Crook v. Ford

229 N.W. 587, 249 Mich. 500, 1930 Mich. LEXIS 736
CourtMichigan Supreme Court
DecidedMarch 6, 1930
DocketDocket No. 42, Calendar No. 34,682.
StatusPublished
Cited by12 cases

This text of 229 N.W. 587 (Crook v. Ford) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crook v. Ford, 229 N.W. 587, 249 Mich. 500, 1930 Mich. LEXIS 736 (Mich. 1930).

Opinion

Potter, J.

Plaintiffs, vendees of city lots in Detroit, were desirous of having built on one of them an income bungalow. Defendants were to acquire title to one of plaintiffs ’ lots on which was to be erected under a verbal contract with defendants a building partially complete, the second story of which was to be finished by plaintiffs. This verbal agreement was made in March, 1926, and defendants were to fully perform their part of the contract by June 5, 1926.'

After the house was up, and according to defendants fully completed on their part, a written land contract was entered into between plaintiffs and defendants, whereby plaintiffs again became vendees of the lot, in May, 1926, which land contract was dated back to March 5,1926. The land contract in part confirmed the terms of the verbal contract as to plaintiffs finishing the second story of the house. It provided:

“All the inside finish on the second floor including lathing, plastering, plumbing, wiring, electric fixtures, painting, decorating, lighting fixtures, labor, inside carpenter finish and all work necessary to complete the second floor ready for occupancy is to be completed and paid for by the purchaser, for which credit has been given on down payment with interest upon interest overdue hereon from maturity *502 to date of payment, at the rate of seven per cent, per annum. ’ ’

Plaintiffs entered into possession. They claim the foundations of the house were not constructed in a workmanlike manner, though so represented to them by defendants, and that by reason thereof it settled, the cellar walls cracked, the basement floor cracked and settled, the plaster on the walls and ceilings cracked, the paper on the walls cracked, the floors took on undulating curves, the doors would not open and close, the house sank in the middle, the furnace tipped over, and defendants, after plaintiffs ’ tenants occupied the house, entered the premises, jacked up the house and put new foundations under the center and sought to repair it, making such a mess that plaintiffs’ tenants moved out, whereupon plaintiffs refused, because of the condition of the building, to pay the monthly payments due on the land contract, and were subsequently formally ejected by summary proceedings before a circuit court commissioner. Plaintiffs, after such summary proceedings were instituted by defendants to recover possession of the premises, filed a bill in equity praying that the verbal agreement between the parties as to the building of the house be decreed to be an integral part of the contract for the purchase of the property by plaintiffs from defendants; that defendants be decreed to perform such revised contract; that the declaration of foreclosure of said land contract by defendants be decreed null and void, and if the court should find the construction of the house as agreed on has become impracticable by the acts of defendants, the land contract be rescinded and defendants be decreed to pay plaintiffs the full amount plaintiffs have expended by virtue of the contract; that defendants be restrained from further prosecuting the suit to *503 recover possession of the premises before the circuit court commissioner of Wayne county, and for other relief.

Upon the filing of this bill, and without giving the statutory bond, an injunction was issued; defendants answered, and on April 25, 1927, the case was ordered transferred to the law side of the court. Subsequently a declaration was filed by plaintiffs against defendants, consisting of three counts. January 9, 1929, the case came on for trial before the court and a jury and resulted in a verdict of $1,000 for plaintiffs. Defendants bring error. The principal question raised by defendants’ several assignments of error is that there was no evidence to sustain the plaintiffs ’ claim of fraud. The court treated the contract as rescinded by plaintiffs. Plaintiffs introduced proof tending to show they expended $1,211.71 in the completion of the second story of the building and also introduced proof tending to show that while defendants admitted prior to the making of the land contract the house was not as it should be, they said they would fix it. Defendants had an assignment of other property of plaintiffs which they threatened to take unless the land contract was signed. They claimed defendants represented the house was complete, whereas it had no proper foundations, and by reason thereof the walls cracked, the basement floors cracked, the house was out of plumb and had to be jacked up, and that therefore the house, which included its foundations, was not completed at the time the contract was entered into as plaintiffs were induced to believe it was. They claim they knew before they entered into the contract that it had sunk, but had been jacked up and the foundations strengthened, but they now claim that this change in the foundations was of no *504 particular value, did not carry out the contract, did not make the foundation sufficient, and was not done in a workmanlike manner, and that the defendants did not disclose to the plaintiffs the cause of the trouble, and that by reason of the failure of the defendants to complete the house, including the foundations, as they agreed to do, the floors became wavy; there is a low spot in one corner of the room, the basement floor cracked, the cement blocks constituting the cellar walls cracked; there is a belt in the center of the basement; the furnace fell down, the sub-flooring was cut through by the defendants so as to allow one side of the house to settle without carrying down the other, the paper on the walls was cracked, and the house was not in substantial compliance with the contract; that plaintiffs believed and relied upon the representations upon the part of the defendants that they would build the house in a good and workmanlike manner, and that in reliance upon such belief induced by defendants, they expended $1,211.71. Considerable testimony was introduced bearing upon when the plaintiffs had knowledge of the defective condition of the house and when the house started to sink; one of defendants testified that he noticed the apparent sinking of the foundations a couple of days after the stanchions to support the superstructure were placed in the cellar, and at another time testifying that it started to sink after the plaster was put on the second floor. It is claimed by defendants that, though they made all the promises claimed by plaintiffs, their violation amounts only to a breach of agreement, and cannot be considered as the basis of fraud.

It is a general rule that the breach of a promise does not constitute fraud; but the mere fact that statements relate to the future will not preclude *505 liability for fraud if the statements were intended to be, and were accepted as, representations of fact, and involved matters peculiarly within the knowledge of the speaker. 26 C. J. p. 1090. Promissory statements were allowed to be shown as the basis of fraud in McDonald v. Smith, 139 Mich. 211.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DBI Investments, LLC v. Paul Blavin
617 F. App'x 374 (Sixth Circuit, 2015)
Johnson v. Wausau Insurance
769 N.W.2d 755 (Michigan Court of Appeals, 2009)
Cummins v. Robinson Township
770 N.W.2d 421 (Michigan Court of Appeals, 2009)
Cooper v. Auto Club Ins. Ass'n
751 N.W.2d 443 (Michigan Supreme Court, 2008)
Foreman v. Foreman
701 N.W.2d 167 (Michigan Court of Appeals, 2005)
Gershman v. Engelstad
160 N.W.2d 80 (North Dakota Supreme Court, 1968)
Holland v. Lentz
397 P.2d 787 (Oregon Supreme Court, 1964)
Zaino v. North Woodward Construction Co.
95 N.W.2d 33 (Michigan Supreme Court, 1959)
Groening v. Opsata
34 N.W.2d 560 (Michigan Supreme Court, 1948)
Claus v. Farmers & Stockgrowers State Bank
63 P.2d 781 (Wyoming Supreme Court, 1936)
Sluss v. Brown-Crummer Investment Co.
53 P.2d 900 (Supreme Court of Kansas, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
229 N.W. 587, 249 Mich. 500, 1930 Mich. LEXIS 736, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crook-v-ford-mich-1930.