CRMC Bethlehem v. NCES CV-09-344-JL 7/29/10
UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE
CRMC Bethlehem, LLC and Commonwealth Bethlehem Energy, LLC
v. Crvrl No. 1 :09-CV-344- JL Opinion No. 2010 DNH 129 North Country Environmental Services, Inc.
MEMORANDUM ORDER
This case involves the scope of certain rights granted under
a contract between a landfill operator and an energy company
planning to develop a facility to produce electricity from gas
generated by landfill waste. Plaintiff, CRMC Bethlehem (CRMCB)1
entered into a Gas Lease and Easement Agreement ("Gas Lease")
with defendant. North Country Environmental Services (NCES),
granting CRMCB the right to extract gas from NCES's landfill in
Bethlehem, New Hampshire. The lease contains a provision
granting NCES certain rights to review and approve CRMCB's
proposals for a landfill gas energy recovery facility.
'CRMCB is a wholly-owned subsidiary of Commonwealth Resource Management Company (CRMC). Plaintiff Commonwealth Bethlehem Energy (CBE) is a limited liability company wholly-owned by CRMC. It is not a party to the Gas Lease, but has subleased certain rights under the Gas Lease. Between September 2008 and May 2009, CRMCB made a series of
proposals to develop an energy recovery facility at the landfill
which were rejected by NCES. Unable to agree on a plan suitable
to all, the plaintiffs filed suit seeking: (1) a declaratory
judgment that either CRMCB does not reguire NCES's approval for
an energy recovery facility project located entirely within an
area designated as a Landfill Gas Utilization Area ("LGUA") or
that withholding approval was unlawful (Count 1); (2) a
declaratory judgment that NCES does not have the authority to
reject placement of the energy recovery facility on land adjacent
to the landfill owned by the Tucker family (the "Tucker Project")
and if it does, NCES may not withhold such approval (Count 2);
(3) a declaratory judgment that it is not reguired to make
certain "Sublessee Payments" due NCES under the Gas Lease if it
decides to construct the Tucker Project (Count 3); (4) injunctive
relief (Count 4); (5) damages for breach of contract (Count 5);
(6) damages for breach of the implied covenant of good faith and
fair dealing (Count 6); (7) damages under a third party
beneficiary claim by CBE (Count 7); and (8) damages pursuant to a
state Consumer Protection Act claim, see N.H. Rev. Stat. Ann.
358-A, (Count 8). CRMCB now moves for partial summary judgment,
reguesting a determination of liability together with injunctive
and declaratory relief. The court denies the plaintiffs' motion
2 because it cannot conclude that the contract terms at issue are
unambiguous and that the plaintiffs are entitled to judgment as a
matter of law. See Fed. R. Civ. Pro. 56(c) (2); Colonial Life
Ins. Co. of Am. v. Elec. Data Sys. Corp., 817 F. Supp. 235, 243
(D.N.H. 1993); see generally, Santoni v. Potter, 369 F.3d 594,
598 (1st Cir. 2004). Further, significant issues of material
fact regarding the parties intent remain in dispute, rendering
summary judgment in favor of the plaintiffs inappropriate at this
time.
First, the court denies the plaintiffs' motion for summary
judgment on Counts 1, 5, 6, and 7. The plaintiffs advance
several arguments based on the meaning and scope of the approval
rights under Section 3.1(b) of the amended Gas Lease and Easement
Agreement. "[T]he general rule is that whether the contract is
clear or ambiguous is a guestion of law. If the contract is
deemed to be ambiguous, then the intention of the parties is a
guestion of fact." Colonial Life Ins. Co. of Am., 817 F. Supp.
at 243 (guotations and ellipses omitted); cf. Daniel v. Hawkeye
Funding, Ltd. P'ship, 150 N.H. 581, 582-83 (2004). Terms are
ambiguous "where the contracting parties reasonably differ as to
[a contract's] meaning," In re Navigation Tech. Corp., 880 F.2d
1491, 1495 (1st Cir. 1989); N.A.P.P. Realty Trust v. CC
Enterprises, 147 N.H. 137, 139 (N.H. 2001), or where the scope of
3 the contract's terms are subject to reasonable interpretation.
C f . N.A.P.P. Realty Trust 147 N.H. at 139. If the court
determines that the contract terms are ambiguous, then such
"ambiguity presents a genuine issue as to a material fact, which
precludes summary judgment . . . ." Colonial Life Ins. Co. of
Am., 817 F. Supp. at 244.
