC did not meet with the M-N employee and did not inform him of its repudiation. On September 27, M-N’s Homer office received the repudiation. Two days later, M-N wrote NGC to announce its search for a new subcontractor and to request NGC to mitigate damages. M-N then hired a substitute contractor at higher cost. Delays caused by the late substitution forced M-N to install temporary closures to protect the site from winter weather.

M-N sued NGC and its owners on November 8, 1983. M-N moved for summary judgment in September, 1984. The trial court ruled that one fact issue remained for trial: whether justice required enforcement of NGC’s promise under the doctrine of promissory estoppel. To encourage settlement and avoid a trial on one narrow issue, the court noted its intent to award fees in excess of the Rule 82(a) schedule. After a four day trial before the court, Judge Shorten entered a judgment of $39,745 in MN’s favor. He found that NGC’s defense lacked merit and bordered on bad faith. He awarded M-N $15,337.60 in attorney’s fees, representing 80% of M-N’s actual attorney’s expenses. NGC then appealed.

A. NGC Estopped from Revoking its Bid

In its final judgment, the superior court ruled:

17. The elements necessary for imposition of promissory estoppel have been proven. NGC made promises to Plaintiff which Defendants NGC and R.J. Braun-schweig reasonably have expected to induce substantial action by Plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keven Windel and Marlene Windel v. Matanuska-Susitna Borough
496 P.3d 392 (Alaska Supreme Court, 2021)
Black v. Whitestone Estates Condo. Homeowners' Ass'n
446 P.3d 786 (Alaska Supreme Court, 2019)
Keenan v. Meyer
424 P.3d 351 (Alaska Supreme Court, 2018)
Jim Crawford v. Emilio Avila, M.D.
Alaska Supreme Court, 2015
Greene v. Tinker
332 P.3d 21 (Alaska Supreme Court, 2014)
Safar v. Wells Fargo Bank, N.A.
254 P.3d 1112 (Alaska Supreme Court, 2011)
Vaska v. State
135 P.3d 1011 (Alaska Supreme Court, 2006)
Adams v. Adams
131 P.3d 464 (Alaska Supreme Court, 2006)
Brady v. State
965 P.2d 1 (Alaska Supreme Court, 1998)
Reichenbach v. Watco Inc.
Montana Supreme Court, 1997
Municipality of Anchorage v. Gentile
922 P.2d 248 (Alaska Supreme Court, 1996)
Stone v. International Marine Carriers, Inc.
918 P.2d 551 (Alaska Supreme Court, 1996)
Exxon Corp. v. Burglin
42 F.3d 948 (Fifth Circuit, 1995)
Eufemio v. Kodiak Island Hospital
837 P.2d 95 (Alaska Supreme Court, 1992)
Van Dort v. Culliton
797 P.2d 642 (Alaska Supreme Court, 1990)
Van Biene v. ERA Helicopters, Inc.
779 P.2d 315 (Alaska Supreme Court, 1989)
Day v. Moore
771 P.2d 436 (Alaska Supreme Court, 1989)
Patrick v. Lynden Transport, Inc.
765 P.2d 1375 (Alaska Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
727 P.2d 297, 1986 Alas. LEXIS 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crook-v-mortenson-neal-alaska-1986.