Crescent Towing & Salvage Company v. Dixilyn Drilling Corporation

303 F.2d 237, 1962 U.S. App. LEXIS 5167
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 9, 1962
Docket19148_1
StatusPublished
Cited by20 cases

This text of 303 F.2d 237 (Crescent Towing & Salvage Company v. Dixilyn Drilling Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crescent Towing & Salvage Company v. Dixilyn Drilling Corporation, 303 F.2d 237, 1962 U.S. App. LEXIS 5167 (5th Cir. 1962).

Opinion

RIVES, Circuit Judge.

The appellant (Crescent) and the appellee (Dixilyn) were respondents to a libel filed by the Mississippi State Highway Commission, the City of Natchez, and the Highway Department of the State of Louisiana for $41,363.24 damages sustained by the Natchez-Vidalia Bridge when Dixilyn’s Julie Ann, an offshore drilling barge, collided with the underside of the bridge. The Julie Ann was being towed down the Mississippi River by Crescent pursuant to its contract with Dixilyn. Crescent and Dixilyn jointly paid the amount of the libelants’ claim under a stipulation approved by the court, which provided in part that “the libelees, as between themselves, may litigate to a final conclusion all questions of negligence, liability, contribution, indemnity and ultimate responsibility on the part of each or both of the libelees.” After a full trial on the merits, the district court entered a final decree holding Crescent solely at fault and liable to repay to Dixilyn its half of the satisfied claim with interest and costs. 1

The district court found Crescent at fault for not furnishing enough power to hold the Julie Ann while her legs were lowered sufficiently to clear the underside of the bridge, and that Crescent’s Tug-Orleans had an engine failure which caused or contributed to the lack of sufficient power. It further found that Crescent’s Captain Brechtel was guilty of negligence in failing to make an earlier test of the holding power of the tugs with the legs lowered to the required depth, in not causing the Julie Ann to be brought to a complete stop for the lowering of her legs, and in failing to notify Dixilyn’s employee Hughes at an earlier time to start the lowering of.the legs. Those findings are vigorously attacked by Crescent as clearly erroneous, and' Crescent insists that the collision was caused by a misunderstanding of the *239 Dixilyn personnel aboard Julie Ann as to the operation of her legs, and by their failure properly to call the draft of the legs, thereby leading Captain Brechtel to the belief that the legs would clear the underside of the bridge.

A review of the district court’s findings of fact would confront us with an extremely difficult decision. Instead, we examine first the towage contract between Dixilyn and Crescent. If that contract validly shifted liability for the collision damages to Dixilyn or its insurer, whether or not Crescent was negligent, the fact findings as to negligence are immaterial.

The facts necessary for our consideration of the towage contract are not in substantial dispute, and are restated lárgely from the briefs of the parties.

The Julie Ann, constructed at the LeTourneau plant at Vicksburg, is a self-contained, submersible type drilling rig. She is 193 feet long, 151 feet wide, and has a displacement of 2500 tons. She is triangular in shape, with legs of open truss steel frame construction 175 feet long set on each corner of the triangle. Approximately 30 feet of the legs had not been installed at the time of the collision. The lower end of each leg consists of spud tanks or feet 35 feet in diameter and about 35 feet in height. The legs provide a tripod on which the hull of the barge can be raised or lowered for drilling operations or for navigational purposes. The legs are operated from a control room situated above the quarters. They are lowered and retracted by three 60 cycle motors powered by three generators, any one of which is capable of lowering or retracting all three legs simultaneously. The legs are controlled by three levers, all of which can be manipulated so that each leg can be raised or lowered by itself or with one or both of the other legs.

The barge hull itself is 20 feet in depth (from main deck to bottom), and at the time of the collision the hull afloat was drawing approximately 13 feet. Below the main deck is a machinery deck containing a complex of equipment and tanks necessary for drilling operations, Including mud tanks, water tanks, and fuel tanks. On the main deck are located draw works, pipe racks and anchor winches. Two story living quarters are situated above the main deck, completely equipped as spacious and comfortable accommodations for 45 men, all air-conditioned and equipped with a modern galley, laundry and recreation lounge. The rig is a complete self-contained unit, capable of drilling in more than 100 feet of water, and includes in her equipment slush pumps, a Schlumberger unit, cement unit, mud lab, water evaporator, mud pits and mixers, jets and guns, six diesel engines, and six electric generators.

The Natchez-Vidalia bridge is a fixed highway bridge over the Mississippi River. The lowest member of the bridge is 142.9 feet above mean sea level. The surface of the river at the bridge is 17.28 feet above mean sea level at zero on the Natchez gauge. On December 27, 1957, the date of the collision, the Natchez gauge reading was 33.2 feet, so that there was a clearance of 92.4 feet between the surface of the water and the lowest steel on the bottom side of the bridge. The legs of the rig being 143 feet long, they had to be lowered so that at least 51 feet were below the water in order for the rig safely to clear under the bridge. The legs could not be lowered to a depth that would cause them to foul on the river bottom during the approach to the bridge.

The channel of the river (the deepest portion, in which safe navigation is afforded) approaching the bridge is no less than 1200 feet wide for a substantial distance above it. The contour of the bottom, however, is not level a short distance above the bridge, there being a ledge or bar less than 55 feet below the surface about 2500 feet above the bridge. Accordingly, until the flotilla passed that point, it was impractical for the legs to have been lowered more than 35 feet. All of these facts were generally known, although, of course, the exact level of the water and the exact conditions which would be encountered on the day that *240 the proposed movement would take place could not be foreseen in advance.

The Julie Ann was scheduled for departure from the builder’s yard at Vicksburg for the day after Christmas. Upon hearing that the rig was nearing completion, Crescent solicited the business of towing her to New Orleans, and a letter of solicitation was written. Whether due to this solicitation or otherwise, Dixilyn contacted Crescent in mid-December and suggested a meeting to negotiate a tow-age contract. A meeting was held at Dixilyn’s office in New Orleans in mid-December, attended by Messrs. Tidwell, Boring and Brigham, corporate officers of Dixilyn, Messrs. Wood and Blakely, whose capacity will be hereafter adverted to, and Messrs. Apgar, Smith and Lanman of Crescent. (Mr. Lanman died prior to the trial.) At this meeting, there was a discussion of the general characteristics of the rig and of the timing of the movement, and it was tentatively agreed that Crescent would undertake the towage. Mr. Wood specified that he desired Captain Brechtel to be in charge of the tow, because he had brought one or more rigs down the river on prior occasions. Crescent stated that it proposed to use Captain Brechtel with its small Tug Orleans and two upriver push boats, the Toltec and the Ouachita, if those vessels were available. The navigation of the flotilla was to be under the command of Crescent’s pilot, Captain Brechtel.

The Toltec is a triple s.erew, 3975 horsepower push boat, 130 feet long by 30 feet wide.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seley Barges, Inc. v. Tug El Leon Grande
396 F. Supp. 1020 (E.D. Louisiana, 1974)
Crawford v. West India Carriers, Inc.
337 F. Supp. 262 (S.D. Florida, 1971)
In re Complaint of Twenty Grand Offshore, Inc.
328 F. Supp. 1385 (S.D. Florida, 1971)
Southern Natural Gas Co. v. Wilson
304 F.2d 253 (Fifth Circuit, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
303 F.2d 237, 1962 U.S. App. LEXIS 5167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crescent-towing-salvage-company-v-dixilyn-drilling-corporation-ca5-1962.