Council of the City of New Orleans v. Federal Energy Regulatory Commission

692 F.3d 172, 402 U.S. App. D.C. 301, 2012 WL 3289799, 2012 U.S. App. LEXIS 16923
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 14, 2012
Docket11-1043, 11-1044
StatusPublished
Cited by4 cases

This text of 692 F.3d 172 (Council of the City of New Orleans v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Council of the City of New Orleans v. Federal Energy Regulatory Commission, 692 F.3d 172, 402 U.S. App. D.C. 301, 2012 WL 3289799, 2012 U.S. App. LEXIS 16923 (D.C. Cir. 2012).

Opinion

Opinion for the Court filed by Circuit Judge GRIFFITH.

GRIFFITH, Circuit Judge:

The Council of the City of New Orleans and the Louisiana Public Service Commission petition for review of an order of the Federal Energy Regulatory Commission allowing two companies to withdraw from a regional energy system agreement without paying exit fees not mentioned in the agreement. For the reasons set forth below, we deny the petitions.

*174 I

The Entergy System Agreement (the Agreement), which has been a feature of many cases before this Court, establishes the operating framework for the six Entergy companies servicing Arkansas, Louisiana, Mississippi, and Texas (the Operating Companies). La. Pub. Serv. Comm’n v. FERC (Louisiana IV), 522 F.3d 378, 383 (D.C.Cir.2008). The Agreement sets forth a rate schedule administered by FERC and creates a centralized process for determining when and where the Operating Companies will build new power plants. Id. at 383-84. By the express terms of the Agreement, each Operating Company assumes responsibility for the costs of building and operating plants in its own area and retains the rights to the energy those plants produce. Id. at 383-84; see also La. Pub. Serv. Comm’n v. FERC (Louisiana I), 174 F.3d 218, 220 (D.C.Cir.1999). Each party to the Agreement must also make any excess capacity available “to its sister companies as a backstop for when demand exceeds self-generated supply.” Louisiana I, 174 F.3d at 220.

In 1982, FERC interpreted the Agreement to require that the cost of producing electricity be “roughly equal” among the Operating Companies. Louisiana IV, 522 F.3d at 384. But production costs are likely to be unequal because the Operating Companies use different types of fuel. For example, Entergy Arkansas relies primarily on coal, whereas Entergy Louisiana and Entergy Gulf States rely more heavily on natural gas. Id. at 384-85. In order to satisfy the Agreement’s equality mandate, FERC requires the Operating Companies with lower production costs to make payments to those with higher expenses. Id. at 384.

In 2000, the price of natural gas shot up, sharply increasing the existing cost disparities among the Operating Companies. Id. at 384-85. On December 19, 2005, FERC ordered the Operating Companies to make payments to each other to offset any difference in their respective annual production costs greater than eleven percent of the System average. La. Pub. Serv. Comm’n v. Entergy Servs., Inc., 113 FERC ¶ 61,282 (2005). As a result, Entergy Arkansas was required to pay hundreds of millions of dollars annually to the other Operating Companies. The same day as the FERC order, Entergy Arkansas notified the other Operating Companies that it intended to withdraw from the Agreement eight years later, the earliest it could do so under the Agreement’s mandatory notice provision. On November 8, 2007, Entergy Mississippi likewise informed the other Operating Companies that it would exit the Agreement eight years hence. 1

On February 2, 2009, Entergy Services, Inc., the parent corporation that owns all six Operating Companies, submitted formal notices to FERC on behalf of Entergy Arkansas and Entergy Mississippi, stating that they would exit the Agreement. See 18 C.F.R. § 35.15 (“When a rate schedule, tariff or service agreement or part thereof required to be on file with the Commission is proposed to be cancelled or is to terminate by its own terms and no new rate schedule, tariff or service agreement or part thereof is to be filed in its place, a filing must be made [with the Commission].”). The notices provided that the two withdrawing Companies would each operate independently while the other four Operating Companies would remain in the System. Entergy Arkansas and Entergy Mississippi would still be able to buy and sell power from the remaining Operating *175 Companies, but without the preferential treatment the Agreement affords.

On November 19, 2009, FERC accepted the notices and issued orders concluding that the Agreement required no further conditions on the withdrawals other than the already-proffered eight-year notice to the other Operating Companies. Order Accepting Notices of Cancellation, Entergy Servs., Inc., 129 FERC ¶ 61,143 (Nov. 19, 2009). The Council of the City of New Orleans and the Louisiana Public Service Commission petition for review of FERC’s order. We take jurisdiction under 16 U.S.C. § 8252(b).

II

We review FERC orders under the Administrative Procedure Act, which requires that we determine whether the challenged action was arbitrary and capricious. Louisiana IV, 522 F.3d at 391. Because the gist of the petitioners’ argument is directed at FERC’s reading of the Agreement, we resort to the learning of Chevron, U.S.A., Inc. v. Natural Resources Defense Council, 467 U.S. 837, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984), to see if the agency’s interpretation of the contract was reasonable. Entergy Servs., Inc. v. FERC, 568 F.3d 978, 981-82 (D.C.Cir.2009) (“We review claims that the Commission acted arbitrarily and capriciously in interpreting contracts within its jurisdiction by employing the familiar principles of Chevron.”). Under that standard, “We evaluate de novo the Commission’s determination that a contract is ambiguous, but we give Chevron-like deference to its reasonable interpretation of ambiguous contract language.” Id. at 982. The petitioners argue that FERC misinterpreted the Agreement and failed to impose two conditions on Entergy Arkansas and Entergy Mississippi that are required when a Company withdraws from the System. As the petitioners read the Agreement, a Company may not leave the System without compensating the remaining Companies for the assets it takes. And even after leaving, the .withdrawing Company must continue making “rough equalization” payments to its former partners. FERC found no such conditions in the Agreement, and we hold that its view is reasonable.

The Agreement provides that “any Company may terminate its participation in this Agreement by ninety-six (96) months written notice to the other Companies hereto.” System Agreement § 1.01. FERC held that the Agreement’s text places no explicit conditions on the withdrawing Companies save this requirement of notice. The petitioners concede that the text of the Agreement “says nothing about the rights and obligations of withdrawing Companies regarding System assets,” but argue that the Agreement’s purpose

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
692 F.3d 172, 402 U.S. App. D.C. 301, 2012 WL 3289799, 2012 U.S. App. LEXIS 16923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/council-of-the-city-of-new-orleans-v-federal-energy-regulatory-commission-cadc-2012.