County of Kern v. Edgemont Development Corp.

222 Cal. App. 2d 874, 35 Cal. Rptr. 629, 1963 Cal. App. LEXIS 1742
CourtCalifornia Court of Appeal
DecidedDecember 4, 1963
DocketCiv. 265
StatusPublished
Cited by12 cases

This text of 222 Cal. App. 2d 874 (County of Kern v. Edgemont Development Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Kern v. Edgemont Development Corp., 222 Cal. App. 2d 874, 35 Cal. Rptr. 629, 1963 Cal. App. LEXIS 1742 (Cal. Ct. App. 1963).

Opinion

BROWN (R.M.), J.

This appeal originated in an action brought by the plaintiff-respondent, County of Kern (hereinafter County), against defendants-appellants, Edgemont Development Corporation (hereinafter Edgemont) and Globe Indemnity Company (hereinafter Globe), for breach of contract for the improvement of streets and installation of a water system in a subdivision located in the County of Kern and on the bond given for the faithful performance thereof. Both defendants join in an appeal from a judgment in favor of County in the sum of $12,938.70, plus prejudgment interest.

*876 The relevant facts may be summarized as follows:

On March 4, 1958, Edgemont, a subdivider, entered into a contract with County whereby, as conditions precedent to approval and acceptance of the final subdivision map, Edgemont agreed to (1) construct certain streets and other public ways, and (2) construct and install a water supply system within the proposed subdivision. Contemporaneously therewith, Edgemont, as principal, and Globe, as surety, executed and posted a faithful performance bond.

Edgemont completed the street work and on October 19, 1959, prompted by a request from Edgemont, the nature of which is not shown by the record, representatives of the county surveyor’s office and of the county road commissioner’s office inspected the street improvement work. On October 20, 1959, the road commissioner’s office, by letter addressed to the board of supervisors but delivered to the office of the county surveyor, stated that the street work had been completed and recommended that it be accepted. The county surveyor returned the letter to the road commissioner’s office and, on October 28, 1959, wrote to Edgemont stating that the street work was found to be complete and satisfactory, that portions of the water system were installed, tested and approved, but since the contract included the installation of a water system, the County was unable to make acceptance until that system was completely installed and accepted. Edgemont then completed the water system.

On July 7, I960, the county surveyor addressed a letter to the board of supervisors, stating that the completed water system had been inspected and found satisfactory on July 6, 1960; that the street work had deteriorated during the winter months so as to be unacceptable; that, since it was not the policy of the County to accept improvement work as separate items, it was recommended that none of the work be accepted but that the matter be referred to the road commissioner and to the county counsel for appropriate action. Copies of this letter were sent to both Edgemont and Globe.

The testimonial evidence shows that the deterioration was primarily the result of wind, rain and lack of maintenance. Some deterioration was caused by heavy equipment operated upon and over the streets and some resulted from the work of installing the water system. County was unable to allocate the damages to one cause or another.

Edgemont refused to do the repair work and the County had it done, letting part out on contract, and using its own equipment and employees to perform the remainder.

*877 On May 23, 1961, the board of supervisors, upon recommendation of the road commissioner and the county surveyor, duly accepted the street improvements and the water system. This action was then commenced for breach of contract and on the bond, tried by the court, and judgment was rendered in favor of County and against both defendants.

On appeal, defendants present four issues: (1) The street improvement work was completed and should have been accepted as of October 20, 1959; (2) Edgemont was under no obligation or duty to maintain or repair the streets; (3) the bond of Globe was exonerated upon the performance of the street work; and (4) in any event, the amount of the judgment is erroneous.

Pursuant to the provisions of the Subdivision Map Act of the State of California (Bus. & Prof. Code, §§ 11500-11629), 1 the County of Kern adopted a subdivision control ordinance which provides, in part, for partial acceptance of improvement work performed by a subdivider as it progresses. Section 5801 of the ordinance requires four things for partial acceptance: a written application for partial acceptance made by the subdivider to the board of supervisors as to street improvement work, the written opinion of the road commissioner that the portion to be accepted is in and of itself a completed unit; as to all other improvement work, the written opinion of the county surveyor that the portion to be accepted is in and of itself a completed unit; and the certificate of the county surveyor that the portion to be accepted has been satisfactorily completed in accordance with the agreement.

There is no question in the case at hand of compliance with the ordinance. Indeed, defendants do not even suggest that there was substantial compliance by either a written or oral application for partial acceptance. The question relates to whether or not defendants’ failure to file a written application for unit acceptance is excused by the law. Defendants rest their claim of legal excuse for noncompliance with the ordinance requirement upon the theory that the filing of an application for partial acceptance, in the face of the position taken by the county surveyor, would be a futile act, and the theory that the county surveyor had arbitrarily and wrongfully withheld his certificate. We cannot agree that complete *878 failure to file an application for partial acceptance may be excused. As the trial judge pertinently remarked in his memorandum decision, “We are not here concerned with a ease of arbitrary refusal to accept the street work alone. Had a proper request for partial acceptance been made and refused, an entirely different situation would be presented.” Had Edgemont intended to seek partial acceptance of the performance due under the contract, under the aegis of section 11612 of the Business and Professions Code, it was under a duty to comply with the procedural requirements prescribed by the ordinance. (See also Bus. & Prof. Code, § 11551.) Had an application been made and rejected for want of the certificate of the county surveyor, Edgemont could have brought a special proceeding in the superior court to determine the reasonableness of the decision of the board (Bus. & Prof. Code, § 11525). The issues which defendants raise on this appeal would be more appropriately addressed to the superior court in such a special proceeding. Instead of pursuing any of the rights available to it under the Subdivision Map Act, Edgemont remained silent, made no protest, and completed installation of the water system. It would now have this court turn back the clock and make primary determinations relating to design and improvement of a subdivision which the Legislature has seen fit to vest in the discretion of the board. (Bus. & Prof. Code, §§ 11506, 11510, 11511, 11525, 11551, 11612.) This a court cannot do. The board has the first right to exercise its discretion in determining whether or not a portion of the work required by the contract is in and of itself a completed unit and to reject or accept streets, before there is court interference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STAMAS v. County of Madera
795 F. Supp. 2d 1047 (E.D. California, 2011)
Opinion No. (2006)
California Attorney General Reports, 2006
Copeland v. City of Oakland
19 Cal. App. 4th 717 (California Court of Appeal, 1993)
City of El Segundo v. Bright
219 Cal. App. 3d 1372 (California Court of Appeal, 1990)
Rink v. City of Cupertino
216 Cal. App. 3d 1362 (California Court of Appeal, 1989)
B & P DEVELOPMENT CORP. v. City of Saratoga
185 Cal. App. 3d 949 (California Court of Appeal, 1986)
County of Yuba v. Central Valley National Bank, Inc.
20 Cal. App. 3d 109 (California Court of Appeal, 1971)
Ackley v. City & County of San Francisco
11 Cal. App. 3d 108 (California Court of Appeal, 1970)
Keizer v. Adams
471 P.2d 983 (California Supreme Court, 1970)
City of Cypress v. New Amsterdam Casualty Co.
259 Cal. App. 2d 219 (California Court of Appeal, 1968)
Pratt v. Adams
229 Cal. App. 2d 602 (California Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
222 Cal. App. 2d 874, 35 Cal. Rptr. 629, 1963 Cal. App. LEXIS 1742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-kern-v-edgemont-development-corp-calctapp-1963.