Cove Creek Development Corp. v. APAC-Alabama, Inc.

588 So. 2d 458, 1991 Ala. LEXIS 684, 1991 WL 137322
CourtSupreme Court of Alabama
DecidedJune 28, 1991
Docket1900253
StatusPublished
Cited by13 cases

This text of 588 So. 2d 458 (Cove Creek Development Corp. v. APAC-Alabama, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cove Creek Development Corp. v. APAC-Alabama, Inc., 588 So. 2d 458, 1991 Ala. LEXIS 684, 1991 WL 137322 (Ala. 1991).

Opinion

APAC-Alabama, Inc. ("APAC"), brought a breach of contract action against Cove Creek Development Corporation ("Cove Creek"). APAC alleged that Cove Creek had wrongfully withheld $81,509.12 from payment for work APAC had performed for Cove Creek as a contractor. Cove Creek argued that under the terms of the construction contract it was entitled to withhold $300 per day as liquidated damages for each day that APAC was late in completing its contract. After an ore tenus hearing, the trial court held in favor of APAC and awarded it $81,509.12 in damages. We reverse and render a judgment in favor of Cove Creek.

The parties entered into a construction contract on May 20, 1988. The contract called for the work to be completed by a deadline of October 20, 1988. The work consisted primarily of site grading, installing storm sewers and a drainage system, and construction of curbs, gutters, and roads. Cove Creek also awarded a contract to R M Construction Company ("R M") for utilities work to be completed by August 20, 1988. APAC claimed that it was forced to abandon the construction site from August 19, 1988, until September 19, 1988, because of R M's work. Because of the delay that R M had caused, Cove Creek moved the deadline back 45 days to December 4, 1988. APAC, however, did not complete construction until September 15, 1989. Consequently, Cove Creek withheld $81,509.12 pursuant to the terms of a liquidated damages clause in the contract. According to the provisions of the liquidated damages clause, APAC would pay Cove Creek $300 for every day past the deadline (adjusted to December 4, 1988). This clause also provided that Cove Creek would pay $300 to APAC for each day that APAC completed the work before the deadline.

When APAC completed construction on September 15, 1989, Cove Creek withheld $81,509.12 on the grounds that APAC had finished construction 285 days late.1 APAC sued Cove Creek for breach of contract, claiming that no money should have been withheld under the liquidated damages clause because, it said, all of the delays were either caused by R M, changes in the specifications, or an excessive amount of rain at the construction site during the contract period. The trial court held in favor of APAC, holding that APAC's delay was excused for the following reasons:

"[Cove Creek] was issuing change orders to the plans and specifications into August of 1989, well after the completion date [of October 20, 1988] called for in the contract. Evidence showed that while rainfall for the months of May 1988 to October 1988 averaged approximately 3.73 inches below the ten (10) year average for the affected area, rainfall *Page 460 for the months of November 1988 to September 1989 was approximately 20.32 inches above average. Evidence was further offered to show that this amount caused the soil used to construct the road bed to pump and yield,2 and did not allow the sub-grade to stabilize. Testimony reflected that [APAC] continued attempts to stabilize the sub-grade well into 1989. Written evidence documented that [APAC] was instructed in late April of 1989 not to lay the final layer of paving until so authorized by the project engineers.

"[A witness for APAC] testified that [APAC] finished the contract work and change order items in September 1989, and invoiced [Cove Creek] for the final work. Evidence reflects that [Cove Creek] continued to obtain final approvals for the subdivision into November 1989, but made a final progress payment to [APAC] on September 18, 1989, wherein [Cove Creek] withheld approximately $81,509.12 from the contract amount requested by the plaintiff. ". . . .

"This order is based on a consideration of the pleadings, the pre-trial briefs submitted by attorneys for both [APAC] and [Cove Creek], applicable law, written evidence, testimony of witnesses and oral arguments of counsel. Based on the entire record in this case, the court finds that [APAC's] delay in completing the above-described work by the date stipulated in the contract was totally excused as a result of interference with the said work by a utilities contractor [R M] hired by [Cove Creek], by changes to the plans and specifications initiated by [Cove Creek] well after the target completion date stated in the contract and by adverse weather conditions not reasonably anticipatable or foreseeable at the time the contract was entered into."

