Crawford-Strauss Properties, Inc. v. Doolittle

540 S.W.2d 334, 1976 Tex. App. LEXIS 2383
CourtCourt of Appeals of Texas
DecidedJanuary 14, 1976
DocketNo. 15447
StatusPublished
Cited by2 cases

This text of 540 S.W.2d 334 (Crawford-Strauss Properties, Inc. v. Doolittle) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crawford-Strauss Properties, Inc. v. Doolittle, 540 S.W.2d 334, 1976 Tex. App. LEXIS 2383 (Tex. Ct. App. 1976).

Opinion

CADENA, Justice.

Defendant, Crawford-Strauss Properties, Inc., appeals from a judgment, based on a jury verdict, awarding plaintiffs, Robert Doolittle and Richard Ragsdale, d/b/a Rio Landscaping & Sprinkler Company, $5,470.50 as compensation for work done, and materials furnished, by plaintiffs under a contract for installation by them of a sprinkler system at an apartment complex under construction in San Antonio. Such construction was under the supervision of defendant as general contractor.

On July 4, 1973, plaintiffs submitted to defendant a proposal for the installation of a sprinkler system at the apartment complex. Defendant accepted the proposal and plaintiffs began installation of the system with the understanding that a written contract would be executed incorporating plaintiffs’ proposal. The contract was signed by defendant on July 30, 1973, after it had been signed by plaintiffs. The record does not disclose the date of execution of the instrument by plaintiffs.

On July 31, 1973, plaintiffs submitted their first “draw sheet,” requesting payment for work done by them up to that time. A check for the amount shown on [336]*336the draw sheet ($5,470.50) was delivered to plaintiffs, but, after an inspection of the work, defendant ordered payment on the check stopped. Plaintiffs have not completed the installation of the sprinkler system; and by this suit they seek recovery of the sum of $5,470.50 as payment for the work done by them prior to July 31, 1973.

The contract price for the installation of the complete sprinkler system was $18,-235.00.

The sprinkler system was to be an automatically operated system consisting of approximately 835 “commercial grade Rain-bird brass high-pop pop-up sprinkler heads.” The contract recited that the exact number of sprinkler heads to be installed would be “determined by adequate coverage, considering topography and landscape planting.” The contract required the installation of 30 “commercial grade Buckner electric automatically operated sprinkler control valves”; approximately 10 “Toro pop-up rotary heads”; and 3 “Rainbird 10-station automatic controllers.” All workmanship and materials were required to conform with the plumbing and building codes of the City of San Antonio, and plaintiffs agreed to install anti-backflow devices “as required.” Plaintiffs guaranteed “100% coverage of the lawn areas below the finished grade.” The contract required that the sprinkler heads be so positioned as to avoid spraying water on the buildings.

The contract specified that no alterations were to be made in the “[w]ork as shown or described by the Contract Documents except on the written order of” defendant.

The jury found that the work actually done by plaintiffs under the contract was done in a good and workmanlike manner and that the work actually done substantially complied with the contract. The jury further found that it would require no additional expense “to place the portion of the sprinkler system actually completed by Plaintiffs in compliance with the contract.”

Plaintiffs’ pleadings did not seek recovery on a theory of quantum meruit.

The following facts are undisputed:

(1) Plaintiffs did not install an anti-back-flow device, although the plumbing code of the city required at least one such device. Operation of the sprinkler system without meeting this requirement would be unlawful and would subject the user to a fine not exceeding $200.00 each time the system was used.

(2) Plaintiffs installed Toro valves instead of the Buckner valves called for in the contract.

(3) Plaintiffs installed a Buckner controller rather than the Rainbird 10-station automatic controller required by the contract.

Clearly, the work actually performed by plaintiffs does not constitute full compliance with the terms of the contract. In order to recover, they must invoke the equitable doctrine of substantial performance. “Substantial performance” has been defined in Texas as follows:1

To constitute substantial compliance the contractor must have in good faith intended to comply with the contract, and shall have substantially done so in the sense that the defects are not pervasive, do not constitute a deviation from the general plan contemplated for the work, and are not so essential that the object of the parties in making the contract and its purpose cannot, without difficulty, be accomplished by remedying them. Such performance permits only such omissions or deviation from the contract as are inadvertent and unintentional, are not due to bad faith, do not impair the structure as a whole, and are remediable without doing material damage to other parts of the building in tearing down and reconstructing.

At the time that defendant stopped payment on the check, one of defendant’s vice-presidents told plaintiffs that the sprinkler system did not give 100% coverage; that there was a defective valve; and that some of the sprinkler heads were Toro vinyl heads rather than the Rainbird heads called for by the contract. There is uncontradict-[337]*337ed testimony to the effect that plaintiffs repaired the defective valve and replaced the Toro sprinkler heads with Rainbird heads. The testimony concerning the coverage afforded by the system is conflicting, and the jury obviously resolved this conflict in favor of plaintiffs.

We thus must consider the effect of plaintiffs’ conduct in failing to install the anti-backflow device, in installing a Buckner controller rather than the Rainbird controller specified in the contract, and in installing Toro valves rather than Buckner valves.

One of the plaintiffs at first explained the absence of the anti-backflow device by stating that the installation of such a device was not required by the plumbing code of the City of San Antonio. When confronted with a provision of the plumbing code requiring the installation of such a device, he took the position that defendant insisted that the connection of the sprinkler system to the city water mains be done by defendant’s plumber, and that it was the duty of such plumber to install the anti-backflow device. The evidence establishes that the plumber who made the connection to the city water main was paid by plaintiffs. It was plaintiffs’ duty under the contract to make such connection, it is clearly plaintiffs’ obligation under the contract to install, or cause to be installed, required anti-backflow devices. This obligation was not performed.

The testimony is sufficient to support a finding that the valves and controller actually installed by plaintiffs were at least equal in quality and performance to those called for by the contract. The portion of the sprinkler system actually installed was, according to plaintiffs’ testimony which the jury accepted as true, sufficient to accomplish the purpose for which the contract was executed. That is, except for the absence of the anti-backflow device, the deviations are not so pervasive as to frustrate the purpose of the contract in any real or substantial sense. Defendant’s testimony establishes that the absent backflow prevention device can be installed for about $715.00.

The evidence, while conflicting, is sufficient to support a finding of substantial compliance.

However, we agree with defendant that the jury’s answer to the effect that no additional expenditures would be required in order to bring the work into literal compliance with the terms of the contract cannot stand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jonas Realty Corp. v. Coker
716 S.W.2d 169 (Court of Appeals of Texas, 1986)
Del Monte Corp. v. Martin
574 S.W.2d 597 (Court of Appeals of Texas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
540 S.W.2d 334, 1976 Tex. App. LEXIS 2383, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crawford-strauss-properties-inc-v-doolittle-texapp-1976.