Credos Industrial v. Targa Pipeline

63 F.4th 452
CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 24, 2023
Docket22-20480
StatusPublished
Cited by6 cases

This text of 63 F.4th 452 (Credos Industrial v. Targa Pipeline) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Credos Industrial v. Targa Pipeline, 63 F.4th 452 (5th Cir. 2023).

Opinion

Case: 22-20480 Document: 00516688627 Page: 1 Date Filed: 03/24/2023

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

FILED March 24, 2023 No. 22-20480 Lyle W. Cayce Summary Calendar Clerk

In the Matter of KP Engineering, L.P.,

Debtor,

Credos Industrial Supplies & Rentals, L.L.C., doing business as Credos Fabrications,

Appellant,

versus

Targa Pipeline Mid-Continent WestTex, L.L.C.,

Appellee.

Appeal from the United States District Court for the Southern District of Texas USDC No. 4:22-CV-664

Before Smith, Elrod, and Douglas, Circuit Judges. Dana M. Douglas, Circuit Judge: Appellant, Credos Industrial Supplies & Rentals, LLC (“Credos”), appealed the bankruptcy court’s order granting Appellee, Targa Pipeline Mid-Continent WestTex LLC’s (“Targa”), motion to dismiss Credos’ Case: 22-20480 Document: 00516688627 Page: 2 Date Filed: 03/24/2023

No. 22-20480

counterclaim. The district court affirmed and dismissed the appeal. For the reasons stated herein, we AFFIRM. I. In August 2017, KP Engineering entered into a contract with Targa to engineer and build a natural gas processing plant (the “Johnson Plant.”) KP Engineering hired Credos as a subcontractor. Midway through the project, KP Engineering stopped paying its subcontractors, including Credos, resulting in $2,329,830.86 in outstanding invoices. Targa then ended its contract with KP Engineering but asked Credos to stay on and complete the project. In exchange, Targa promised that it would pay Credos any unpaid KP Engineering invoices. Targa paid nine of eleven outstanding invoices. Several weeks later, and after Credos had substantially completed work on the project, Targa informed Credos that it would not pay the final two invoices, totaling $930,507.76. In August 2019, KP Engineering filed for bankruptcy in the Southern District of Texas. Credos initiated an adversary proceeding against Targa in KP Engineering’s bankruptcy proceeding, seeking to recover the $930,507.76 in unpaid invoices based on claims of unjust enrichment and quantum meruit. Targa moved to dismiss Credos’ complaint, which Credos amended, and Targa again asserted its motion to dismiss. The bankruptcy court dismissed the amended complaint with prejudice and the district court affirmed. Credos now appeals. II. A district court’s grant of a Rule 12(b)(6) motion to dismiss is reviewed de novo. White v. U.S. Corr., LLC, 996 F.3d 302, 306 (5th Cir. 2021). Rule 12(b)(6) allows dismissal if a plaintiff fails “to state a claim upon which relief can be granted.” Fed. R. Civ. P. 12(b)(6). A complaint must contain “enough facts to state a claim to relief that is plausible on its

2 Case: 22-20480 Document: 00516688627 Page: 3 Date Filed: 03/24/2023

face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (citing Twombly, 550 U.S. at 556). “The plausibility standard is not akin to a ‘probability requirement,’ but it asks for more than a sheer possibility that a defendant has acted lawfully.” Id. (quoting Twombly, 550 U.S. at 556). III. A. Quantum Meruit Credos argues that it plead a valid quantum meruit claim. To recover under quantum meruit, the plaintiff must prove that: “(1) valuable services were rendered or materials furnished; (2) for the party sought to be charged; (3) which services and materials were accepted by the party sought to be charged, used and enjoyed by him; (4) under such circumstances as reasonably notified the person sought to be charged that the plaintiff, in performing such services, was expecting to be paid by the person sought to be charged.” Vortt Exploration Co. v. Chevron U.S.A., Inc., 787 S.W.2d 942, 944 (Tex. 1990). “Generally, a party may recover under quantum meruit only when there is no express contract covering the services or materials furnished.” Id. “This rule not only applies when a plaintiff is seeking to recover in quantum meruit from the party with whom he expressly contracted, but also when a plaintiff is seeking to recover ‘from a third party foreign to the original [contract] but who benefitted from its performance.’” Pepi Corp. v. Galliford, 254 S.W.3d 457, 462 (Tex. App.—Houston [1st Dist.] 2007, pet. denied.) (citation omitted) (holding that subcontractor was precluded from recovering against property owner in quantum meruit, even though property owner promised to pay when the general contractor failed to pay, because

3 Case: 22-20480 Document: 00516688627 Page: 4 Date Filed: 03/24/2023

subject matter was covered by an express contract between subcontractor and general contractor). 1 The district court held that Credos’ factual allegations establish that it had a contractual relationship with KP Engineering that covered the services at issue. The district court found that Credos had a contractual relationship with KP Engineering by reviewing Credos’ allegations that: (1) it was “hired by KP [Engineering] to supply mechanical fabrication labor and welding services” for work on the Johnson Plant “on a time and materials basis”; (2) KP engineering issued two purchased orders “to Credos for work at the Johnson Plant” for $2,500,000; (3) Credos “submitted invoices for its work to KP [Engineering] on a weekly basis”; and (4) KP Engineering paid some of those invoices. We agree. While there are three exceptions to the general rule that an express contract bars recovery under quantum meruit, no exception applies here. 2 Galliford, 254 S.W.3d at 462-63. Thus, Credos’

1 See also W & W Oil Co. v. Capps, 784 S.W.2d 536, 537–38 (Tex. App.—Tyler 1990, no writ) (holding that construction company, who was unaware of agreement and who furnished goods and services to farmee, was precluded from recovering value of goods and services against farmor in quantum meruit, even though farmor made verbal promises to pay for completed work, because subject matter was covered by valid express contract (farm-out agreement)); Morales v. Dalworth Oil Co., Inc., 698 S.W.2d 772, 774–76 (Tex. App.—Fort Worth 1985, writ ref’d n.r.e.) (holding same and explaining that implied contract cannot exist where subject matter is covered by valid express contract and holding that valid express contract between gasoline equipment installer and land lessees precluded installer's recovery against lessor in quantum meruit because the subject matter of claim, the equipment, was covered by installer's contract with lessees)). 2 “First, recovery in quantum meruit is allowed when a plaintiff has partially performed an express contract but, because of the defendant’s breach, the plaintiff is prevented from completing the contract.” Galliford, 254 S.W.3d at 462 (citation omitted). This exception does not apply because Credos has fully performed under the contract and because Targa was not the breaching party under the contract with KP Engineering.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
63 F.4th 452, Counsel Stack Legal Research, https://law.counselstack.com/opinion/credos-industrial-v-targa-pipeline-ca5-2023.