Cranford v. District of Columbia

20 Ct. Cl. 376, 1885 U.S. Ct. Cl. LEXIS 11, 1800 WL 1422
CourtUnited States Court of Claims
DecidedJune 1, 1885
DocketNo. 359
StatusPublished

This text of 20 Ct. Cl. 376 (Cranford v. District of Columbia) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cranford v. District of Columbia, 20 Ct. Cl. 376, 1885 U.S. Ct. Cl. LEXIS 11, 1800 WL 1422 (cc 1885).

Opinion

Weldon, J.,

delivered tbe opinion of tbe court:

Tbe claimants brought suit to recover tbe sum of $14,748 due them, as they allege, for labor performed on tbe streets of Washington during the latter part of tbe year 1875.

They bad nine contracts with th'e defendant, under which they laid 73,741 square rods of concrete or vulcanite pavement, for which they have been paid at tbe rate of $3 per square yard, being twenty cents per yard less than the contract price, as they now insist. The agreements on which this suit is founded are numbered 762, 627, 270, 323, 620, 626, 346, 44, and 571.

No specific compensation is provided by the terms of the agreements, but reference is made to the amount “paid” and “established and paid” by the Board of Public Works for such work.

The contracts are similar in terms, except Nos. 44 and 346; in those two the word “ paid ” is used, while in all of the others the words “ established and paid ” are employed by the parties.

With that variation the contracts as to compensation are as follows:

“It is further agreed that the parties of the second part hereto shall receive the price established and paid by the Board of Public Works for the vulcanite concrete pavement.”

In order to develop fully the agreements it is necessary for us to incorporate into them so much of the contracts made by the Board of Public Works as indicate the price paid, “ or established and paid,” by that body for similar work during its administration.

In the contract ottered in evidence as establishing the price by the Board of Public Works, and which is set forth in finding xii, it is provided:

“ Also to take up and remove the wooden pavement on Pennsylvania avenue between Ninth and Tenth streets northwest, in the city of Washington, D. C. •, and to lay and put down the pavement known as and called the vulcanite concrete pavement on the carriage-way of said Pennsylvania avenue between said Ninth and Tenth streets northwest, in the city of Washington.
^ ^ ^
“Tenth. It is further agreed that the said parties of the second part shall receive the following prices'as full compensation for furnishing all the materials and labor which may be required [384]*384in the prosecution of the whole of the work to be clone under this agreement, and in all respects completing the same, to wit:
#*####*
“ Laying and putting down the said vulcanite concrete pavement, per square yard, three dollars and twenty ($3.20) cents, which shall include two (2) feet of grading, which said sums or prices the said party of the first part shall pay to the said parties of the second part as herein provided.”

The controversy grows out of that part of the contract which relates to the subject of grading, the claimants insisting that they are entitled to the $3.20 for having removed the wooden pavement, without reference to the fact whether any grading was done, and the defendant insisting that in order to entitle the claimants to the full measure of the agreement they must have done at least two feet of grading. The portion of the contract relating to the depth of grading was differently construed by the Board of Public Works and the Commissioners, the former, not regarding it as material that the contractor did not do two feet of grading, and the latter, by its engineer, determining the compensation as dependent upon the amount and depth of grading. Upon the latter theory accounts were made outfor the claimants from time to time by the engineer, and receipts given by them, upon the basis of such a construction; and the claimants themselves made out and presented to the Board of Audit two accounts based upon the Commissioners’ construction of the contract.

The claimants objected to that construction of the agreements, when the defendant first sought to establish it under the Commissioners, and presented the two accounts made out by them after their objections and protest against the action of the District engineer in construing the contracts as excluding the twenty cents where the two feet of grading was not done.

On the 28th of September, 1875, the parties had a controversy upon the subject of the construction of the contract as to the price, the claimants insisting that they were entitled to $3.20, and the engineer of the defendant insisting that, inasmuch as two full feet of grading was not done, the parties were only entitled to $3. They differed as to the construction of the agreements, the claimants making out their bill at the former price and the defendant estimating the work on the basis of the latter. The claimants on that date accepted the compensation resulting [385]*385from the defendant’s construction of the agreement and gave a receipt in full of the account, but protested that it was not as much as they were entitled to, and that it was not in full satisfaction of their claim.

It will be seen by reference to finding vi that up to the 28th of September the claimants had commenced work on contracts Nos. 702, 571, 620, and 346, and although contracts Nos. 346 and 626 were not actually reduced to writing and signed until the 14th of October, they were in fact let before the controversy between the parties as to the price on the 28th of September. The amount of work done under the contracts completed and commenced before said last-mentioned date is 36,928 yards, leaving of the 73,741 yards completed under all the contracts 36,813 yards commenced and completed after the 28th of September, 1875.

It is also insisted that on the 14th day of September, 1871, the Board of Public Works, by an order entered on its minutes, fixed the price to be paid by it per square yard for concrete pavement at $3, and therefore that became the price under the contracts made by the Commissioners of the District.

That precise question, on a similar finding, was before this court in the case Jonathan Taylor v. District of Columbia (17 C. Cls. R., 367). In that action it was held:

u Where the District Commissioners agree to pay for work the price previously “paid by the Board of Public Works f the contractor is not limited to the price fixed by the order of the Board of Public Works appearing on its minutes, but is entitled to the price actually paid by the. board. * * * An order of the former Board of Public Works fixing the price to be paid for concrete pavement was simply a rule for its own government, and could not by the mere force of its adoption bind a contractor.”

In all the contracts embraced in this controversy except Nos. 44 and 346 the words are “ established and paid ” instead of “ paid.” A price usually is established by parties in dealing with a given subject-matter, and ordinarily is the best evidence of its value, and must be taken as the best evidence of such value even though it may be contradicted by a declaration or act of one of the parties not communicated to the other. The ^findings show that one of the claimants, before the making of Ibhe agreements declared on, had been a large contractor with ■he Board of Public Works; that he had received $3.20 for [386]*386concrete pavement; and they do not show that he had any knowledge of the entry made on the books of the board on the 14th of September, 1871.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Child & Co.
79 U.S. 232 (Supreme Court, 1871)
United States v. Bostwick
94 U.S. 53 (Supreme Court, 1877)
Brawley v. United States
96 U.S. 168 (Supreme Court, 1878)
Child v. United States
7 Ct. Cl. 209 (Supreme Court, 1871)
Tutlis v. West Virginia Board of Regents
9 Ct. Cl. 114 (West Virginia Court of Claims, 1972)
Bostwick v. United States
12 Ct. Cl. 67 (Supreme Court, 1877)
Mylott v. Department of Health
15 Ct. Cl. 303 (West Virginia Court of Claims, 1985)
Taylor v. District of Columbia
17 Ct. Cl. 367 (Court of Claims, 1881)

Cite This Page — Counsel Stack

Bluebook (online)
20 Ct. Cl. 376, 1885 U.S. Ct. Cl. LEXIS 11, 1800 WL 1422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cranford-v-district-of-columbia-cc-1885.