Courtyard on Coventry v. Giambrone Masonry, Unpublished Decision (3-9-2000)

CourtOhio Court of Appeals
DecidedMarch 9, 2000
DocketNo. 75271.
StatusUnpublished

This text of Courtyard on Coventry v. Giambrone Masonry, Unpublished Decision (3-9-2000) (Courtyard on Coventry v. Giambrone Masonry, Unpublished Decision (3-9-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Courtyard on Coventry v. Giambrone Masonry, Unpublished Decision (3-9-2000), (Ohio Ct. App. 2000).

Opinion

JOURNAL ENTRY AND OPINION
Plaintiff Courtyard on Coventry ("Courtyard") appeals from the judgment of the trial court which directed a verdict in favor of Giambrone Masonry, Inc. and its president, David Giambrone, (collectively referred to as "Giambrone") on Giambrone's counterclaim for payment for masonry services. For the reasons set forth below, we affirm.

In June 1996, Courtyard, through its Trustee, Lewis A. Zipkin, entered into an agreement with Giambrone for the performance of the masonry portion of construction of a multi-unit retail structure located at 1854-1876 Coventry Road in Cleveland Heights. On June 20, 1996, Zipkin sent a proposed agreement to Giambrone which indicated that Giambrone was to receive $314,600 and the work was to include, inter alia, face brick, concrete block, and installation of "Durawall," a ladder-shaped wire which connects exterior and interior masonry walls. Giambrone indicated on the proposed agreement that it would perform the project for $320,000 and excluded various items (other than "Durawall") from the job. Further, although both the proposal sent by Zipkin and the reply sent by Giambrone contained language by which the parties could designate "substantial completion" dates, no date of substantial completion was ever listed in the written documents.

Giambrone worked at the site from June 24, 1996 until December 12, 1996. On January 8, 1997, David Giambrone, completed an affidavit for a mechanic's lien at the premises in which he averred that Giambrone was owed $65,609.26, plus interest, on the project.

On January 24, 1997, Courtyard filed a complaint against Giambrone Masonry and David Giambrone. In relevant part, Courtyard alleged that the parties orally agreed that Giambrone would "complete the project with haste," not later than the end of summer 1996. Courtyard claimed that Giambrone did not use due diligence to complete the project, failed to substantially complete the project by the summer of 1996, and did not complete the project at all. Courtyard further alleged that Giambrone also breached oral agreements to keep the same foreman for the duration of the project, to staff the project with full crews, and to perform with high quality workmanship and in compliance with applicable building and safety codes. Courtyard asserted causes of action in fraud and negligence. It sought compensatory damages for expenses to complete the project, and loss of potential income, and also sought punitive damages.

Giambrone denied liability and asserted a counterclaim in which it alleged that it had substantially complied with all the terms of the agreement and that it was owed $79,944.14. Giambrone also filed a third party complaint against the county treasurer for foreclosure upon its mechanic lien.

The matter came to trial before a jury on August 16, 1998. For its key evidence, Courtyard presented the testimony of structural engineer and registered architect Joseph Nyzen, leasing agent Stephen Passov (by deposition), Stuart McLean (by deposition), Gary Rogalski (by deposition), Greg Bankhurst, construction manager for the project, and owners Andrew Goldstein and Lewis Zipkin.

Nyzen testified that a delivery truck struck the north corner of the building and, after examining the resulting damage, the owners requested that Nyzen view the building and determine whether the masonry work was properly performed. Nyzen viewed the structure from scaffolding and also probed the inside of some of the walls. According to Nyzen, the ties which the masons had used to connect the brick exterior wall to the block interior wall did not meet the drawings and specifications for the building and did not comply with the code. Nyzen testified that three-sixteenth rod anchors were to be installed at sixteen inch intervals stretching across and above. The failure to use these rods increased the risk that the building would buckle and that the brick wall would come off in a very high wind. Nyzen testified that it would cost between $90,000 and $130,000 to repair the problem.

He also testified that the interior walls were not properly crisscrossed and bonded at the corners. This problem could lead to localized breakage and leakage and plaintiff subsequently bonded the corners of the building in order to remedy this problem. Nyzen was also concerned that limestone had not been properly anchored to the front of the building.

On cross-examination, Nyzen admitted that he was retained by plaintiff two weeks prior to a scheduled trial date. He also admitted that he had no knowledge of whether plaintiff's construction manager ever voiced any complaint with the masonry work as it was being performed. He did not review the job logs for the project in order to determine whether a change order had been issued but, he admitted, such changes are commonplace. He did not know whether the corner of the building which was damaged was constructed by defendant or a second mason hired to finish the job.

Passov, a real estate broker, testified that he was the leasing agent and that plaintiff lost potential tenants because the building was not complete by the Christmas season of 1996. The building was not rented until the summer of 1997.

Stuart McLean, president of Avalon stores, testified that he had negotiated with Zipkin to lease a portion of the building. He hoped to open before the Christmas season, but after numerous postponements, decided not to go forward with the project. Rogalski testified that he considered the site for a pizzeria, but ultimately determined that the construction was not moving at a satisfactory pace and was concerned that other portions of the building had not been rented.

Greg Bankhurst testified that he received various masonry bids for the project then set up interviews of the candidates. He and Zipkin's son, Andrew Goldstein, met with David Giambrone and Matt Birch of Giambrone. At this meeting, Bankhurst and Goldstein told Giambrone that they expected the same foreman to be on the job from beginning to end, that there would be proper staffing, and that things were done "on time" because they wanted the building opened for the Christmas season. Plaintiff was to provide most of the materials, but, according to Bankhurst, the anchors and ties for the project were to be supplied by Giambrone.

Bankhurst also testified that Giambrone worked continuously on the project from June 24, 1996 until October 24, 1996. On July 12, 1996, Birch sent Bankhurst a memo in which he indicated that Giambrone would not be present at the site for a while because of complaints that they had with the job, and masonry work subsequently ceased for one week. According to Bankhurst, the complaints concerned matters that had no effect upon Giambrone's ability to perform its portion of the contract and did not provide valid reasons for stopping work. Bankhurst also claimed that Giambrone simply had another job to perform at this time. Thereafter, Giambrone did not properly staff the job.

Finally, Bankhurst outlined for the jury numerous written change orders which concerned Giambrone's permitted deviations from the written specifications. Each outlined the change and the resulting cost, and one such change order concerned addition of heavy plastic and portable heaters ("winter protection") which were not anticipated when the project was bid. He also stated that Giambrone was paid each month but did not finish the job. He denied that other tradesmen refused to perform their portions of the job because they had not been paid.

On cross-examination, Bankhurst acknowledged that he had written a letter to the architect regarding his refusal to attend additional meetings until he received additional funds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Muskingum Watershed Conservancy District v. Funk
16 N.E.2d 454 (Ohio Supreme Court, 1938)
Ornella v. Robertson
237 N.E.2d 140 (Ohio Supreme Court, 1968)
Hake v. George Wiedemann Brewing Co.
262 N.E.2d 703 (Ohio Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
Courtyard on Coventry v. Giambrone Masonry, Unpublished Decision (3-9-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/courtyard-on-coventry-v-giambrone-masonry-unpublished-decision-3-9-2000-ohioctapp-2000.