Credit Rep. Serv. v. Joseph Sylvester Co., Unpublished Decision (8-24-1999)

CourtOhio Court of Appeals
DecidedAugust 24, 1999
DocketCase No. 98 CA 30.
StatusUnpublished

This text of Credit Rep. Serv. v. Joseph Sylvester Co., Unpublished Decision (8-24-1999) (Credit Rep. Serv. v. Joseph Sylvester Co., Unpublished Decision (8-24-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Credit Rep. Serv. v. Joseph Sylvester Co., Unpublished Decision (8-24-1999), (Ohio Ct. App. 1999).

Opinion

OPINION
Defendant-appellant Joseph Sylvester Construction Company, Inc. ("Contractor") appeals the decision of the Mahoning County Common Pleas Court which adopted the magistrate's order of summary judgment for plaintiff-appellee Credit Reporting Service, Inc. ("CRS"). For the following reasons, the order granting summary judgment is reversed, and this case is remanded for further proceedings.

In April 1991, the parties entered into a written agreement under which Contractor would construct a commercial office building in Boardman, Ohio for CRS. In June 1991, CRS took possession of the building. Thereafter, Contractor remodeled the basement of the building to contain a lounge and a conference room. CRS later had a second stairway installed by an entity unidentified in the record. At the request of the county building inspector, Contractor closed this illegal stairway and installed a fire-rated stairwell with doors.

On July 12, 1994, the county building inspector sent a notice of violations to CRS which specified the following deviations from the Ohio Basic Building Code:

"1. Interior completions and alterations were performed under your direction contrary to the approved plans, specifically:

a. An interior stair was constructed. The stair as constructed does not conform to O.B.B.C. The risers exceed the 7" maximum height. The handrails do not have extensions. The work was performed without a building permit or submission of plans.

b. A conference room was constructed in the basement. The work was performed without a permit or submission of plans.

2. The building was occupied under your direction before issuance of a certificate of use and occupancy."

A notice of violations was also sent to Contractor which stated:

"1. Interior completions and alterations were performed under your direction contrary to the approved plans, specifically:

a. A one-hour fire-rated floor/ceiling assembly was not installed at the basement ceiling.

b. An interior stair was eliminated at the front (north) of the building. Although a one-exit space is allowable under O.B.B.C., plans must be submitted showing proposed change.

c. The basement storage area did not receive a limited area sprinkler system.

d. A conference room was constructed in the basement. The work was performed without a permit or submission of plans.

2. Restroom exhaust does not discharge to the exterior of the building." (Citations to code sections omitted)

The notices informed the recipients that they had thirty days to file an appeal and request a hearing before the Board of Building Appeals pursuant to Ohio Adm. Code 4101:2-1-35 (C). Contractor failed to appeal its notice of violations. CRS appealed item 1b in its notice of violations, and the Board agreed that Contractor was responsible for obtaining a building permit before constructing the conference room. The Board then told CRS that an occupancy permit was mandatory. In order to obtain the occupancy permit, CRS paid $18,745.51 to Alex Downie Sons Co. to bring the building up to code. CRS also allegedly spent $5,546.82 in costs and legal fees in its quest to obtain the permit.

On April 9, 1996, CRS filed a civil suit against Contractor seeking to be reimbursed for the aforementioned sums of money expended on bringing the building up to code and obtaining an occupancy permit. After the case was assigned to a magistrate, CRS moved for summary judgment arguing that because Contractor failed to appeal its notice of violations, it is barred by the doctrine of res judicata from disputing liability. CRS also stated that the amount of damages was undisputed. Contractor filed a memorandum in opposition and filed its own motion for summary judgment stating that there existed genuine issues of material fact with regards to who performed the work that was code violative. On June 19, 1997, the magistrate granted summary judgment for CRS. Contractor filed timely objections to the magistrate's order. The trial court adopted the magistrate's decision on January 28, 1998. The within timely appeal resulted.

Contractor sets forth two assignments of error, the first of which contends:

"THE COURT ERRED IN GRANTING THE PLAINTIFF-APPELLEE'S MOTION FOR SUMMARY JUDGMENT."
Contractor argues that there exists genuine issues of material facts with regards to who caused the building code violations. CRS counters that Contractor's argument is irrelevant because Contractor's failure to administratively appeal its notice of violations resulted in a final order with res judicata effect on the issue of liability in the case at bar.

Res judicata consists of two concepts: claim preclusion and issue preclusion. Grava v. Parkman Twp. (1995), 73 Ohio St.3d 379,381. The doctrine of claim preclusion states that a judgment rendered in a prior action bars relitigation of the same cause of action and bars litigation of a claim that could have been litigated previously between the same parties. Schomaeker v.First Natl. Bank (1981), 66 Ohio St.2d 304, 313. The doctrine of issue preclusion, also called collateral estoppel, precludes relitigation of an issue that was actually and necessarily determined in a prior action between the same parties or their privies. Id. Both doctrines are applicable to an administrative decision that resulted from a proceeding of a judicial nature.Set Products, Inc. v. Bainbridge Twp. Bd. of Zoning App. (1987),31 Ohio St.3d 260, 262-63.

In the case at bar, CRS contends that Contractor is barred from defensively litigating the issue of whose work resulted in the code violations because the notice of violations, which became final when no appeal was filed, already determined this issue. Thus, it is the doctrine of collateral estoppel that CRS utilizes to defend the trial court's grant of summary judgment. More specifically, CRS is attempting to use the doctrine of offensive collateral estoppel. Offensive collateral estoppel is a term used to describe the scenario where a plaintiff prevents a defendant from relitigating issues that have previously been decided against the defendant in a suit by a different plaintiff. Black's Law Dictionary (6 Ed. 1991) 179. However, the use of offensive collateral estoppel is not permitted in Ohio courts. Goodson v.McDonough Power Equip., Inc. (1983), 2 Ohio St.3d 193, 198-199. As advanced supra, the basic requirements that must be met before applying collateral estoppel are: "(1) an administrative proceeding of a judicial nature, (2) an identity of the parties, and (3) an identity of the issues." Dublin Sch. Dist. Bd. offEdn. v. Limbach (1994), 69 Ohio St.3d 255, 257, quoting Am. Soc.for Metals v. Limbach (1991), 59 Ohio St.3d 38, 39.

In accordance, collateral estoppel will not operate in the case at bar to preclude Contractor from defending the breach of contract action brought against it by CRS. Initially, we point out that a notice of violations is not judicial in nature. The first sentence of the notice states that it is being issued without prior hearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitehead v. General Telephone Co.
254 N.E.2d 10 (Ohio Supreme Court, 1969)
Schomaeker v. First National Bank of Ottawa
421 N.E.2d 530 (Ohio Supreme Court, 1981)
Goodson v. McDonough Power Equipment, Inc.
443 N.E.2d 978 (Ohio Supreme Court, 1983)
American Society for Metals v. Limbach
569 N.E.2d 1065 (Ohio Supreme Court, 1991)
Turner v. Turner
617 N.E.2d 1123 (Ohio Supreme Court, 1993)
Board of Education of Dublin School District v. Limbach
631 N.E.2d 604 (Ohio Supreme Court, 1994)
Grava v. Parkman Township
653 N.E.2d 226 (Ohio Supreme Court, 1995)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Fort Frye Teachers Ass'n v. State Employment Relations Board
692 N.E.2d 140 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Credit Rep. Serv. v. Joseph Sylvester Co., Unpublished Decision (8-24-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/credit-rep-serv-v-joseph-sylvester-co-unpublished-decision-8-24-1999-ohioctapp-1999.