Neither the meaning nor the scope of the approval rights set
forth in Section 3.1(b) is easily discerned from the plain
language of the Gas Lease. Each party posits reasonable
interpretations of Section 3.1(b) based not only on specific
contract terms, but also in light of each party's valid business
considerations,2 and the language of the provision is not
2In support of its narrow reading of Section 3.1(b), CRMCB contends that it would not have executed the Gas Lease if that section gave NCES broad approval rights. It is a well established principle of contract law that parties are "presumed to be capable of managing [their] own affairs, and the guestion whether [their] bargains are . . . economically efficient or disastrous, is not ordinarily a legitimate subject of judicial inguiry." 11 Richard A. Lord, Williston on Contracts § 31:5 (4th ed. 2010). The fact that a broad interpretation may not be in CRMCB's optimal business interest does not favor its interpretation of the Gas Lease, nor renders the terms of the lease unambiguously favorable to CRMCB. C f . id.; Olbres v. Hampton Co-op. Bank, 142 N.H. 227, 233 (1997) ("[C]ourts cannot make better agreements than the parties themselves have entered into or rewrite contracts merely because they might operate harshly or ineguitably" (guotations omitted)). Further, NCES proffers an egually plausible business reason for a broad interpretation of Section 3.1(b), namely that because it is primarily engaged in the trash disposal business, it wanted to ensure that the conversion of landfill gas (a byproduct of the landfill), would not interfere with their primary operation.
4 sufficiently clear or unambiguous to resolve their differences.
Given this ambiguity, summary judgment in favor of the plaintiffs
on issues concerning the scope of Section 3.1(b) is precluded.
See id.
The plaintiffs' further argument that they are entitled to
summary judgment on Count 1 because "NCES has already approved
the development of the [energy recovery facility] in the LGUA"
when it established the LGUA as part of an amendment to the Gas
Lease likewise fails. Significant issues of fact remain in
dispute regarding the intent of the parties when they established
the LGUA, and whether verbal approvals were given by NCES
employees to use the LGUA for the energy recovery facility.
Further, it is unclear from the terms of the amended Gas Lease
that placement of an energy recovery facility in the LGUA is
subject to the approval provision of Section 3.1(b) and if so,
the extent of NCES's approval power. Each of these issues are
disputed and material, precluding summary judgment.
Summary judgment on Count 2 is similarly denied because the
court cannot conclude, as a matter of law, that Section 3.1(b) of
the Gas Lease does not reguire CRMCB to obtain approval from NCES
Free access — add to your briefcase to read the full text and ask questions with AI
CRMC Bethlehem v. NCES CV-09-344-JL 7/29/10
UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE
CRMC Bethlehem, LLC and Commonwealth Bethlehem Energy, LLC
v. Crvrl No. 1 :09-CV-344- JL Opinion No. 2010 DNH 129 North Country Environmental Services, Inc.
MEMORANDUM ORDER
This case involves the scope of certain rights granted under
a contract between a landfill operator and an energy company
planning to develop a facility to produce electricity from gas
generated by landfill waste. Plaintiff, CRMC Bethlehem (CRMCB)1
entered into a Gas Lease and Easement Agreement ("Gas Lease")
with defendant. North Country Environmental Services (NCES),
granting CRMCB the right to extract gas from NCES's landfill in
Bethlehem, New Hampshire. The lease contains a provision
granting NCES certain rights to review and approve CRMCB's
proposals for a landfill gas energy recovery facility.
'CRMCB is a wholly-owned subsidiary of Commonwealth Resource Management Company (CRMC). Plaintiff Commonwealth Bethlehem Energy (CBE) is a limited liability company wholly-owned by CRMC. It is not a party to the Gas Lease, but has subleased certain rights under the Gas Lease. Between September 2008 and May 2009, CRMCB made a series of
proposals to develop an energy recovery facility at the landfill
which were rejected by NCES. Unable to agree on a plan suitable
to all, the plaintiffs filed suit seeking: (1) a declaratory
judgment that either CRMCB does not reguire NCES's approval for
an energy recovery facility project located entirely within an
area designated as a Landfill Gas Utilization Area ("LGUA") or
that withholding approval was unlawful (Count 1); (2) a
declaratory judgment that NCES does not have the authority to
reject placement of the energy recovery facility on land adjacent
to the landfill owned by the Tucker family (the "Tucker Project")
and if it does, NCES may not withhold such approval (Count 2);
(3) a declaratory judgment that it is not reguired to make
certain "Sublessee Payments" due NCES under the Gas Lease if it
decides to construct the Tucker Project (Count 3); (4) injunctive
relief (Count 4); (5) damages for breach of contract (Count 5);
(6) damages for breach of the implied covenant of good faith and
fair dealing (Count 6); (7) damages under a third party
beneficiary claim by CBE (Count 7); and (8) damages pursuant to a
state Consumer Protection Act claim, see N.H. Rev. Stat. Ann.
