Craig v. Uyeoka

32 Haw. 913
Hawaii Supreme Court·Decided December 19, 1933·No. No. 2104.·Published

Opinion

*914 OPINION OF THE COURT BY

PERRY, C. J.

The defendant Uyeoka entered into a contract for the erection of a building for the plaintiffs and the defendant corporation became the surety on a bond given to the plaintiffs for the faithful performance of the contract of construction. The building was completed on May 3, 1930. This is an action on the bond for the recovery of damages for the loss suffered by the plaintiffs by reason of alleged partial nonperformance of the contract by Uyeoka. The trial was had without a jury and the presiding judge rendered judgment for the plaintiffs in the sum of $1758.49, together with interest and costs or a grand total of $2115.72. Thereupon the defendants brought the case to this court upon a bill of exceptions.

The Fiebig company furnished materials that were *915 used in tlie construction of the building to the amount of $795.43 and the Smith Lumber Company to the amount of $212.96, or a total of $1008.39. On June 14, 1930, before the expiration of the statutory period of forty-five days during which notices of lien were permitted by law to be filed, these two companies made demand upon the plaintiffs for the payment of the amounts due them, accompanying the demands with threats to file liens in the event of nonpayment. Thereupon the owners paid these two bills and their claim for reimbursement of these amounts by the defendants was sustained in the judgment rendered.

While these two claims of the materialmen were of a lienable nature, no liens had as a matter of law attached, at the time of payment, to the building or to the land upon which it stood. As has been held by this court liens for materials and labor used in the construction of a building do not attach to the building or to the land by mere reason of the fact of the furnishing of the material or the labor but only after compliance with two other statutory prerequisites, to-wit, the filing in the office of the clei’k of the circuit court where the property is situated of a notice of the lien and the service upon the owner of the property of a copy of the notice. § 2892, R. L. 1925; Lucas v. Redward, 9 Haw. 23; Lewers & Cooke v. Jones, 25 Haw. 214. And the lien is not enforceable by judicial proceedings except after demand upon the owner and refusal of payment of the amount due. §2895, R. L. 1925; Lewers & Cooke v. Fernandez, 23 Haw. 744; Lewers & Cooke v. Wong Wong, 24 Haw. 39. The proceeding is somewhat technical, the statute must be complied with in order to fully create a lien and to render it enforceable and it does not necessarily follow that because there is an attempt at compliance the attempt will succeed. Instances have occurred where attempts *916 of that nature have proved to be failures. The contractor in the case at bar had undertaken, as a part of his contract, to deliver the building not only completed but free of liens. The surety was entitled to the full statutory period of forty-five days from the completion of the building in Avhich to cause such arrangements to be made as might be necessary or possible for the avoidance of the creation of liens and it was also entitled to the benefit of the failure, if any, on the part of the materialmen, for whatever reason, to take the steps required by law in order to bring the liens into existence. At the time of the making of the threats and of the payment, notice of lien had not been filed and there Avere no liens in the two instances under consideration. The payments by the plaintiffs must therefore be deemed to have been voluntary and the plaintiffs are not entitled to recover .for the two amounts so paid. See Morley v. Carlson, 27 Mo. App. 5, 8, 9; Simonson v. Thori, 31 N. W. (Minn.) 861, 862.

After the building had been constructed to the extent that installments aggregating $5300 had been paid on account of the contract price of $8000 in complete accordance with the requirements of the contract, there were various occasions when the work practically came to a standstill, due in some instances to refusal of laborers to Avork on the job for the° contractor and in other instances to the inability of the contractor, for lack of credit, to purchase needed materials. On each of these occasions the owners promptly notified one Herman Luis, Avho in these matters Avas acting for the insurance company, of the defaults of the contractor. On some of these occasions, Avith reference to lack of labor, Mr. Luis said that he would speak to the contractor arid endeavor to obtain a resumption of the Avork. On other occasions, Avith reference to materials, Mr. Luis, as the court below *917 found, authorized and requested the owners to purchase the materials in their own names and to pay for them, adding, “We must carry on.” In pursuance of these authorizations and requests the owners purchased materials and paid for them. It is admitted that the materials so purchased were used in the construction of the building. The judgment rendered in favor of the plaintiffs included these items.

Free access — add to your briefcase to read the full text and ask questions with AI

Craig v. Uyeoka, 32 Haw. 913 (haw 1933).

32 Haw. 913 (Craig v. Uyeoka) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lucas v. Redward
9 Haw. 23 (Hawaii Supreme Court, 1893)
Lewers & Cooke, Ltd. v. Fernandez
23 Haw. 744 (Hawaii Supreme Court, 1917)
Lewers & Cooke, Ltd. v. Wong Wong
24 Haw. 39 (Hawaii Supreme Court, 1917)
Lewers & Cooke, Ltd. v. Jones
25 Haw. 214 (Hawaii Supreme Court, 1919)
Morley v. Carlson
27 Mo. App. 5 (Missouri Court of Appeals, 1887)