Cresson Consolidated Gold Mining & Milling Co. v. Whitten

338 P.2d 278, 139 Colo. 273, 1959 Colo. LEXIS 429
CourtSupreme Court of Colorado
DecidedApril 20, 1959
DocketNo. 18,128
StatusPublished
Cited by18 cases

This text of 338 P.2d 278 (Cresson Consolidated Gold Mining & Milling Co. v. Whitten) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cresson Consolidated Gold Mining & Milling Co. v. Whitten, 338 P.2d 278, 139 Colo. 273, 1959 Colo. LEXIS 429 (Colo. 1959).

Opinion

Mr. Justice Hall

delivered the opinion of the Court.

Prior to July 7, 1942, the Golden Cycle Corporation, hereinafter referred to as Cycle, original plaintiff in this action,, had driven the. Carlton Tunnel some five, miles into the mountain side in Teller County. The tunnel, located at an elevation of 6893 feet, was driven for the [275]*275purpose of draining mines in the Cripple Creek mining district, so that they might be worked at lower levels, and also for the purpose of developing and putting to beneficial use water entrapped in a cone area and from which area water, due to the impervious nature of the rock filling the cone area and the walls thereof, escaped, if at all, in very limited amounts by seepage through small fissures, fractures and veins. The water in the bowl area comes entirely from precipitation upon the surface thereof; precipitation in excess of that entering the bowl escaped over the low points on the lip or rim of the bowl. Water escaping from the bowl by seepage, as stated above, and over the lip of the bowl found its way to Cripple Creek, a tributary to Four Mile Creek which discharges into the Arkansas River.

On July 7, 1942, in an adjudication proceeding in -Fremont County, in which all then parties in interest were present, a decree was entered awarding to Cycle:

“ * * * the use and consumption, as ‘developed’ water, for irrigation purposes, so much of the water which had accumulated in the said bowl or crater described in the findings of this court prior to the time when the said Carlton Tunnel of the petitioner penetrated, tapped and began to drain said bowl or crater, and which was then still confined and impounded in said bowl or crater, as can be discharged and released from said bowl or crater by and through said tunnel.

“And it is Considered, Ordered and Adjudged by the Court, that in releasing and withdrawing said accumulated water from said bowl or crater four cubic feet of water per second of time shall at all times be allowed to flow uninterruptedly and constantly from said tunnel at its portal into the stream [Four Mile Creek] into which said tunnel discharges, as part of the natural flow of water in said stream, and that when the discharge of water from said tunnel, at the portal thereof, shall have been diminished and reduced to four cubic feet of water per second of time the petitioner [Cycle] will then have [276]*276had and received all of the water awarded it by this judgment and Decree and shall not be entitled to the use or consumption of any more water through or by means of said tunnel, * * (Emphasis supplied.)

During the year 1947, the flow of water from the Carlton Tunnel fell below four cubic feet per second of time, and so remained until some time during the year 1954.

About December 1, 1947, the plaintiff in error, United Gold Mines Co., hereinafter referred to as UGM, commenced work on the Vindicator Lateral Tunnel and Extension of the Carlton Tunnel. In January 1948 the plaintiff in error, The Cresson Consolidated Gold Mining and Milling Co., hereinafter referred to as Cresson, commenced a similar lateral tunnel. These laterals were driven for the dual purpose of draining the mines of the respective owners so they would be more workable, and also for the purpose of developing water to be put to beneficial use.

In November of 1954, due to the opening of these two new laterals, the flow of water from the Carlton Tunnel was increased from its then flow of less than four cubic feet per second to over six feet, and at one time the flow exceeded thirteen feet. When the flow from the Carlton Tunnel again exceeded four feet, Cycle, claiming under its 1942 decree, commenced using all water in excess of four feet flowing from the tunnel. Shortly thereafter holders of adjudicated rights on Four Mile Creek, defendants in error herein, and to whom we refer as Intervenors, claimed that Cycle had no remaining rights and that ail waters flowing from the Carlton Tunnel belonged to the holders of adjudicated rights on the Creek. They made complaint of Cycle’s use of said water to the defendants in error, O. R. Van Cleve, Water Commissioner, Water District No. 12, and to F. C. Snyder, Division Engineer, Irrigation Division No. 2, and these two ruled that Cycle was entitled to the water in excess of four feet. •

[277]*277Intervenors “appealed” from this ruling and submitted the matter to defendant in error J. E. Whitten, State Engineer, who on March 31, 1955, .made his decision in writing, wherein he. held that Cycle’s rights granted under the decree of 1942 terminated when the flow fell below four feet and it has no further rights under that decree no matter what the future flow might be. Cycle, not satisfied with that ruling, on May 10, 1955, filed Action No. 7378 in the District Court of Fremont County and named as defendants, Whitten, Snyder and Van Cleve, and sought a mandatory injunction requiring them to administer the waters of Four Mile Creek so that Cycle would obtain all the water, in excess of four feet, flowing from the Carlton Tunnel, as provided by the 1942. decree.

