Crain v. Yatebs

178 S.W. 679, 1915 Tex. App. LEXIS 806
CourtCourt of Appeals of Texas
DecidedJune 21, 1915
DocketNo. 6967.
StatusPublished
Cited by2 cases

This text of 178 S.W. 679 (Crain v. Yatebs) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crain v. Yatebs, 178 S.W. 679, 1915 Tex. App. LEXIS 806 (Tex. Ct. App. 1915).

Opinion

McMEANS, J.

Henry H. Tates sued E. L. Crain in tbe county court at law of Harris county, alleging substantially that at the special instance and request of the defendant he agreed to build on certain premises of the defendant in Montrose addition to the city of Houston, a frame-stucco one-story, six room dwelling house, complete, and ready for’occupancy, with water and light connections, and that the defendant agreed to pay him the reasonable value of the work and material to be furnished by the plaintiff in the construction of the house; that in pursuance of the terms of his agreement, he erected and completed the house, and that defendant accepted it as in compliance with the contract; that the reasonable value of the work and material used in the construction of the house was §2,500 ; that defendant paid him on said job $2,140, but failed and refused to pay the balance of $360, for which the- suit was brought. Defendant admitted that the plaintiff agreed to erect for him the kind of house referred to in the petition, but denied that he ever agreed or promised to pay the plaintiff the reasonable value of the work and material furnished on the job, but that, on the contrary, the plaintiff contracted and agreed to erect and complete the house, with water and light connections, for a fixed sum, to wit, $2,140 cash, upon the completion of the work. Defendant alleged he had paid the $2,140 as agreed, and admitted that he had refused to pay the balance of $360, or any other amount claimed by the plaintiff. By supplemental petition plaintiff traversed the affirmative allegations of the answer, and additionally alleged that defendant, if he did not expressly agree to pay the reasonable value of the work and material furnished, was impliedly bound to do so by his acceptance of the work after completion. Other allegations were made, but the court made no findings of fact thereon, and it will be unnecessary to make further reference to them. The case was tried before the court without a jury and resulted in a judgment for plaintiff for $278, from which the defendant has appealed.

By his first assignment of error appellant contends that the judgment is contrary to the law and to the facts found by the court, and by his second assignment he urges that:

“The court erred in its conclusion of law in holding that under the facts found no contract for the erection of the proposed house existed between Crain and Tates concerning the price to be paid therefor, and that in the absence of a contract, fixing the price, the price to be paid was the reasonable value of the work and the materials furnished and the labor done, when combined in a completed house.”

The court upon proper request reduced to writing and filed its findings of fact, which we here copy in full:

“Crain was a real estate man, engaged in the business of furnishing to purchasers completed properties, including houses and lots. Tates was a contractor, engaged in the business of building houses. Those two parties had a conversation or conversations which led up to the business transactions subsequently between them, wherein Tates in order to get the business of Crain, agreed to figure his prices for building operations contemplated on the basis of actual cost and 1^2 per cent, thereon as profits to the contractor. Subsequently, Crain and Tates entered into a written contract, whereby Tates was to build a house, referred to between the parties in this case as Crain No. 1 job. After No. 1 was completed by Tates, and paid for by Crain, another house was built by Tates for Crain, and paid for by the latter. During the erection of these two houses, one Lindsay was carpenter foreman for Tates, and had been working in that capacity for Tates for a couple of years. It was customary for Tates to permit him to figure on the cost of lumber and of labor on jobs, which figures would be taken by Tates and used in his estimates in arriving at contracts. ’ ,
“While the second house above referred to was under way, and almost completed, Crain told Tates that he was figuring on erecting a house for McMurray, and showed Tates a sketch of floor plans for the contemplated house, and discussed with Tates the general nature of the house, and asked Tates to figure on a price for building the house. Tates had blueprints made, and discussed with Lindsay the estimate of the cost of the supposed house. In this discussion between Tates and Lindsay, as well as between Tates and Crain, concerning the proposed house, it was considered as a house of very nearly the same sort and character as the Crain job No. 1, above referred to. Tates never individually quoted any figures on this supposed house to Crain, hut Lindsay, being Tates’ carpenter foreman, and knowing that the matter of the proposed house was under discussion and consideration between Tates and Crain, met with Grain and told Crain that he, for Tates, had figured on the probable cost of the proposed house, and submitted his estimate to Crain thereon, as follows: $2,055 being the actual cost to the contractor of Crain No. 1 job, plus $50 for water heater not included in Crain job No. 1, less $115, being cost of barn included in Crain job' No. 1, no barn being included in the job figured on, plus $150 as profits to the contractor, totaling $2,140. This amount of this estimate Crain says Lindsay quoted him as what the total cost would be, and at which Tates would build the house, while Lindsay says he merely submitted it as an estimated cost, and had no instructions from Tates to enter into a contract with Crain, and that he did not do so, and that he told Crain it was merely his estimate of the cost, supposing that Tates and Crain would make their own contract with reference to the erection of the building. With reference to this conflict between the testimony of the two gentlemen, I am compelled to resolve the doubt in favor of the testimony of Lindsay, who seems to be entirely disinterested. After seeing Crain and making him this estimate of $2,140, Lindsay went to Tates and told him that he had made the estimate at $2,140 to Crain. On the day following that on which Lindsay so told Tates, the erection of the house in question, and concerning which the above matter transpired, was begun by Tates, and prosecuted to completion, without any further understanding or agreement between Tates and Crain or any one for him. The total cost of the house, including materials, money actually paid for labor, was $2,249.30, 7Y¡¡ per cent, of which is *681 $168.70. The reasonable value of the house as erected was between $2,400 and $2,500. I find as a definite amount, for the purpose of arriving at a conclusion, the sum of $2,418 which I find to be the actual cost, plus 7% per cent, thereof, which I think is a fair valuation. Crain has paid $2,140 to the plaintiff, it being agreed between the parties at the time of such payment that it should be made without prejudice to either party. The balance thus left remaining is $278.”

At the reguest of the defendant, the court found the following additional and supplemental findings of fact:

“First. That Crain told Yates, when he requested him to figure on the job, that he would have to know what it would cost before he could tell whether he would be able to make a deal with McMurray, the contemplated purchaser, or not.
“Second.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chapman v. Head
5 S.W.2d 1001 (Court of Appeals of Texas, 1928)
Arbaugh v. Robinson
286 S.W. 339 (Court of Appeals of Texas, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
178 S.W. 679, 1915 Tex. App. LEXIS 806, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crain-v-yatebs-texapp-1915.