County Excavation, Inc. v. State

44 Misc. 2d 1057, 255 N.Y.S.2d 708, 1964 N.Y. Misc. LEXIS 1333
CourtNew York Court of Claims
DecidedNovember 3, 1964
DocketClaim No. 39982
StatusPublished
Cited by2 cases

This text of 44 Misc. 2d 1057 (County Excavation, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County Excavation, Inc. v. State, 44 Misc. 2d 1057, 255 N.Y.S.2d 708, 1964 N.Y. Misc. LEXIS 1333 (N.Y. Super. Ct. 1964).

Opinion

Henry W. Lengyel, J.

This is a claim for damages arising out of a certain contract executed on August 17, 1959' by the claimant and the State of New York. The contract was known as Contract No. FASH 59-12 for the construction of approximately 0,9 of a mile of highway along Route 28 in the Village of Herkimer, New York.

The claimant generally seeks the following damages: (a) $9,640.69 caused by the failure of the State to provide a clear site and to undertake acquisition of the necessary right of way with due diligence; (b) $2,000 for removal of three sections of railroad track from the right of way; (c) $500 for construction of drainage ditches under railroad track sections as replaced; (d) $1,800 for construction of three temporary wooden railroad crossings required as a result of the delay in obtaining right of way and removal of said railroad tracks; and (e) $14,165, less a credit of $8,365 already paid under a supplemental agreement, or $5,800, for removal of 16,730 cubic yards of woódíbark and scraps from right of way on the project and for purchase, transportation and filling the same with approved fill.

The State concedes the claim for extra work caused by removal of the railroad tracks from the right of way and the court, therefore, awards the claimant the sum of $1,529.95.

The State also concedes the claim for damages caused by the construction of drainage ditches under railroad track sections and the court, therefore, awards the claimant the sum of $581.10. It should be noted that the Attorney-General stipulated at the trial that the damages occasioned here were $581.10 as opposed to the amount stated in the claim and we consider the claim amended to reflect this stipulation.

The State further does not oppose the claim for damages for the construction of three temporary wooden crossings caused by the failure of the railroad to remove its tracks. There was testimony by the claimant and by the State that an average of one hour each for two men each day would be needed to maintain and repair these crossings. The court awards the claimant the sum of $1,800 as damages for construction and maintenance of these three temporary wooden crossings.

On June 23, 1960, one Mr, Reile, a tenant of the owner of part of the land appropriated for the construction, removed a structure situated upon the right of way. Additional work, which is conceded by the State, was encountered by the claimant [1059]*1059in this area because Mr. B-eile did not leave said area in the condition it was before he removed the structure. The claimant’s superintendent, Mr. Wielt, testified that it took some men and a fiat-bed truck around two to three hours to clear this land, The court believes that $25 is a fair sum for this additional work.

In addtion, the State concedes there was a delay caused by the falure of the Department of Public Work to provide a job site for the claimant. Mr. Kellogg, the State Associate Lands and Claims Adjuster for District 2, Utica, testified that negotiations for acquiring the land at the job site did not begin until August, 1959, According to claimant’s contract, it was to begin work within 10 days of its signing, or by August 24,1959, The plans prepared by the State were completed on April 22, 1959 and maps of the project were filed with the Secretary of State in June, 1959, which filing allows the State or its subagents the right to enter the land for the purpose of clearing and grubbing, but nothing more.

In order for the contractor to proceed further than grubbing and clearing the land, the State must first acquire title to the land or execute a working agreement with the landowner. Acquiring title is accomplished by simply filing copies of the appropriation maps in the office of the Clerk of the county in which the property is located and the office of the Secretary of State. The record is void of any reason as to why these appropriation maps were not filed shortly after they were prepared in the Spring of 1959, or certainly before the contract with the claimant was executed. The delay in filing was certainly one of the causes of the failure of the State to provide a job site for the contractor. As a matter of fact, Mr. Kellogg testified that title to Hubbard property was not acquired until after October, 1959, nearly two months from the signing of the contract, and title to the New York Central property was not acquired until June, I960 or 10 months thereafter.

The court holds that the State by failing to act diligently in making this job site available has made itself liable to the claimant for damages. (Wright & Kremers v. State of New York, 263 N. Y. 615; Grandview Constr. Corp. v. State of New York, 204 Misc. 389; Johnson v. State of New York, 5 AD 2d 919.)

As a basis for computing damages caused by idle equipment the State relied upon the “ Contractor’s Equipment Ownership Expense ” manual (CEOE). That manual states at page 3 under the heading Daily Equipment Expense: Since the idle time of equipment is taken c:are of by a factor in the monthly expense, no such, factor should be used in computing a daily rate. The daily rate is derived simply by dividing the monthly [1060]*1060rate by thirty. When a machine is charged to a job on a daily basis the rate should be charged for each calendar day without deductions for Sundays, holidays, or other idle time during the period it is assigned to the job.”

The claimant relied upon the ‘ ‘ Associated Equipment Distributors ’ ’ manual (AED) in computing damages. That manual also states that the monthly rates should be divided by 30 to figure the daily rate indicating to the court that, unless the proof indicates otherwise, Saturdays, Sundays and holidays should be included in the computation if they are part of a consecutive period. The court finds that each day, regardless of Saturday, Sunday, or holiday, should be counted as part of a consecutive period of use in computing the daily compensation for use of the contractor’s equipment. If these days were not counted, then the monthly rate should be divided by the average number of working days each month, i.e., 22 days, to arrive at a daily rate. This daily rate is of course much higher but used over a number of weeks should not vary too much from the other method. It would, however, have a great effect on the idleness for single days. The court believes that the method followed herein is practical and equitable.

The State contends that the period of delay extends from September 7,1959 to September 30,1959, exclusive of Saturdays and Sundays or a total of 18 days. The claimant contends that the delay runs from September 7, 1959 to October 6, 1959. State’s Exhibit E, a letter from its engineer in charge, Mr. Reagen, to the District Engineer in Utica, indicates that the claimant was authorized to resume work on October 1, 1959. Claimant’s job diary, prepared by its superintendent Mr. Wielt, states at the notation for Thursday, October 1, “ Rained all day wasn’t able to work.” This indicates to the court that the claimant chose not to work on this day because of the inclement weather rather than the failure of the State to provide a job site. The court holds that it was the claimant’s choice not to resume work on October 1, 1959 because it was raining and therefore the State should not be held responsible for any delay after September 30, 1959. We find a total delay period of 24 days.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Ace Stone, Inc. v. Township of Wayne
221 A.2d 515 (Supreme Court of New Jersey, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
44 Misc. 2d 1057, 255 N.Y.S.2d 708, 1964 N.Y. Misc. LEXIS 1333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-excavation-inc-v-state-nyclaimsct-1964.