Cramp & Co. v. Boyertown Burial Casket Co.

88 A. 69, 241 Pa. 15, 1913 Pa. LEXIS 729
Supreme Court of Pennsylvania·Decided May 5, 1913·No. Appeal, No. 406·Published·Cited by 2 cases

Opinion

Opinion by

Mr. Justice Elkin,

This suit was brought to recover the balance due the contractor on a building, contract. The defendant claims a set off by way of liquidated damages for delay in completing the work. By agreement of the parties trial by jury was waived and the case was referred under the Act of May 14,1874, P. L. 166. In the agreement of reference it was stipulated that “the right of exception, writ of error and appeal being reserved to the parties only insofar as any question of law is concerned, it being understood and agreed that the referee’s findings of fact shall be final.” It will therefore be seen that the parties only reserved the right of exception and appeal on questions of law. On questions of fact the findings of the referee are final. This was the agreement of the parties and they are bound by it.. This stipulation in the reference eliminates from our consideration the first, second, seventh and eighth assignments of error. These assignments relate to findings of fact and the complaint is that the learned referee erred in his findings. It is difficult to understand how these questions can be raised on appeal when it was stipulated that the findings of fact by the referee should be final. The parties only reserved the right of exception and appeal on questions of law, and having made their own stipulation, as they had the right to do, this court is not at liberty to disregard it so as to open up all questions for review on appeal.

The contract provided that for each and every day, [18] except Sundays and legal holidays, in which the work is delayed beyond the time fixed for completion, the contractor shall be required to pay the owner the sum of fifty dollars to be deducted from the contract price. The referee found that there was a delay in completing the building of eighty-one days, and the question before him for decision was who was responsible for this delay. The contract further provided that if the contractor was obstructed or delayed in the prosecution of the work by the neglect or delay of the owner or architects or of any other contractor employed by the owner on the work, the time fixed for completion “shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid.” But it was also provided that “no such allowance will be made unless a claim thereof is presented in writing to the architects within five days of the occurrence of such delay, the duration of such extension to be certified by the architects.” Under this stipulation it was necessary for the contractor to present a claim in writing to the architects within the five-day period and failure to do so must be deemed a waiver of the right to demand an allowance of time for the delay. It will be seen at a glance that whether the contractor was obstructed or delayed in the prosecution of the work by the owner, and whether the claim for allowance of time for completion was made in writing within five days after the occurrence, depend upon the facts. In his thirteenth finding of fact the referee adopted a suggestion or recommendation of the architects that plaintiff had been actually delayed in the prosecution and completion of the building by the owner for at least fifty-six working days. In addition to these delays the referee found as a fact that plaintiff was further delayed in the prosecution and completion of the work at least twenty-five working days, making in all eighty-one days for which the contractor was entitled to an extension of time for completion. Then follows the fifteenth finding of fact: “The aggregate amount of the [19] delays which plaintiff thus suffered is, therefore, at least equal to the number of working days that elapsed between January 15 and May 1, 1908.” January 15, 1908, was the time fixed in the contract for completion, and May 1, 1908, was the date found by the referee when the work was substantially completed. Under these findings of fact it necessarily followed that appellant was not entitled to any deduction from the contract price on account of delay in completion because the delay was occasioned by the owner. It is urged by appellant that claims for delays were not presented in writing to the architects within the five-day period required by the contract and that the referee was not warranted in making allowances for delays for this reason. The answer to this position is found in the supplemental report of the referee in which there is the following finding of fact: “The notices of claims for delay required by Article VII, clause b, of the contract were duly given as to each of the items for which an allowance has been made by the referee.” ’This finding of fact was based upon the twentieth finding of the supplemental report in which parts of letters giving notice of the causes of delay and claiming an allowance for the same are set forth. We think the evidence was sufficient to warrant the finding. It is also contended that the referee erred in receiving these letters in evidence after the original report was filed but before the exceptions were disposed of. There is no assignment of error which raises this question. There was an exception to the finding but the admission of the letters in evidence is not assigned for error. The order of admitting the evidence was largely in the discretion of the referee and under the facts of this case there was no abuse of that discretion in the admission of these proofs.

Free access — add to your briefcase to read the full text and ask questions with AI

Cramp & Co. v. Boyertown Burial Casket Co., 88 A. 69, 241 Pa. 15, 1913 Pa. LEXIS 729 (Pa. 1913).

88 A. 69 (Cramp & Co. v. Boyertown Burial Casket Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Nail v. Browning
76 So. 679 (Supreme Court of Florida, 1917)
Holscher v. Ingalls Stone Co.
66 Pa. Super. 76 (Superior Court of Pennsylvania, 1917)