Cristy v. Commonwealth

84 P.R. 226
CourtSupreme Court of Puerto Rico
DecidedDecember 21, 1961
DocketNo. 12484
StatusPublished

This text of 84 P.R. 226 (Cristy v. Commonwealth) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cristy v. Commonwealth, 84 P.R. 226 (prsupreme 1961).

Opinion

Mr. Justice Belaval

delivered the opinion of the Court.

On February 3, 1948, Ángel (2) Silva, Public Works Superintendent of the former Department of the Interior of' the former Government of Puerto Rico, and Fongora Corporation entered into a public-works contract for the construction of a bridge on the Yagiiez River of the Municipality of Ma-yagiiez, which was countersigned on February 12, 1948, by the former Commissioner of the Interior of Puerto Rico. With the approval of the Superintendent of Public Works, contractor Fongora Corporation subcontracted with the plaintiff-appellant, Cristy & Sánchez, for the furnishing, installation, and supervision of all the electric material required in the contract. The bonds required for the faithful performance [228]*228of the contract and for the payment of materials and labor used in the work were given by the codefendant, United States Fidelity and Guaranty Company. It is a stipulated fact that the other contracts involved in this action are identical with that herein described.

The subcontractor complied fully with the subcontract furnishing the materials and the labor and supervising the installation of the electric system. Having failed to receive payment for its work because of the contractor’s bankruptcy, it judicially demanded payment from the Commonwealth of Puerto Rico, successor at law of the former Government of Puerto Rico, and from the surety company. The Commonwealth alleged (1) that since it was not a party to the contract between the subcontractor and the contractor, it was not bound to pay, and (2) that assuming that the subcontractor had a cause of action against the Commonwealth arising prior to Act No. 104 of June 29, 1955 (Sess. Laws, p. 550), authorizing claims and suits against the Commonwealth, the latter had not given its consent to be sued. The surety company in turn alleged (3) that the bonds had been issued in favor of the Commonwealth and not of the subcontractors or other persons, and that it was not therefore liable for the payment of the electric materials and labor claimed by the subcontractor. The trial court agreed with the objections to the cause of action alleged by both defendants and dismissed the complaint summarily.

1. The contract entered into recognized the contractor’s right to subcontract or to assign part of the contract. See item 19(b) (page 9), subdivision IV (page 15), and subdivision VI (page 19) of the specifications; item 1.22 (page 4), item 8.1 (page 31), and item 8.4 (page 34), of the General Specifications for Public Works Contracts. Both the specifications and the General Specifications authorize the subcontract or assignment upon approval by the Public Works Superintendent, and the subcontractor is bound to perform [229]*229his part of the work with the same skill and under the same conditions as the contractor — item 8.1 (page 31), noted above.

2. We do not stop to consider the possible immunity of the Commonwealth in this type of actions. As a matter of reality, the Commonwealth is in this action an instrumental party because of the subsidiary character of the bond. Incidentally, these bonds are required to protect the Commonwealth against any direct claim for nonpayment of the materials or labor. Regarding the Commonwealth’s liability for contracts executed by public corporations, see Keifer & Keifer v. Reconstruction Finance Corp., 306 U.S. 381, 388-92; 83 L.Ed. 784, 788-90 (Frankfurter, 1939).

3. In every public-works contract executed in Puerto Rico, the contractor is required to secure the faithful performance of the construction contract (performance bond) and the payment of the materials and labor which he may use or employ in the construction (labor and material bond). The Commonwealth thereby protects itself against the abandonment of any public work by the contractor and, as stated above, against claims against the Commonwealth for materials and labor which the contractor may fail to pay. See item 1.5 (page 1), item 1.14 (page 3), and item 3.4 (page 9) of the General Specifications.

The General Specifications for the Contracting of Public Works adopted on March 14, 1946, require a bond to secure “the prompt payment of labor, equipment, and materials necessary for the execution of the work.” The General Specifications as well as the bond form part of the public-works contract — § 426 of the Political Code of Puerto Rico and item 1.5 (page 1) of the General Specifications. As a matter of fact, both documents are embraced in the contract under consideration.

The bond given in a public-works contract in Puerto Rico partakes of the nature of a statutory bond — in this case the General Specifications — and of a contract bond. [230]*230Hence, the description of the parties actually guaranteed must be read into the statutory provision and the terms of the contract as well as into the bond instrument, since taken together they form a single instrument. 43 Am. Jur. 891 (first paragraph) and 892 (first paragraph), § § 148 and 149. As a matter of law, the bond is not given in favor of the Commonwealth but of the persons furnishing the materials and labor. 43 Am. Jur. 893 (first paragraph), § 155. Where policies are required by statutory provision, the statute is considered as forming part thereof. González v. Santos, 75 P.R.R. 883, 885 (Ortiz, 1954); U.S. Casualty Co. v. Sup. Court; Gayá et al., Ints., 79 P.R.R. 802, 808 (Pérez Pimentel, 1957). A similar principle applies to bonds. It is not therefore necessary that each and every one of the persons thereby guaranteed be named in the bond instrument, since such persons are duly described in the applicable legal provisions or in the terms of the contract secured. 43 Am. Jur. 896, § 155.

We ought to be fair with the trial court and accept that its conclusion that there is no contractual relation between the sureties and the furnishers of materials and labor, is based on our previous decisions in the cases of Municipality of Fajardo et al. v. Axtmayer et al., 31 P.R.R. 780 (1923); Morales v. Chabert, 43 P.R.R. 114 (1932); Battle v. Pereyó, 67 P.R.R. 621 (1947), and on our judgment of December 21, 1953, in the case of The People of Puerto Rico, now the Commonwealth of Puerto Rico, plaintiff-appellant v. United States Fidelity & Guaranty Company, defendant-appellee, civil No. 10845.

In the case of Municipality of Fajardo v. Axtmayer, a contract was entered into between the Commissioner of the Interior and Axtmayer for the construction of a public' building. The contract contained a bond in favor of the Commissioner of the Interior, similar to that under consideration. It seems that the Municipality of Fajardo sued Axtmayer [231]*231and the sureties to recover the payment of certain materials sold by J. Ochoa & Hermano which were used in the work. It was held that there was no privity between the sureties and J. Ochoa & Hermano (p. 785). The only authority cited is an opinion of the Attorney General of Puerto Rico making reference to a case decided by the Supreme Court of the Philippine Islands.

In the case of Morales v. Chabert,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keifer & Keifer v. Reconstruction Finance Corp.
306 U.S. 381 (Supreme Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
84 P.R. 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cristy-v-commonwealth-prsupreme-1961.