Craven v. Skobba

121 N.W. 625, 108 Minn. 165, 1909 Minn. LEXIS 661
CourtSupreme Court of Minnesota
DecidedJune 11, 1909
DocketNos. 16,217—(109)
StatusPublished
Cited by5 cases

This text of 121 N.W. 625 (Craven v. Skobba) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Craven v. Skobba, 121 N.W. 625, 108 Minn. 165, 1909 Minn. LEXIS 661 (Mich. 1909).

Opinion

Brown, J.

Action for damages for the alleged breach of certain conditions [166]*166of a lease, in which plaintiff had a verdict, and subsequently moved for, and appealed from an order denying, a new trial.

The facts are substantially as follows: Plaintiff was the owner of a residence property situated in' Minneapolis, and on August 24, 1907, leased the same to the defendant for the term of one year from and after the first day of September following, at an agreed rent of $40 per month. The lease was in the usual form of such instruments, and contained, among other things, the following stipulation or condition, ' namely: “And the lessor specifically agrees and covenants with the lessee that he will do the following repairs on said premises: Paint the kitchen and pantry, paint dado in dining room and clean the ceiling, calcimine walls in parlor and library and hall, retouch .ceilings and border in parlor and library room, and paint the house on the outside. That these repairs are to be done at once, or within, a reasonable time.” The repairs provided for by this stipulation were all made, except painting the house on the outside, before September 9, 1907, at which time defendant took possession of and moved-into'the house with his family. Plaintiff failed to have the house- painted, and on October 14, over a month after taking possession, defendant demanded in writing that the condition of the lease in this respect be complied with, and notified plaintiff that unless painting operations were commenced before October 21 following he wpuld treat the lease as terminated and vacate the premises. In the same demand and notice defendant insisted that other repairs be made which were not provided for by the lease. In response to this demand, plaintiff replied with some criticisms of defendant’s manner of using the premises, apd recognized his obligation at that time to paint the house,' stating that he would do so as soon as possible. His recognition of the obligation to paint was contained in the following extract from his letter:

“I have employed a man to paint that house on the outside, and it will be done just as soon as that man can possibly get to it. I shall keep my contract with you to the letter, and I shall expect the same of you.”

The house was not painted, and defendant vacated on the ninth day of November, surrendering the key thereof to plaintiff’s agent. Plaintiff was thereafter unable to rent the premises until May 1, [167]*1671908, and then at a reduced rent. He brought this action for the loss suffered in the premises, for injuries to the property alleged to have been caused by defendant while in possession, and damages in other respects. The defense was, first, a breach of plaintiff’s contract to paint the house; and, second, a surrender of the premises and an acceptance thereof by plaintiff.

1. It is contended by plaintiff, in support of his claim that he was entitled to an instructed verdict, and consequently judgment notwithstanding the verdict in this court, that defendant waived the failure of plaintiff to paint the house by taking possession thereof, knowing that the work had not been done, and, further, that defendant’s abandonment of the premises was for the reason that plaintiff refused to make repairs not stipulated for in the lease, and not because the painting was not completed, and that he cannot, therefore, not? rely upon the breach of the contract in that respect. The position cannot be sustained. The lease was executed by the parties on the twenty-fourth day of August for the term of one year, commencing the first day of September following. It contained the stipulation respecting the repairs, including the outside painting, and that this work should be completed “within a reasonable time.” Defendant took possession on the ninth day of September. A fair construction of this contract leaves it reasonably clear that the parties contemplated that defendant would or might -take possession of the premises before the repairs were made. The term of tenancy commenced within a week after the contract was entered into, and it would be unreasonable to suppose that defendant was to commence paying rent at that time and have no use of the premises. And, again, a reasonable time would not elapse between the date of making the contract, August 24, and the commencement of the tenancy, September 1, and the case comes within the rule that where the landlord agrees to repair before a certain day, which does not arrive until after the term of tenancy begins, an entry by the tenant does not-operate as a waiver. Wood, Landlord & Tenant, 382; 24 Cyc. 1085, et seq., and cases cited.

Defendánt insisted in October that this work be commenced and completed, and gave notice that unless plaintiff performed his agree[168]*168ment on this subject the premises would be vacated. This plaintiff recognized defendant’s right to demand, but he wholly failed to have the work done. At the time the demand was made upon him he informed defendant that he had employed “a. man” to do the work, and that the man would complete it as soon as he could turn his attention to it. Defendant had the unquestioned right to insist that the work be done within a reasonable time after the date of the contract, and was not required to await the pleasure of a particular painter. Plaintiff was required by his contract to proceed with diligence, not in the employment of a particular workman, but to see that, the work was commenced and completed. The trial court rightly submitted this question to the jury, and their finding that the painting was not done within a reasonable time should not be disturbed. Defendant, therefore, not having waived his right to insist upon the painting, was justified in vacating the premises and surrendering the lease.

2. The demand made by defendant that plaintiff proceed and paint the house was coupled with a demand that other improvements not included in plaintiff’s agreement for repairs be also made; and it is urged that it conclusively appears that he vacated the premises because those repairs were not made. This question was properly submitted to the jury. The mere fact that defendant made an excessive demand for repairs would not preclude him from urging a breach of the contract in respect to which he had an unquestioned right. Plaintiff was not thereby put in default as to the repairs not provided for by the contract, but he was in default respecting the painting which he expressly covenanted to do. It is not important whether the failure to paint the house did or did not materially lessen the enjoyment thereof. It was expressly agreed between the parties that the painting should be done, and their respective rights and liabilities are measured by the terms of their written contract, and not by the consequences resulting from a breach thereof. Piper v. Fletcher, 115 Iowa, 263, 88 N. W. 380; Barnes v. Strohecker, 17 Ga. 340; Clarke v. Spaulding, 20 N. H. 313; Rogers v. Babcock, 139 Mich. 94, 102 N. W. 636; 18 Am. & Eng. (2d Ed.) 230.

3. Defendant offered evidence on the trial tending to show an agreement with plaintiff’s agent, subsequent to the execution of the [169]*169lease, to the effect that defendant’s act in taking possession of the premises should not be treated as a waiver of his right to insist that the painting be done. Of this plaintiff complains. We discover no error here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. LeRoy
594 N.W.2d 193 (Court of Appeals of Minnesota, 1999)
Craigie v. Firemen's Insurance Co. of Newark
191 F. Supp. 710 (D. Minnesota, 1961)
Peterson v. Anderson
235 N.W. 534 (Supreme Court of Minnesota, 1931)
Strite Governor Pulley Co. v. Lyons
152 N.W. 765 (Supreme Court of Minnesota, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
121 N.W. 625, 108 Minn. 165, 1909 Minn. LEXIS 661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/craven-v-skobba-minn-1909.