County of Mariposa v. Yosemite West Associates

202 Cal. App. 3d 791, 248 Cal. Rptr. 778, 1988 Cal. App. LEXIS 615
CourtCalifornia Court of Appeal
DecidedJune 30, 1988
DocketF008068
StatusPublished
Cited by14 cases

This text of 202 Cal. App. 3d 791 (County of Mariposa v. Yosemite West Associates) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Mariposa v. Yosemite West Associates, 202 Cal. App. 3d 791, 248 Cal. Rptr. 778, 1988 Cal. App. LEXIS 615 (Cal. Ct. App. 1988).

Opinion

Opinion

STONE (W. A.), J.

In December 1966, appellants, Yosemite West Associates 1 (YWA), presented to respondent, County of Mariposa (County), plans to develop approximately 900 acres of land adjacent to Yosemite National Park into a recreational area which would include home sites, condominiums, town houses, a hotel, restaurants, a commercial area and recreational facilities. The first phase of the project was to subdivide 135 acres of land into a 293-lot residential area called “Yosemite West Subdivision, Unit Number One” (Unit #1). In 1967 YWA and the County entered into a subdivision agreement for Unit # 1 which provided, in pertinent part, that YWA would complete all necessary improvements, including water system, water storage and fire hydrants; initiate and consummate assessment bond proceedings for the completion of the improvements; and initiate the formation of Yosemite West Maintenance District (Maintenance District). The agreement further provided that YWA “shall indemnify and hold harmless the County from any and all loss, damage, or liability resulting from [YWA’s] performance or non-performance of [its] duties” under the agreement.

YWA retained the services of James W. Tolladay, a civil engineer with the firm of Jorgenson and Tolladay, to prepare the necessary plans, specifications and other documents for the construction and installation of *798 the improvements. In a letter to YWA’s president and general manager, John Doubt, Tolladay urged Doubt to persuade the County to appoint Tolladay as “Engineer of the Work” so that Tolladay could adequately look out for YWA’s interests. Tolladay was appointed engineer of the work and as such had complete control over the project. The County put the project out for bid in 1967, and the construction firm of Georgé Reed, Inc. was selected as the general contractor. Tolladay prepared all of the contract documents sent out to bid. The County also hired the firm of Hanna Brothers to do the final inspection of the project; however, Tolladay’s interpretation of the plans and specifications was controlling, and Tolladay’s decisions were final.

In April 1971, YWA entered into an agreement with defendant and appellant, Interwest Corporation of Utah, to develop the second phase of the project which involved the building of 48 condominiums on approximately 1.2 acres of land adjacent to Unit #1. YWA was responsible for the land development, including off-site improvements such as the water and sewer systems, and Interwest was responsible for the construction and sale of the condominiums.

In January 1972, Doubt presented the proposed map and summarized the condominium project for the Mariposa County Planning Commission. The planning commission unanimously rejected the project based upon the advice of two county engineers that the existing water and sewer systems in the Yosemite West Maintenance District that were designed to meet the needs of the homeowners in Unit # 1 would not be adequate to meet the additional needs of the condominium project. This decision was appealed to the Mariposa County Board of Supervisors who approved the project based upon promises by YWA that several conditions would be met before the condominiums were sold. These promises were embodied in the February 1973 agreement between YWA, Interwest and the County. First, 10 acres were to be dedicated to the County to be used by the Maintenance District for sewer plant expansion. Second, YWA would develop a well that would provide 100 gallons of potable water per minute to be proven and tested to county standards. Third, all necessary parts of the water and sewer systems were to be dedicated to the County within 12 months of the date of the agreement. Until the 100-gallons per minute requirement was reached on the existing water system, the condominium project was allowed to hook up with the Maintenance District, but could use only one of three wells (well No. 2) within the system so that homeowners in Unit # 1 would not experience a loss of water supply. In April 1973 the agreement was amended to provide that the foregoing conditions were to be completed by October 1, 1973. The 100-gallon per minute requirement was not met until 1985.

