CP National Corp. v. Jura

876 F.2d 745, 1989 WL 54292
CourtCourt of Appeals for the Ninth Circuit
DecidedMay 25, 1989
DocketNos. 85-7536, 85-7542
StatusPublished
Cited by5 cases

This text of 876 F.2d 745 (CP National Corp. v. Jura) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CP National Corp. v. Jura, 876 F.2d 745, 1989 WL 54292 (9th Cir. 1989).

Opinion

SCHROEDER, Circuit Judge:

This is a petition to review rate schedules enacted by the Bonneville Power Administration in 1983. Petitioner Puget Sound Power and Light Company is an investor-owned utility serving retail customers in Washington, and petitioner Public Generating Pool is a group of nine publicly-owned utilities serving customers in Washington and Oregon. In this proceeding they challenge the “availability charge” contained in the 1983 Priority Firm Power Rate Schedule (“PF-83”) for publicly-owned utilities, and the 1983 New Resources Firm Power Rate Schedule (“NR-83”) for investor-owned utilities. This “availability charge” has the effect of requiring petitioners to pay rates based on how much power they are empowered to purchase from the BPA under their power sales contracts, not solely on the actual amount of power purchased. Petitioners ask us to invalidate this rate mechanism because petitioners claim that it conflicts with the provisions of their contracts with the BPA for the purchase of power.

This matter has had a complex procedural history which will be explained more fully below. Most recently, petitioners moved to transfer this matter to the Claims Court, so we must deal with a threshold jurisdictional issue before reaching plaintiffs’ challenge to the validity of the rate provisions. We conclude that under the Pacific Northwest Electric Power Planning and Conservation Act, as recently interpreted by this court in Public Utility Dist. No. 1 of Clark County v. Johnson, 855 F.2d 647, 650 (9th Cir.1988), this court, rather than the Claims Court, has jurisdiction to review this rate determination. 16 U.S.C. § 839f(e)(1)(G) (1982). We further [747]*747hold on the merits that petitioners have not shown any basis for invalidating the availability charge.

Procedural Background and Jurisdiction.

These claims were originally brought before this court in City of Seattle v. Johnson and Puget Sound Power and Light Co. v. Johnson (the “City of Seattle Cases”). Those cases were dismissed for lack of jurisdiction because the 1983 rates challenged had not yet been approved by the Federal Energy Regulatory Commission and were thus not yet final. City of Seattle v. Johnson, 813 F.2d 1364, 1368 (9th Cir.1987). On July 2, 1985, FERC confirmed and approved the 1983 BPA rates. 32 FERC ¶ 61,014 (1985). Petitioners timely filed their petition for review in this court pursuant to 16 U.S.C. § 839f(e)(5) within 90 days of final FERC approval.

In a motion filed with this court September 19, 1988, petitioners sought to transfer the action to the U.S. Claims Court pursuant to 28 U.S.C. § 1631 (1982). Petitioners argue that this court’s decision in Public Utility Dist. No. 1 of Clark County v. Johnson, 855 F.2d 647 (9th Cir.1988), signifies that the U.S. Claims Court is the exclusive forum for their claims, because petitioners now choose to characterize their claims as sounding in contract. They assert that the availability charges included in the 1983 rates constitute a “breach” of petitioners’ power sales contracts with BPA.

Despite the words used to characterize petitioners’ grievance, however, its focus is on the 1983 rates. Neither the Pacific Northwest Power Act nor any of our decisions interpreting it support petitioners’ argument that the Claims Court has jurisdiction over an action which calls for review of ratemaking by the BPA. The Act provides that:

Suits to challenge ... final actions and decisions taken pursuant to this chapter by the Administrator or the Council, or the implementation of such final actions ... shall be filed in the United States Court of Appeals for the region.

16 U.S.C. § 839f(e)(5) (1982). Under the Act, final rate determinations are “final actions” by the BPA, and challenges to such rate determinations must be filed in this court. 16 U.S.C. § 839f(e)(1)(G) (1982); see also Central Lincoln Peoples’ Utility Dist. v. Johnson, 735 F.2d 1101, 1108-09 (9th Cir.1984) (“Central Lincoln II”). We have noted in the past that, in providing for direct review by this court, Congress intended to facilitate prompt action on challenges to BPA’s decisions. See Public Power Council v. Johnson, 674 F.2d 791, 795 (9th Cir.1982).

A party’s characterization of its claim as one for breach of contract is not dispositive of jurisdictional issues. In Pacific Power and Light Co. v. Bonneville Power Administration, 795 F.2d 810, 816 (9th Cir.1986), we stated that in enacting section 839f(e)(5), Congress has decided that jurisdiction under the Act should be a “function of the agency whose actions are being challenged rather than a function of the cause of action which petitioner asserts.” In City of Seattle v. Johnson, 813 F.2d 1364, 1368 (9th Cir.1987), we said with respect to this very dispute that challenges to the rate changes were not ripe for review by this court until final approval by FERC, irrespective of the fact that the challenge was characterized as a breach of contract claim. We have consistently exercised jurisdiction where the action being challenged is in reality final ratemaking pursuant to BPA’s statutory authority, regardless of the petitioner’s characterization of its claim. See Atlantic Richfield Co. v. Bonneville Power Administration, 818 F.2d 701, 705 (9th Cir.1987) (reviewing claim that customer charge imposed in 1983 rates constituted a breach of contract); Pacificorp v. FERC, 795 F.2d 816, 818-20 (9th Cir.1986) (court of appeals had jurisdiction to review BPA’s revision of cost methodology, although claim was characterized as one for breach of contract).

Our recent decision in Public Utility Dist. No. 1, upon which petitioners rely, is not to the contrary. Its reasoning actually lends support to our exercise of jurisdiction here. In Public Utility Dist. No. 1, a [748]*748public utility challenged not an aspect of a rate, but BPA’s refusal to purchase one of the utility’s power resources. Public Utility Dist. No. 1, 855 F.2d at 648. The utility alleged the existence of an oral or implied-in-fact contract in which the BPA agreed to purchase the power source. Id. This court held that it had no jurisdiction over the utility’s contract claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
876 F.2d 745, 1989 WL 54292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cp-national-corp-v-jura-ca9-1989.