Cronan v. Stutsman

151 S.W. 166, 168 Mo. App. 46, 1912 Mo. App. LEXIS 406
CourtMissouri Court of Appeals
DecidedNovember 12, 1912
StatusPublished
Cited by4 cases

This text of 151 S.W. 166 (Cronan v. Stutsman) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cronan v. Stutsman, 151 S.W. 166, 168 Mo. App. 46, 1912 Mo. App. LEXIS 406 (Mo. Ct. App. 1912).

Opinion

REYNOLDS, P. J.

Plaintiff and defendants, the latter under the name of Southeast Missouri Cypress Company, were engaged in the business of cutting logs and piles from lands in Pemiscot county and placing the malong the railroad at different points for shipment, the principal shipping point of defendants being at Clay' Root, a station on what is known as the St. Louis & Gulf Railroad. Prior to February 27, 1908> having had numerous dealings together growing out of this business, according to the averments of the pe[49]*49tition, a dispute arose between the parties over them, and defendants instituted one and threatened other actions against plaintiff. These actions pending or threatened, on February 27, 1908, as is averred and admitted, the parties compromised and settled all the matters in dispute between them up-to that date and entered into a written contra'ct, the execution of which is admitted. In and by that contract defendants agreed, among other things, to float to Olay Root all the oak piles in controversy, these piles to be found in water sufficient to float them to the bayou at the west end of the land on which the timber was cut; defendants, to float, skid and load these piles on cars at Clay Root without cost- to plaintiff. Defendants agreed that “from the total amount of indebtedness determined by the inspecting of all accounts and notes now at hand, John H. Cronan is to be allowed a reduction of' $550; the Southeast Missouri Cypress Company is to. assist John H. Cronan in borrowing $500, which shall be added to the said John H. Cronan’s indebtedness.’7 Summarizing the remainder of the petition, plaintiff' alleges that after the making of this contract the water was sufficient to float the piles to'the bayou and remained so long enough to float all of these piles; that in order to handle oak piles of the nature and kind covered by the contract between plaintiff and defendants, it takes large and strong machinery and equipment to haul them out of the water and load them on cars; that defendants at that time had such equipment at Clay Root which they were using in loading piles of like nature; that plaintiff had no such equipment, and was wholly unprepared to handle the piles himself,'and was therefore bound to rely solely upon the contract entered into with defendants to handle them and have them placed on cars; that the reasonable market value of the piles was $4411.68; that defendants failed and refused to float the piles except eighty-[50]*50eight pieces of the value of $512,96, and that the remainder, of the value of $3899.02., was wholly lost, to plaintiff’s damage in that sum.

The answer, as summarized by counsel for defendants, is an “admission of contract and general denial; plea of insufficiency of water, and that plaintiff, knowing of the insufficietLcy of water over the piling where they lay, refused to put them in water sufficient / to float them; permitted them to lay- and rot, and the damage, if any, was occasioned by plaintiff’s own negligence. ’ ’

By way of counterclaim the answer further set nut that plaintiff is indebted to defendants in the sum of $314.75 on account accruing after making the contract and judgment is prayed for this amount. No issue on the correctness of this counterclaim is now presented.

At the close of the testimony in the case the jury returned a verdict in favor of plaintiff in the sum of ■$1000, and in favor of defendants on the counterclaim in the sum of $314.75, a balance in favor of plaintiff of $685.25, for which amount judgment went in favor -of plaintiff. Filing a motion for new trial as well as -one in arrest and these being overruled and exceptions duly saved, defendants have perfected their appeal to this court.

Defendants here make four assignments of error. 'First, that the verdict is against the evidence and -against the law under the evidence and could only "have been for nominal damages. Second, that the ■court erred in giving certain instructions for plain-tiff. Third, the court erred in refusing to give certain -'instructions asked by defendants, and fourth, that it .erred in the admission of testimony.

The making of the contract and its terms are admitted. So also it is practically conceded that plaintiff had paid to defendants the $550' of old indebtedness .•and the $500 raised for him by defendants, in all $1050. [51]*51ior the work which defendants were to do in dragging out and loading the piles.

As conceded by learned counsel for appellants, many witnesses swore that on one or more rises the water whs deep enough to float the oak piles, and as many or more witnesses swore that at no time from the making of the contract until the piles spoiled, which was about a year after this contract had been entered into, did the water get high enough to float these piles. It was agreed by all the witnesses that green oak piles with the sap in them would not float and that to float them required “floaters,” that is sticks of light weight timber, such as ash or cypress, to be placed on each side of the oak pile and fastened so as to buoy them. When properly buoyed, the oak piles, said one of the witnesses, could be floated and when floated it would take, say twenty-two inches of water to float an eighteen-inch oak pile. It seems that it was also the custom, in floating this timber, to cut through the swamps and sandy ridges or higher ground to the deeper water, what is called a “float road,” that is, as we understand it, a ditch from which stumps and undergrowth were cleared for the requisite depth, and by means of these “float roads,” the piles were carried through the swamps and ridges that might intervene between the starting point and the deep bayou down which they were to be floated. It was in evidence that by means of “float roads,” the piles could easily have been floated out at different times between the making of the contract and the time when it is alleged that by allowing them to remain they had rotted and become valueless. In their statement before us, counsel for appellants themselves admit that “whether or not the oak piling was ever found in sufficient water to float it, was the question for the jury, and by their verdict they evidently found that it was. ■ Hence we are bound on this appeal by that verdict that there was a breach of the contract.” Counsel then argue that “a breach of [52]*52this contract without any other or further showing would only entitle plaintiff to a verdict for nominal damages.” Herein lies the crux of this appeal and on it are based practically all the assignments of error except the fourth. ' ”

It may he conceded, as claimed by counsel, that where a plaintiff sues for damages and proves that he has been damaged, but fails to give any evidence tending to prove the amount of his damage, he can recover only nominal damage. Furthermore it is beyond doubt, as also urged by counsel, that it is the duty of the party injured by a breach of contract to make reasonable effort to render the injury as light as possible. If he knows of the failure or neglect of the one with whom he has contracted to perform that contract within ample time to do it himself, and fails to do so, he cannot hold the other for a loss by such neglect. [Lawson on Contracts (2 Ed.), sec. 484. See also City of St. Louis v. Brown, 155 Mo. 545, l. c. 564,. 56 S. W. 298.] 'We do not think that the facts in evidence bring defendants within the protection of these rules.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Rose
208 S.E.2d 666 (Supreme Court of North Carolina, 1974)
Citizens National Bank v. Hermsdore
77 A.2d 862 (Supreme Court of New Hampshire, 1951)
American Surety Co. of New York v. Franciscus
127 F.2d 810 (Eighth Circuit, 1942)
Taylor v. Sturm Lumber Co.
111 S.E. 481 (West Virginia Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
151 S.W. 166, 168 Mo. App. 46, 1912 Mo. App. LEXIS 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cronan-v-stutsman-moctapp-1912.