Intervenors are holders of adjudicated water rights on Four Mile Creek and, as such, vitally interested in who gets the water flowing from the Carlton Tunnel into Four Mile Creek. Waters from Four Mile Creek had been over appropriated long prior to 1942, some of the decreed rights dating back to the early ’60s.

On August 28, 1956, Intervenors filed a motion in the above Action No. 7378, setting forth the fact that Cresson and UGM had built bulkheads in their tunnels which impounded, stopped and curtailed the flow of water in the Carlton Tunnel, and to which water Intervenors claimed to be entitled in accordance with their decreed rights. They requested that Cresson and UGM be joined as indispensable parties.

On September 5, 1956, Intervenors filed their motion seeking a temporary restraining order and preliminary injunction restraining Cycle from interfering with the flow of water in the Carlton Tunnel. The temporary restraining order was granted ex parte, on condition that bond of $500.00 be furnished and the matter set for hearing on temporary injunction on September 8, 1956. No further proceedings have been had with reference to Cycle.

[278]*278On September 8, 1956, an order was entered directing that Cresson and UGM be brought in as indispensable third party defendants.

On September 11, 1956, the Intervenors filed a third party complaint against Cresson and UGM, setting ‘forth in substance that Cresson and UGM, as owners of lateral tunnels;- claimed water developed thereby, and had in Case No. 7512, in the District Court of Fremont County, sought to have their rights adjudicated, and that such cause is still pending and undetermined. That on or about August 26, 1956, Cresson and UGM had built bulkheads in their tunnels'which had the effect of stopping the flow of water in the Carlton Tunnel, and by so doing had caused the flow of water to drop from in excess of six cubic feet per second to less than two feet. They asked for a temporary restraining order and prelimináry injunction, and a mandatory injunction requiring Cresson and UGM to release water stored behind said bulkheads at the rate of twenty-five feet per second.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dill v. Yamasaki Ring, LLC
2019 CO 14 (Supreme Court of Colorado, 2019)
Broomfield v. FARMERS RESERVOIR AND IRR.
235 P.3d 296 (Supreme Court of Colorado, 2010)
Ready Mixed Concrete Co. v. Farmers Reservoir & Irrigation Co.
115 P.3d 638 (Supreme Court of Colorado, 2005)
Shirola v. Turkey Cañon Ranch Ltd.
937 P.2d 739 (Supreme Court of Colorado, 1997)
Bayou Land Co. v. Talley
924 P.2d 136 (Supreme Court of Colorado, 1996)
People Ex Rel. Simpson v. Highland Irrigation Co.
917 P.2d 1242 (Supreme Court of Colorado, 1996)
United States v. Bell
724 P.2d 631 (Supreme Court of Colorado, 1986)
R.J.A., Inc. v. Water Users Ass'n of District No. 6
690 P.2d 823 (Supreme Court of Colorado, 1984)
State v. Southwestern Colorado Water Conservation District
671 P.2d 1294 (Supreme Court of Colorado, 1983)
Southeastern Colorado Water Conservancy District v. Rich
625 P.2d 977 (Supreme Court of Colorado, 1981)
Weibert v. Rothe Bros., Inc.
618 P.2d 1367 (Supreme Court of Colorado, 1980)
Ranson v. City of Boulder & Public Service Co.
424 P.2d 122 (Supreme Court of Colorado, 1967)
Cline v. Whitten
372 P.2d 145 (Supreme Court of Colorado, 1962)
Saunders v. Spina
344 P.2d 469 (Supreme Court of Colorado, 1959)
Koch v. Whitten
342 P.2d 1011 (Supreme Court of Colorado, 1959)
CRESSON CONSOLIDATED GOLD MIN. & MILL. CO. v. Whitten
338 P.2d 278 (Supreme Court of Colorado, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
338 P.2d 278, 139 Colo. 273, 1959 Colo. LEXIS 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cresson-consolidated-gold-mining-milling-co-v-whitten-colo-1959.