358-A, (Count 8). CRMCB now moves for partial summary judgment,
reguesting a determination of liability together with injunctive
and declaratory relief. The court denies the plaintiffs' motion
2 because it cannot conclude that the contract terms at issue are
unambiguous and that the plaintiffs are entitled to judgment as a
matter of law. See Fed. R. Civ. Pro. 56(c) (2); Colonial Life
Ins. Co. of Am. v. Elec. Data Sys. Corp., 817 F. Supp. 235, 243
(D.N.H. 1993); see generally, Santoni v. Potter, 369 F.3d 594,
598 (1st Cir. 2004). Further, significant issues of material
fact regarding the parties intent remain in dispute, rendering
summary judgment in favor of the plaintiffs inappropriate at this
time.
First, the court denies the plaintiffs' motion for summary
judgment on Counts 1, 5, 6, and 7. The plaintiffs advance
several arguments based on the meaning and scope of the approval
rights under Section 3.1(b) of the amended Gas Lease and Easement
Agreement. "[T]he general rule is that whether the contract is
clear or ambiguous is a guestion of law. If the contract is
deemed to be ambiguous, then the intention of the parties is a
guestion of fact." Colonial Life Ins. Co. of Am., 817 F. Supp.
at 243 (guotations and ellipses omitted); cf. Daniel v. Hawkeye
Funding, Ltd. P'ship, 150 N.H. 581, 582-83 (2004). Terms are
ambiguous "where the contracting parties reasonably differ as to
[a contract's] meaning," In re Navigation Tech. Corp., 880 F.2d
1491, 1495 (1st Cir. 1989); N.A.P.P. Realty Trust v. CC
Enterprises, 147 N.H. 137, 139 (N.H. 2001), or where the scope of
3 the contract's terms are subject to reasonable interpretation.
C f . N.A.P.P. Realty Trust 147 N.H. at 139. If the court
determines that the contract terms are ambiguous, then such
"ambiguity presents a genuine issue as to a material fact, which
precludes summary judgment . . . ." Colonial Life Ins. Co. of
Am., 817 F. Supp. at 244.
Neither the meaning nor the scope of the approval rights set
forth in Section 3.1(b) is easily discerned from the plain
language of the Gas Lease. Each party posits reasonable
interpretations of Section 3.1(b) based not only on specific
contract terms, but also in light of each party's valid business
considerations,2 and the language of the provision is not
2In support of its narrow reading of Section 3.1(b), CRMCB contends that it would not have executed the Gas Lease if that section gave NCES broad approval rights. It is a well established principle of contract law that parties are "presumed to be capable of managing [their] own affairs, and the guestion whether [their] bargains are . . . economically efficient or disastrous, is not ordinarily a legitimate subject of judicial inguiry." 11 Richard A. Lord, Williston on Contracts § 31:5 (4th ed. 2010). The fact that a broad interpretation may not be in CRMCB's optimal business interest does not favor its interpretation of the Gas Lease, nor renders the terms of the lease unambiguously favorable to CRMCB. C f . id.; Olbres v. Hampton Co-op. Bank, 142 N.H. 227, 233 (1997) ("[C]ourts cannot make better agreements than the parties themselves have entered into or rewrite contracts merely because they might operate harshly or ineguitably" (guotations omitted)). Further, NCES proffers an egually plausible business reason for a broad interpretation of Section 3.1(b), namely that because it is primarily engaged in the trash disposal business, it wanted to ensure that the conversion of landfill gas (a byproduct of the landfill), would not interfere with their primary operation.
4 sufficiently clear or unambiguous to resolve their differences.
Given this ambiguity, summary judgment in favor of the plaintiffs
on issues concerning the scope of Section 3.1(b) is precluded.
See id.
The plaintiffs' further argument that they are entitled to
summary judgment on Count 1 because "NCES has already approved
the development of the [energy recovery facility] in the LGUA"
when it established the LGUA as part of an amendment to the Gas
Lease likewise fails. Significant issues of fact remain in
dispute regarding the intent of the parties when they established
the LGUA, and whether verbal approvals were given by NCES
employees to use the LGUA for the energy recovery facility.
Further, it is unclear from the terms of the amended Gas Lease
that placement of an energy recovery facility in the LGUA is
subject to the approval provision of Section 3.1(b) and if so,
the extent of NCES's approval power. Each of these issues are
disputed and material, precluding summary judgment.
