County of Hennepin v. Richardson

220 N.W. 432, 175 Minn. 60, 1928 Minn. LEXIS 831
CourtSupreme Court of Minnesota
DecidedJune 29, 1928
DocketNos. 26,676, 26,677.
StatusPublished
Cited by3 cases

This text of 220 N.W. 432 (County of Hennepin v. Richardson) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Hennepin v. Richardson, 220 N.W. 432, 175 Minn. 60, 1928 Minn. LEXIS 831 (Mich. 1928).

Opinion

Taylor, C.

On October 10, 1921, plaintiff and defendants Richardson & Ridge entered into a contract whereby Richardson & Ridge (hereinafter called the contractors) agreed to construct county ditch No. 35 of Hennepin county according to designated plans and specifications for the sum of $14,878.70. Defendant Union Indemnity Company executed a bond to plaintiff to secure the performance of the contract. The plans and specifications and the bid of the contractors are made a part of the contract, and it appears therefrom that the contractors were to perform all the work and furnish all the material for the construction of a tile ditch consisting of a main ditch of 140 stations of 100 feet each and three laterals; that the price bid therefor was a specified sum per lineal foot for laying each specified size of tile, amounting in the aggregate to the sum stated in the contract as the contract price; and that the contractors were to lay the tile at a specified depth and grade, and were to refill the trench so as to leave the surface of the ground in its natural condition. The contract contains this provision:

*62 “In the event that solid rock, shale rock or any material that cannot be excavated without drilling or blasting is encountered, the contractor shall be paid at the rate of 15% above cost in lieu of prices set forth in bid.”

The stations on the main ditch are numbered consecutively from 1 to 140 beginning at its source. The contractors began work at the outlet and constructed the ditch as required by the plans and specifications from station 140 to station 113 and were paid $3,006 therefor. It is conceded that this part of the ditch was constructed in the manner required by the contract; that the contractors were entitled to the payment received therefor; and that this suit involves only the work done on the remainder of the ditch and the payments made on monthly estimates as this part of the work proceeded.

At station 113 the contractors encountered rock. Instead of excavating to the required depth they excavated only to the rock and laid the tile on the surface of the rock. This was done by agreement with the engineer but without the consent of the county board. It was deviation from the contract which constituted a breach thereof, for the engineer could not relieve the contractors from their obligation to lay the tile at the specified depth. County of Blue Barth v. National Surety Co. 164 Minn. 390, 205 N. W. 277. By the time the work of construction reached station 22, it became evident that the deviation from the required grade had been so great that the ditch would not carry water from the land to be drained and was useless for the purpose intended. The .trench had been refilled as the tile was laid, and to place the tile at the contract depth and grade would require digging a new trench and excavating the rock to the proper depth. The contractors abandoned the job and refused to complete the contract. They had been paid on monthly estimates for work done and material furnished on this part of the job, amounts aggregating the sum of $9,140.37. In 1926 plaintiff brought this suit against the contractors and their surety setting forth the breach of the contract and asking to recover the amounts so paid as damages resulting from the breach. The court *63 made complete and detailed findings of fact and directed judgment for plaintiff for the amounts so paid and interest thereon less the sum of $249.26 allowed for tile on the ground and not laid. The contractors and the surety made separate motions for a new .trial and took separate appeals from the order denying their respective motions.

At the trial plaintiff proved the facts above outlined and the amounts paid to the contractors but made no attempt to prove the amount of damages in any other manner, asserting that the action was based on the theory

“that the contract has been breached, and that the only measure of damages is the partial payments which have been made under the contract, the only yardstick which will or can measure the damages which have been sustained by the plaintiff.”

The action was tried by plaintiff on that theory, and the court made its findings in accordance therewith.

Defendants contended throughout the trial and contend here that the partial payments made by plaintiff are not the measure of damages and that plaintiff's remedy is to relet the job as provided by G. S. 1923, § 6691. In support of their contention defendants urge that the county is not a party to the proceeding in its proprietary capacity but only as a government agency; and that its duties in respect thereto are' prescribed by the statute and must be performed in the manner directed by the statute, This is undoubtedly true. County of Blue Earth v. Bisballe Constr. Co. 171 Minn. 20, 213 N. W. 30. The statute cited provides that a job not completed by the contractor or his bondsmen

“shall be resold by the auditor, * * * , after ten days' notice by publication, to the lowest responsible bidder, but not for a sum exceeding fifty per cent in excess of the original estimated cost of such work,”

and that the excess, if any, of the cost of so completing it shall be recoverable from the bondsmen of the original contractor. The statute plainly intends that where neither the contractor nor his *64 bondsmen complete the ditch, the county shall cause it to be completed, and in that event shall be entitled to recover as damages the amount, if any, by which the total cost of constructing and completing it exceeds the contract price. This is the usual measure of damages in such cases. Carli v. Seymour, Sabin & Co. 26 Minn. 276, 3 N. W. 348; City of Winona v. Jackson, 92 Minn. 453, 100 N. W. 368; Haney v. Ferch, 150 Minn. 323, 185 N. W. 397; City of St. Paul v. Bielenberg, 164 Minn. 72, 204 N. W. 544.

Pursuant to the provisions of the statute, the auditor advertised for bids to complete the work and received one bid of $11,742.50. The engineer had estimated the cost of the ditch at the sum of $16,027.08. The viewers had assessed the total benefits at the sum of $21,318. Plaintiff had paid out on account of the ditch the sum of $15,467.96. Plaintiff contends that it could not lawfully let the contract to complete the ditch for the reason that the amount of the bid added to the amount previously paid out would make the cost of the ditch exceed the estimated cost by more than 50 per cent and would also make the cost exceed the total amount of benefits.

It is true that a ditch cannot lawfully be constructed if the cost will exceed the benefits. Alden v. County of Todd, 140 Minn. 175, 167 N. W. 548. It is also true that the statute forbids reletting the work for a sum which will make the cost exceed the estimated cost by more than 50 per cent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Guardianship of Hampton
374 N.W.2d 264 (Supreme Court of Minnesota, 1985)
In Re Guardianship of Hampton
359 N.W.2d 740 (Court of Appeals of Minnesota, 1984)
Groves v. John Wunder Co.
286 N.W. 235 (Supreme Court of Minnesota, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
220 N.W. 432, 175 Minn. 60, 1928 Minn. LEXIS 831, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-hennepin-v-richardson-minn-1928.