Cranford v. Brooklyn Heights Railroad

168 A.D. 457, 154 N.Y.S. 16, 1915 N.Y. App. Div. LEXIS 8958
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 11, 1915
StatusPublished
Cited by1 cases

This text of 168 A.D. 457 (Cranford v. Brooklyn Heights Railroad) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cranford v. Brooklyn Heights Railroad, 168 A.D. 457, 154 N.Y.S. 16, 1915 N.Y. App. Div. LEXIS 8958 (N.Y. Ct. App. 1915).

Opinion

Thomas, J.:

The action is based on a contract whereby the plaintiff undertook between stated points to make a change in the right of way of defendant’s railway. The work in its principal features demanded excavation for a part of the distance and filling for a part thereof, and the construction of a concrete wall on each side beyond the limit of the right of way, for which purpose the defendant procured easements. The contract also included the construction of depots and stations, and contemplated that [458]*458the plaintiff should do extra work, with methods of payment not necessary to state. Differences arose involving numerous questions, and many items of recovery and counterclaim were considered by the Trial Term during a period of some fifty days. The subjects of inquiry were complex and most difficult of solution, but the facts were decided with such accuracy by the trial justice as to require slight modification. In some instances, usually relating to the interpretation of a single paragraph of the contract, this decision -affects conclusions of law. Every item has been examined with attention, but advantage would not come from a discussion of the facts, and, therefore, where the decision is modified the item is named and a brief statement of the reasons.for allowing or disallowing the same are stated. But before taking up such items, it may be stated that the finding that the defendant may deduct the cost of the steam shovel and digger from the amount due the plaintiff is approved. The evidence shows that the plaintiff would not have finished the work by May'1, 1907, had there been no delay caused by the defendant. Upon such state of facts the law does not permit the plaintiff to recover the cost of the shovel, which is, in fact,, an addition to the contract price to be gained by him in case he should complete the contract at the stipulated time. In other words, he cannot contribute so effectively to the delay as to prevent his finishing in time, and have the reward that could be earned only by such due completion. The 89th finding of fact that “ The contractor substantially completed the contract work within the time stipulated, as extended,” should be modified to read, “The contractor substantially completed his contract by August 10, 1907, save in respect to items for which allowances have been made to defendant.” Other finding, if needed, to conform the decision to this memorandum will be made.

Cause II, item, 1; reinforced concrete at Newkirk avenue, $$,$88.90.

This item should be disallowed. It is decided, first, that the evidence shows that the work was not reinforced concrete within the contemplation of the contract; second, that it was the function of the engineer to decide whether it was such reinforced concrete; third, that in the absence of other evidence [459]*459of the reasonable value of the work, the plaintiff should be awarded the sum fixed by the engineer, to wit, $14.85.

Cause II, item 3, $1,169.62.

The recovery should be at the rate of three cents a pound instead of five and one-half cents a pound. The contract fixes a price of five and one-half cents per pound for steel columns, “including column base and anchor bolts.” The grillage rails were not a part of the cast iron base, but of the concrete foundation. Although the original plans did not show such grillage in the concrete foundation of the canopy columns, the working plans did show the same. The cast iron base is something that is placed upon a concrete foundation and affixed thereto, while the steel rails or grillage are set in and made a part of the concrete foundation upon which the column base rests.

Cause III, item 1; moving derrick to sandpit, $180.70.

Cause III, item 2 ; moving derrick from sandpit, $261.75.

These items are disallowed for the reason that the new contract for the Foster avenue sewer was not only substituted for the original contract in that respect, but also in full discharge of all claims on the part of the contractor arising out of the construction of the sewer and of his original contract. This conclusion is aided by considering the manner of arriving at the sum that would be paid the plaintiff for the work and material under the new contract.

Cause III, item 3; delay to derrick north of Foster avenue, $11.

Cause III, item 1; delay to derrick at Luck’s Hotel, $27.50.

These items should be disallowed, as they fall within section 12 of the contract, which provides that plaintiff “shall not be entitled to any claim for damages for any hindrance or delay from any cause whatever, during the progress of the work.”

Cause III, item 9; non-removal of trolley pole, causing delay, $29.12.

The conclusion allowing this item is reversed for the reason that it falls under section 12 of the contract above noted.

Cause III, item 12; delay at Schmidt building, $12.25.

The conclusion allowing this item is reversed as falling within section 12 of the contract.

[460]*460 Cause IV, items 13 and 11¡.; delay after, inspection of derailed locomotive, $3.25; $1¡.3.30.

These items are disallowed as falling under section 12 of the contract.

Cause IV, item 73; delay due to bracket arms, $93.51.

This item is not recoverable under section 12 of the contract.

Canse IV, item 1; hand-mixing at Foster avenue, $1,082.17.

The conclusion allowing this finding is reversed. The demand grows out of delay which was caused by the necessity of a new plan for the Foster avenue sewer, respecting which a new, particular contract was made with the plaintiff. The plaintiff was hindered from continuing the wall when, in his progress northward, he approached the locality, and such hindrance delayed him to a time when a condition of the work created by himself precluded the use of the machine for concreting; hence the matter falls within section 12 of the contract, which disables plaintiff from recovering damages arising out of hindrance or delay from any cause. Moreover, the cause of action, if any, takes its rise from the interruption of the performance of the main contract. The substituted, particular contract for the sewer discharged all claims from such cause.

Cause TV, item 12; cost of trucking to wall above Avenue H, $31¡.2.

It is quite inconsistent to- allow this item and to disapprove of items 18, 20 and 40 of cause IV. I discover no finding of fault on the part of the defendant which justifies its allowance, nor am I satisfied that the evidence would justify such a finding. Indeed, the finding would not be in harmony, I think, with the findings of the court respecting the matter out of which this claim grows.

Respecting the items disallowed the plaintiff, it is considered that finding 471 (Cause IV, item 21, material on Wood-Harmon Company land), that it cost the contractor twenty-six cents per cubic yard more to haul the earth to raise the grades at Foster avenue and East Sixteenth street than it would have cost to place the material diverted to the Wood-Harmon property, is not sustained by the evidence, although the evidence does show that there was an increased cost, .and, there[461]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman Co. v. County of Nassau
27 A.D.2d 936 (Appellate Division of the Supreme Court of New York, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
168 A.D. 457, 154 N.Y.S. 16, 1915 N.Y. App. Div. LEXIS 8958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cranford-v-brooklyn-heights-railroad-nyappdiv-1915.