*799 1. Problems With the Water System

A. Adequate Water Supply

Before the project plans were presented to the County in 1966, YWA obtained hydrologists’ reports regarding water potential which indicated limited availability of water at the upper elevations and sufficient availability at the lower elevations, specifically, the Indian Creek area. Indian Creek was always considered to be the best source of a constarit and sufficient supply of potable water, but it was considered to be a last resort because of the expense involved in constructing a pipeline system up the hill to the project. Instead, YWA exhausted all potential sources at the upper elevations, which proved to be evasive.

From the very beginning the supply was inadequate to meet County standards. During construction in 1968 the contractor experienced water shortages. The shortages were discussed in a report by the County’s engineer, in which it was concluded that only one-sixth of the minimum requirements of water was available in the existing system. In response to the report the board of supervisors requested that YWA guarantee an adequate water supply before the project would be approved, and Doubt provided such a guarantee.

The preceding year (1967), YWA applied for a public subdivision report from the Division of Real Estate of the State of California (DRE). The DRE would not issue a final public report until it was certain that “financial arrangements have been completed for the installation of water service to the individual lots in this tract, that ample water and service are available, and that same will be furnished on demand without exception.” The matter was referred by Doubt to Tolladáy, who wrote a letter to the DRE certifying an adequate water supply and financial resources to develop the supply based upon well tests and the assessment district bond. Subsequent to the issuance of the final report in 1969, it was discovered that the water supply was inadequate; but the DRE was not apprised of this fact, and YWA continued to give prospective purchasers the DRE report which was based on there being an adequate water supply.

YWA began negotiations with Interwest in 1970 to develop the “Yosemite West Subdivision, Unit Number Two” (Unit #2) condominium project because YWA was not in a position to undertake the project. Throughout negotiations, YWA represented to Interwest that there was an adequate supply of water.

In July 1971, YWA inquired of the County regarding the charges for connecting the condominium project to the Yosemite West Maintenance *800 District and advised the County that information was needed for Inter-west’s application for a public report from the DRE. In December 1971, Doubt presented to the county planning commission YWA’s plans regarding annexation of the condominium project to the Maintenance District. The County’s engineers objected to the condominiums being connected to the Maintenance District because the water and sewer systems within the district would not be able to handle the additional load.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young Han v. City of Folsom
695 F. App'x 197 (Ninth Circuit, 2017)
Lashgari v. Chen CA4/1
California Court of Appeal, 2014
George v. California Unemployment Insurance Appeals Board
179 Cal. App. 4th 1475 (California Court of Appeal, 2009)
In Re Guardianship of Lv
38 Cal. Rptr. 3d 894 (California Court of Appeal, 2006)
S.V. v. J.M.
136 Cal. App. 4th 481 (California Court of Appeal, 2006)
Kephart v. Genuity, Inc.
38 Cal. Rptr. 3d 845 (California Court of Appeal, 2006)
Shafer v. Berger, Kahn, Shafton, Moss, Figler, Simon & Gladstone
131 Cal. Rptr. 2d 777 (California Court of Appeal, 2003)
Howard v. Owens Corning
85 Cal. Rptr. 2d 386 (California Court of Appeal, 1999)
In Re Estate of Breard
84 Cal. Rptr. 2d 276 (California Court of Appeal, 1999)
Cables v. Beard
71 Cal. App. 4th 753 (California Court of Appeal, 1999)
Le Bourgeois v. FIREPLACE MANUFACTURERS, INC.
80 Cal. Rptr. 2d 660 (California Court of Appeal, 1998)
Kizer v. Hillhaven, Inc.
19 Cal. App. 4th 309 (California Court of Appeal, 1993)
Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co.
234 Cal. App. 3d 1724 (California Court of Appeal, 1991)
Continental Airlines, Inc. v. McDonnell Douglas Corp.
216 Cal. App. 3d 388 (California Court of Appeal, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
202 Cal. App. 3d 791, 248 Cal. Rptr. 778, 1988 Cal. App. LEXIS 615, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-mariposa-v-yosemite-west-associates-calctapp-1988.