Summary judgment on Count 2 is similarly denied because the
court cannot conclude, as a matter of law, that Section 3.1(b) of
the Gas Lease does not reguire CRMCB to obtain approval from NCES
in order to construct the Tucker Project. The plaintiffs contend
that because the project does not involve placement of an energy
recovery facility in the landfill or landfill gas permit
5 applications, and the 125 feet of trench across the landfill for
a buried gas pipeline and other energy and utility conduits is
not part of any landfill gas management system, approval is not
reguired. Section 3.1(b) reguires that "[t]he [energy recovery
facility's]'s design and plan of incorporation into the landfill
. . . shall be subject to prior review and written approval." It
remains unclear whether the piping connecting the source of
landfill gas with the energy recovery facility on the Tucker
Property constitutes a "plan of incorporation" of the energy
recovery facility "into the landfill." Put another way, the
scope of Section 3.1(b) as it pertains to the Tucker Project is
sufficiently ambiguous to preclude summary judgment in favor of
the plaintiffs. See Colonial Life Ins. Co. of Am., 817 F. Supp.
at 244 .
The plaintiffs' motion for summary judgment on Count 3 is
denied. The plaintiffs reguest that the court declare that CRMCB
is not liable for "Sublessee Payments" under Sections 6.1 and
11.3 of the Gas Lease if an energy recovery facility were
developed on the Tucker Property by CRMCB's wholly owned
subsidiary, Muchmore Energy, LLC. Although Sections 6.1 and 11.3
read in their entirety may not reguire CRMCB to make Sublessee
Payments if the Tucker Project becomes operational, it is
difficult to conclude, as a matter of law, that those contract
6 terms are sufficiently clear to permit the plaintiffs to prevail
on summary judgment.
What the present record reveals is not a definitive
"agreement" or specific operational plan between Muchmore and
CRMCB, but rather a paragraph summary of what the project might
look like. And CRMCB concedes that significant regulatory and
legal obstacles may impact the plan's development. The
plaintiffs have therefore not shown that Counts 2 and 3 are ripe
for consideration, further rendering summary judgment
inappropriate on those claims. See Santoni, 369 F.3d at 598;
Pardee v. Consumer Portfolio Servs., Inc., 344 F. Supp. 2d 823,
836 (D.R.I. 2004) (a claim is not ripe for consideration where it
"involves uncertain and contingent events that may not occur as
anticipated or may not occur at all") (guotations omitted).
In sum, because the contract terms are ambiguous, there is
significant uncertainty regarding material facts, and the issue
may arguably not be ripe for consideration, the plaintiffs'
motion for summary judgment on Count 3 is denied.3
Finally, the plaintiffs' reguest for summary judgment on
their state Consumer Protection Act claim, see N.H. Rev. Stat.
3Because the court denies the plaintiffs' reguest for summary judgment on Counts 1 through 3, their reguest for injunctive relief (Count 4) is denied.
7 Ann. § 358-A, is denied. The New Hampshire Supreme Court has
recognized that although "the general provision of [N.H. Rev.
Stat. Ann. § 358-A:2] is broadly worded, . . . not all conduct in
the course of trade or commerce falls within its scope." ACAS
Acguisitions (Precitech) Inc. v. Hobert, 155 N.H. 381, 402
(2007). As such, "[a]n ordinary breach of contract claim does
not present an occasion for the remedies under the Consumer
Protection Act." Barrows v. Boles, 141 N.H. 382, 390 (1996); see
State v. Moran, 151 N.H. 450, 453 (2004). "Whether a party has
committed an unfair or deceptive act, within the meaning of the
consumer protection act, is a question of fact." Chroniak v.
Golden Inv. Corp., 983 F.2d 1140, 1146 (1st Cir. 1993)
(guotations and brackets omitted). The parties vehemently
dispute, in conflicting affidavits, whether NCES's refusal to
approve CRMCB's expansion plans result from a genuine concern
about the impact on landfill operations or that concern is mere
pretext. It would be inappropriate, therefore, to grant summary
judgment where there exists, at the most basic level, a genuine
issue of material fact, namely, whether NCES acted in a deceptive
or unfair manner. See, e.g., Curtis Mfg. Co., Inc. v. Plasti-
Clip Corp., 888 F. Supp. 1212, 1228 (D.N.H. 1994); cf. Navarro v.
Pfizer Corp., 261 F.3d 90, 93-94 (1st Cir. 2001).
8 CONCLUSION
The plaintiffs' motion for partial summary judgment4 is
therefore denied in its entirety.
SO ORDERED.
ited States District Judge
Dated: July 29, 2010
cc: Andrew W. Serell, Esq. Curtis A. Connors, Esq Edward C. Cooley, Esq. James F. Norton, Esq.
4Document no. 11.