Cove Creek argues on appeal that the trial court erred because, it says, portions of the contract specifically govern any excusable delay. Cove Creek first points out that this construction contract stated that time was of the essence and then contained a liquidated damages clause applicable to any delays:

"The number of days in which the contractor [APAC] shall fully perform the proposed work has been set out in the proposal and/or contract. The date of beginning and the time for completion of the work are essential conditions of the contract.

". . . .

"The contractor shall commence work on a date to be specified in a written order of the engineer, and shall fully complete all work under the contract within the number of days set out in the proposal and contract. As set forth in the proposal and contract, the work under the contract will be subject to liquidated damages in the event the work is not completed within the contract time.

"Should the contractor fail or refuse to complete the work within the time specified in his proposal and/or contract (or extension of time granted by the owner [Cove Creek]), the contractor shall pay liquidated damages in an amount set out in said proposal and/or contract.

"Liquidated damages: If the contractor shall fail to complete work by October 20, 1988, the contractor shall pay to the owner liquidated damages in the stipulated amount of $300.00 per day for each calendar day of delay, until the work is accepted. Owner also agrees to pay contractor $300.00 per day for each day work is completed before October 20, 1988."

The contract also provided for adjustments to the completion date made necessary by unavoidable delays, overruns, or additions to the contract:

"In arriving at any credit due the contractor [APAC] for an extension of time on the contract, the owner [Cove Creek], upon the recommendation of the engineer, *Page 461 may allow such credit as in his judgment is deemed equitable and just for all delays occasioned by any act, or failure to act, on the part of the contractor or caused by forces beyond the contractor's control. Additional time will also be allowed the contractor to cover approved overruns or additions to the contract in the same proportion that the said over-runs or additions in monetary value bears to the original contract amount.

"Time extensions may be granted upon proper justification by the contractor. Any claim for time extensions under these provisions shall be submitted in writing to the engineer not more than twenty (20) days following commencement of the delay; otherwise the claim will be waived."

The above provisions were the sole remedy provided in the contract for any delay in the construction. The contract also provided:

"The contractor shall make no claim for extra compensation due to delays of the project beyond his control. Such delays may include those caused by any act of neglect on the part of the owner or the engineer, or by any employee of either, or by any separate contractor employed by the owner [i.e., R M], or by any changes ordered in the work

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green v. Beard & Beard Attorneys
255 So. 3d 775 (Court of Civil Appeals of Alabama, 2017)
Schweiger v. Town of Hurtsboro
68 So. 3d 181 (Court of Civil Appeals of Alabama, 2011)
Mahoney v. Loma Alta Property Owners Ass'n
52 So. 3d 518 (Supreme Court of Alabama, 2010)
Adams v. Adams
21 So. 3d 1247 (Court of Civil Appeals of Alabama, 2009)
Mahoney v. Loma Alta Property Owners Ass'n
52 So. 3d 510 (Court of Civil Appeals of Alabama, 2009)
The Sanderson Group, Inc. v. Smith
809 So. 2d 823 (Court of Civil Appeals of Alabama, 2001)
Housing Auth. of City of Chickasaw v. Cbe, Inc.
656 So. 2d 1219 (Court of Civil Appeals of Alabama, 1995)
Becraft v. Becraft
628 So. 2d 404 (Supreme Court of Alabama, 1993)
Brashear v. Spinks
623 So. 2d 321 (Court of Civil Appeals of Alabama, 1993)
PACIFIC ENT. OIL v. Howell Petroleum
614 So. 2d 409 (Supreme Court of Alabama, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
588 So. 2d 458, 1991 Ala. LEXIS 684, 1991 WL 137322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cove-creek-development-corp-v-apac-alabama-inc-ala-1991.