Coto-Matic, Inc. v. The Home Indemnity Company and Harry Keener, Trustee in Bankruptcy for Industrial Engineer Co., Inc.

354 F.2d 720
CourtCourt of Appeals for the Tenth Circuit
DecidedJanuary 5, 1966
Docket7874
StatusPublished
Cited by1 cases

This text of 354 F.2d 720 (Coto-Matic, Inc. v. The Home Indemnity Company and Harry Keener, Trustee in Bankruptcy for Industrial Engineer Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coto-Matic, Inc. v. The Home Indemnity Company and Harry Keener, Trustee in Bankruptcy for Industrial Engineer Co., Inc., 354 F.2d 720 (10th Cir. 1966).

Opinion

DAVID T. LEWIS, Circuit Judge.

This diversity action was filed in the District of Kansas by the appellant-plaintiff to recover upon a performance bond furnished by the defendant Home Indemnity Company as surety for Industrial Engineering Co., Inc. (Industrial) upon allegations that Industrial had breached a written contract for the fabrication of a metal painting machine. The appellee Keener was permitted to intervene in his capacity as trustee in bankruptcy for Industrial and counterclaimed for judgment for payment monies claimed under the *722 contract. The trial court determined that Industrial had substantially performed its contract, denied recovery to plaintiff, and awarded judgment on the counterclaim. The plaintiff’s appellate contentions attack the trial court’s findings and conclusions as not supported by the evidence and, more specifically, attack the trial court’s categorization of the subject contract as a plan and specification contract and not an end result contract.

The machine fabricated by Industrial was designated by the contracting parties as a “Five Stage Continuous Coil Stock Finishing System.” Its general concept originated with plaintiff’s founder and subsequent genex’al manager, Clarence Hooper, who, while visiting in Los Angeles, had observed the operation of a semi-automated process for applying paint to small steel sheets. Hooper, an industrial paint salesman, determined that a probable market for a comparable machine existed in the Wichita, Kansas area and began making inquiry about the possibilities of building such a machine. He was first referred to the owner of Jake’s Steel Fabricating Company of Wichita, received some assurance that the idea was feasible, and was referred over to Industrial for whom Jake’s company had done considerable subcontracting.

Hooper knew that Industrial was not a firm of consulting engineers but was primarily engaged in the sale and installation of heating controls, pumps and blowers. However, Industrial evinced interest in the project and numerous discussions ensued during the course of which the concept of the machine was expanded to that of a fully automatic process for painting coiled aluminum or steel. In general, the process contemplated a decoiler or unwinder of the coiled metal, a series of metal treatment tanks, a dry off tower, a paint applicator and bake oven, and a rewinder or recoiler, all operating through a connecting and timed system.

After some three months of talks Hooper requested and received on March 29, 1960, from Industrial a price quotation setting out the materials and components of the machine. This quotation provided in part that: 1) the process was to be a five stage continuous coil stock finishing system, 2) the decoiler was to handle coils of 26 gauge steel or aluminum from 4,000 to 6,000 lbs, 24 to 36 inches in width, 3) the process speed was to be 10 feet per minute, 4) power spray washer and rinse cabinets were to be provided according to certain specifications and be followed by a drying cabinet twelve feet in length, 5) a strip coater or continuous roller coater process would be provided to paint both sides of the metal, 6) a large 42-foot bake oven would be constructed with two temperature zones of 200 and 500 degrees respectively, 7) a hydraulically driven coil rewinder would be fabricated to handle coils of the same weight and size as the decoiler.

During the first week in April Industrial supplemented its quotation with a layout drawing of the proposed machine. This schematic was not a design drawing but did indicate the proposed components, the sequence of their operation and, in general, reflected the parties’ broad concept of the machine, i. e., that metal would be fed off the decoiler in one direction until it had passed through about half the process, then elevated and reversed in direction and returned to a recoiler located very near the decoiler.

On May 16, 1960, Coto-Matic and Industrial executed a written contract, pertinent parts of which follows:

“Whereas, Contractor has prepared and submitted to Owner, an instrument designed, ‘Quotation,’ dated March 29, 1960, and drawings, dated April 4, 1960, with reference to the construction and placing in use of equipment for a five-stage continuous coil stock finishing system and therein set out certain equipment and material, which is to be used in the construction of equipment for said finishing system and,
Whereas, Owner is desirous of employing Contractor for the instal *723 lation and construction of said project.
Now, Therefore, It Is Agreed by and between the parties as follows, for and in consideration of the mutual conditions and covenants as hereinafter set forth.
1. Contractor shall furnish all of the materials as set forth in the Quotation and Drawing which are hereto attached and made a part hereof by reference.
2. Contractor shall submit to Owner, prior to signing of contract, general specifications (which are listed in quotation and drawing), showing the equipment to be installed and placed into operation. Said specifications and drawings shall be deemed to have been approved by Owner upon his signing of contract. It shall be agreed that these drawings are subject to minor deviations or changes which may be required to improve manufacturability or function, or for adaptability to specific installation requirements.
Major changes, if any, in specifications or drawings shall be approved by each of the parties in writing and the contract price set forth herein shall be changed accordingly and approved by the parties in writing.
3. Upon the approval of the specifications and drawings above referred to, and signing of the contract, Owner shall thereupon pay the Contractor, a sum equal to Fifteen per cent (15%) of the total cost of said project, said total cost being in the amount of $32,943.00 plus any use and sales taxes. Contractor agrees to do everything required by this agreement and the specifications and drawings, which by reference, after approval thereof, shall be made a part hereof. * * *
5. Final payment shall be made by Owner to Contractor within thirty (30) days after said equipment has been installed and found to be in a workable mechanical order. Upon receipt of written notice by Contractor to Owner that same is ready for final inspection, same shall be promptly inspected by Owner, and Contractor shall thereupon issue a final certificate stating that work provided for has been completed and that said equipment is in proper working condition. At the time of said inspection Owner shall notify Contractor in writing of any and all deficiencies. If contractor is in agreement with said deficiencies, Contractor will promptly remedy them, * * *
6. Prior to the commencement of work pursuant to this contract, Contractor shall furnish to Owner, a good and sufficient bond, guaranteeing the full and complete performance by Contractor of the terms of this contract, specifications and drawings. * * *
7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
354 F.2d 720, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coto-matic-inc-v-the-home-indemnity-company-and-harry-keener-trustee-in-ca10-1966.