CPS 1 Realty v. R.P. Brennan General Contractors & Builders, Inc.
This text of 66 A.D.2d 418 (CPS 1 Realty v. R.P. Brennan General Contractors & Builders, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Orders, Supreme Court, New York County (Barbara R. Kapnick, J.), entered March 10, 2009, which denied petitioner’s motions to stay arbitration and granted respondent’s motion to dismiss this proceeding, unanimously affirmed, with costs.
On a motion to stay arbitration, the court’s “gatekeeper” role is limited to deciding whether there was a valid arbitration agreement, whether the parties complied with the agreement, and whether the claim to be arbitrated was barred by the statute of limitations (see Cooper v Bruckner, 21 AD3d 758, 759 [2005]).
Here, the court properly found that the issue of respondent’s failure to provide timely notices to petitioner, “though couched in terms of satisfaction of a condition precedent to arbitration, is in actuality nothing more than an allegation of noncompliance with the substantive terms of the contract, a matter plainly encompassed by the arbitration clause” (Matter of MontgomeryOtsego-Schoharie Solid Waste Mgt. Auth. [Bonded Insulation Co.], 215 AD2d 995, 996 [1995]). Concur—Saxe, J.P., Sweeny, Moskowitz, Acosta and Richter, JJ. [See 22 Misc 3d 1135(A), 2009 NY Slip Op 50451(H).]
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
66 A.D.2d 418, 885 N.Y.S.2d 601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cps-1-realty-v-rp-brennan-general-contractors-builders-inc-nyappdiv-2009.