Creative West Architects, LLC v. Downtown Natick Development Co.

28 Mass. L. Rptr. 319
CourtMassachusetts Superior Court
DecidedApril 14, 2011
DocketNo. MICV200904513A
StatusPublished

This text of 28 Mass. L. Rptr. 319 (Creative West Architects, LLC v. Downtown Natick Development Co.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creative West Architects, LLC v. Downtown Natick Development Co., 28 Mass. L. Rptr. 319 (Mass. Ct. App. 2011).

Opinion

Wilkins, Douglas H., J.

The plaintiffs, Creative West Architects, LLC (“Creative West”) and CWA Architects, LLC (“CWA”) brought this action for payment for architectural services rendered to defendant Downtown Natick Development Company, LLC (“DNDC”) on a construction project (“Project”) at 20 South Avenue, Natick, Massachusetts (“Property”). They also have sued DNDC’s principal, Robert F. Rinaldi and have asserted a lender liability claim against defendant Needham Bank. The third amended complaint contains ten counts, four of which name the Bank as a defendant, including Count II (mechanics lien), Count VII (accounting), Count IX (intentional interference with contractual relations) and Count X (lender liability under the so-called instrumentality theoiy).

Needham Bank has moved for summary judgment on Counts II, VII and IX on the grounds that the plaintiffs did not perfect a lawful mechanics lien against the property and lack sufficient evidence to support their other claims. After amendment of the complaint, Needham Bank filed a supplemental motion for summary judgment on Count X, on the ground that the plaintiffs have not shown grounds for lender liability. The plaintiffs have opposed both motions. After hearing and review of the parties’ written submissions, the court ALLOWS Needham Bank’s motion for summary judgment and supplemental motion for summary judgment.

BACKGROUND

The facts apparent from the parties’ Rule 9A(b)(5) statements and reasonable inferences favorable to the plaintiffs are as follows.

The defendant, Robert F. Rinaldi formed DNDC as a single asset and single-purpose entity to own the Property and develop the Project. The Project was DNDC’s sole business. Needham Bank was the principal lender to DNDC on the Project, having extended a loan of $8,631,800, secured by a first mortgage on the Property. DNDC also gave a second mortgage to the seller of the property in the amount of $380,000.

On December 1, 2006, Creative West and CWA entered into separate contracts with DNDC for the provision of architectural services. The contracts provided in relevant part:

... at the sale of each unit DNDC will pay $12,000 per unit (total $96,000) of the stated deferred fees to Creative West Architects . . . Payment of the condo sale allocation to Creative West Architects shall be concurrent with, and a part of, the closing of the unit sales. In the event that DNDC cannot pay the full $12,000 at the closing of the unit sale, the unpaid balance shall incur a [sic] 6% interest ... Postponement of payment will be permitted only if DNDC can demonstrate that the monies cannot be paid at closing due to the proprietary debts to other parties who have position over Creative West Architects (i.e., the Bank and the previous owners of the property).

Creative West and CWA are owed more than $100,000 for design, management and consulting services in connection with the development of the Project. They have not been paid, for reasons having nothing to do with the quality or completeness of their work.

Needham Bank issued a construction loan for the Project. DNDC stopped making regular interest payments in April 2009, at which point Needham Bank declared the loan in default. At approximately the same time, Rinaldi returned to work full time at EMC. From that point on, DNDC had no further involvement in the Project. Needham Bank then paid RFR’s project manager and superintendent, Dean Laprade, directly in his individual capacity to finish and oversee completion of the Project. Creative West and CWA provided no services to the Project after April 2009.

[320]*320In May 2009, Needham Bank’s president prepared a letter to guarantee unconditionally its commitment to the Project. It then urged Rinaldi to try an accelerated marketing approach to auction the remaining units. In the summer of 2009, Needham Bank met on multiple occasions with an auctioneer concerning the private auction of the remaining units. It paid $64,000 from its own account for all up-front marketing costs to be incurred in publicizing the private auction. It also commented on, negotiated and signed a contract for auction services.

By August 2009 at the latest, Needham Bank had assumed final decision making authority on construction decisions. It was paying contractors directly for construction work performed on the Project and hired its own general contractor and subcontractors and used its own contract for these purposes. An entity wholly owned by Rinaldi, named RFR Enterprises, LLC (“RFR”), was the general contractor for the Project until Needham Bank replaced it with its own general contractor, Edgehill Construction Enterprises, Inc. (“Edgehill”), pursuant to an agreement dated September 28, 2009. As of September 30, 2009 at the latest, the Bank was no longer paying RFR. While Needham Bank honored and paid many of the contractual obligations owed by DNDC and RFR, it refused to pay the plaintiffs for their work. Instead, it hired a replacement design firm, M.Z.O. Architectural Group, Inc. (“MZO”). MZO was a preferred contractor of Needham Bank and has performed regular work for the Bank, including work on multiple Needham Bank branch offices.

As of September 2009, Needham Bank had taken over a presence in overall management of the Project. Rinaldi, DNDC and RFR were no longer involved in construction or financial decisions concerning the Project. The Bank never paid RFR. Edgehill’s principal never met or spoke with Rinaldi or any representative of RFR or DNDC. Whenever Edgehill needed direction, Edgehill went directly to Needham Bank. Needham Bank also controlled the finances of the Project. The Bank issued all construction payments directly and made all financial decisions regarding construction and development of the Project.

The Bank continued to work with and pay its own contractors and subcontractors directly at all times through the foreclosure sale on December 29, 2009. On several occasions Needham Bank met with its own general contractor, Edgehill, which took over all remaining construction activities, including the interior of units, the building exterior and common areas. Edgehill had long been a contractor for Needham Bank on all properties that the Bank expected to acquire at foreclosure.

As of September 2009 and continuing through foreclosure, Needham Bank also controlled unit sales. Two market rate units were under agreement and were scheduled to close prior to the November 2009 auction. One buyer walked away from the deal. Needham Bank extended the closing of the other unit until after foreclosure. Two additional units went under agreement at the auction. Pursuant to the mandatoiy auction terms, those sales were required to close within thirty days. Needham Bank postponed those sales until after it acquired title to the remaining units through foreclosure. It was in the borrower’s interest to consummate those closings prior to foreclosure (as originally agreed) because the outstanding loan obligations and potential deficiency of the borrower (DNDC and Rinaldi) would decrease considerably. The November 19, 2009 auction absolutely had a negative effect on the value of the Property.

On October 13, 2009, the plaintiffs recorded statements of account, listing the amounts they claimed were owed to them, at the Middlesex South District Registry of Deeds (“Registry”). The Bank contends that, at the time, DNDC owed $6,898,335.35 under its mortgage loan. The plaintiffs contend that the balance was $6,428,580.00 as of October 5, 2009. No payments were made after October 5, 2009.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FAMM Steel, Inc. v. Sovereign Bank
571 F.3d 93 (First Circuit, 2009)
Kennedy v. Columbia Lumber & Manufacturing Co.
384 S.E.2d 730 (Supreme Court of South Carolina, 1989)
Volpe Construction Co. v. First National Bank
567 N.E.2d 1244 (Massachusetts Appeals Court, 1991)
United Truck Leasing Corp. v. Geltman
551 N.E.2d 20 (Massachusetts Supreme Judicial Court, 1990)
Libbey v. Tidden
78 N.E. 313 (Massachusetts Supreme Judicial Court, 1906)
National Lumber Co. v. United Casualty & Surety Insurance
802 N.E.2d 82 (Massachusetts Supreme Judicial Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
28 Mass. L. Rptr. 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creative-west-architects-llc-v-downtown-natick-development-co-masssuperct-2011.