Cottrell v. Atlanta Development Authority, D/B/A Invest Atlanta

Supreme Court of Georgia·Decided March 16, 2015·No. S14A1874·Published

Opinion

297 Ga. 1 FINAL COPY

S14A1874. COTTRELL et al. v. ATLANTA DEVELOPMENT AUTHORITY et al.

MELTON, Justice.

This case concerns the Superior Court of Fulton County’s validation of

roughly $200 million in municipal bonds (the “2014 NSP Bonds”) to be issued

by the Atlanta Development Authority d/b/a Invest Atlanta (“Invest Atlanta”).

Invest Atlanta and the Geo. L. Smith II Georgia World Congress Center

Authority (“Congress Center Authority”) (collectively, the “New Stadium

Entities”) propose to have the 2014 NSP Bonds issued for the purpose of

funding a portion of the cost of developing, constructing, and operating a new

stadium facility in downtown Atlanta (the “New Stadium Project” or “NSP”) for

the Atlanta Falcons professional football team. Additional funding for the NSP

will be provided by the Atlanta Falcons Stadium Company, LLC (“StadCo”), a

Georgia limited liability company associated with the Atlanta Falcons Football

Club, LLC (the “Club”), as well as through the sale of personal seat licenses.

The NSP is a successor facility to the over twenty-year-old Georgia Dome, and it will be owned by the Congress Center Authority, which also owns the Georgia

Dome.

Procedurally, on February 4, 2014, the State of Georgia filed a Petition for

Bond Validation in the superior court to authorize the issuance of the 2014 NSP

Bonds. A notice to the public was filed on that same day, as well as a Rule Nisi

Order setting the bond validation hearing for February 17, 2014. Notice of the

proceeding was published in the Fulton County Daily Report on February 7,

2014 and February 14, 2014 as required by OCGA § 36-82-76. Rev. William L.

Cottrell, Sr., Mamie Lee Moore, Tracy Y. Bates, John H. Lewis, III, and Joe

Henry Beasley (hereinafter collectively “Cottrell”) moved to intervene in the

proceedings to file objections to the bond validation, and the trial court allowed

them to do so. Among other things, Cottrell contended that OCGA § 48-13-51

(a) (5) (B), which allows for an extended time period in which a county or

municipality may levy a Hotel/Motel tax for purposes of funding a “successor

facility” to an existing “multipurpose domed stadium facility,” was an

unconstitutional special law. See Ga. Const. of 1983, Art. III, Sec. VI, Par. IV

(a). The bond hearing was continued until April 10, 2014, and the trial court

entered a Consolidated Pre-Trial Order on April 8, 2014. Following the April

2 10, 2014 hearing, the trial court entered a May 8, 2014 Validation Order and

Final Judgment validating the 2014 NSP Bonds and overruling all objections.

Cottrell appeals from this ruling, and, for the reasons that follow, we affirm.

By way of background, the Georgia Dome was, and the NSP is to be,

funded in part by a Hotel/Motel tax levied under OCGA § 48-13-51 (a) (5).1

Generally, Hotel/Motel taxes can only be levied at a rate of three percent or less.

The statute states in relevant part that 1

(i) . . . a county (within the territorial limits of the special district located within the county) or municipality is authorized to levy a tax under this Code section at a rate of 7 percent. A county or municipality levying a tax pursuant to this paragraph shall expend an amount equal to at least 51.4 percent of the total taxes collected prior to July 1, 1990, at the rate of 7 percent and an amount equal to at least 32.14 percent of the total taxes collected on or after July 1, 1990, at the rate of 7 percent for the purpose of [among other things]: (I) promoting tourism, conventions, and trade shows[.] . . . (ii) In addition to the amounts required to be expended under division (i) of this subparagraph, a county or municipality levying a tax pursuant to this paragraph shall further expend (in each fiscal year during which the tax is collected under this paragraph) an amount equal to 14.3 percent of the total taxes collected prior to July 1, 1990, at the rate of 7 percent and an amount equal to 39.3 percent of the total taxes collected on or after July 1, 1990, at the rate of 7 percent toward funding a multipurpose domed stadium facility. . . . Any tax levied pursuant to this paragraph shall terminate not later than December 31, 2020[.] . . . OCGA § 48-13-51 (a) (5) (A) (i) and (ii). 3 See OCGA § 48-13-51 (a) (1) (D) (“Except as provided in paragraphs (2.1),

(2.2), (3), (3.1), (3.2), (3.3), (3.4), (3.5), (3.7), (4), (4.1), (4.2), (4.3), (4.4), (4.5),

(4.6), (4.7), (5), (5.1), (5.2), and (5.3) of this subsection, no tax levied pursuant

to this Code section shall be levied or collected at a rate exceeding 3 percent of

the charge to the public for the furnishings.”). However, OCGA § 48-13-51 (a)

(5) (A) provides an exception to this three percent ceiling for Hotel/Motel taxes

by allowing counties and municipalities to levy a seven percent Hotel/Motel tax

as long as a designated portion of the collected tax proceeds is used to fund a

multipurpose domed stadium facility. Before 2010, taxes imposed under

Paragraph (a) (5) of OCGA § 48-13-51 were required to have a stated expiration

date “not later than December 31, 2020.” OCGA § 48-13-51 (a) (5) (A) (ii).

However, the General Assembly amended Paragraph (a) (5) in 2010 to add a

new subsection (B), which allowed those taxing jurisdictions that had previously

levied a tax under Paragraph (a) (5) to extend the stated expiration date to

December 31, 2050, so long as the same portion of the proceeds that had been

used to fund the original multipurpose domed facility was expended to fund a

“successor facility” during the extended period. Pursuant to OCGA § 48-13-51

(a) (5) (B):

4 Notwithstanding the [December 31, 2020] termination date stated in division (ii) of subparagraph (A) of this paragraph . . . a tax levied under this paragraph may be extended by resolution of the levying county or municipality and continue to be collected through December 31, 2050, if a state authority certifies: (i) that the same portion of the proceeds will be used to fund a successor facility to the multipurpose domed facility as is currently required to fund the multipurpose domed facility under division (ii) of subparagraph (A) of this paragraph; (ii) that such successor facility will be located on property owned by the state authority; and (iii) that the state authority has entered into a contract with a national football league team for use of the successor facility by the national football league team through the end of the new extended period of the tax collection.

In order to structure the deal and issue the 2014 NSP Bonds for the New

Stadium Project, the New Stadium Entities created various agreements and took

Free access — add to your briefcase to read the full text and ask questions with AI

Cottrell v. Atlanta Development Authority, D/B/A Invest Atlanta, (Ga. 2015).

Cottrell v. Atlanta Development Authority, D/B/A Invest Atlanta (Cottrell v. Atlanta Development Authority, D/B/A Invest Atlanta) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Berry v. City of East Point
627 S.E.2d 391 (Court of Appeals of Georgia, 2006)
Lasseter v. Georgia Public Service Commission
319 S.E.2d 824 (Supreme Court of Georgia, 1984)
McAllister v. American National Red Cross
240 S.E.2d 247 (Supreme Court of Georgia, 1977)
Youngblood v. State of Ga.
388 S.E.2d 671 (Supreme Court of Georgia, 1990)
State v. Martin
466 S.E.2d 216 (Supreme Court of Georgia, 1996)
COTTRELL Et Al. v. ATLANTA DEVELOPMENT AUTHORITY Et Al.
770 S.E.2d 616 (Supreme Court of Georgia, 2015)