Costello v. Delano

274 Ill. 426
CourtIllinois Supreme Court
DecidedJune 22, 1916
StatusPublished
Cited by1 cases

This text of 274 Ill. 426 (Costello v. Delano) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Costello v. Delano, 274 Ill. 426 (Ill. 1916).

Opinion

Mr. Justice Carter

delivered the opinion of the court:

Defendants in error brought an action of assumpsit in the Moultrie county circuit court against the plaintiffs in error, who are the receivers of the Wabash Railroad Company, and recovered a judgment for $11,318.63, which the Appellate Court for the Third District affirmed, and the record has been brought to this court by writ of certiorari.

The action was brought to recover a balance alleged to be due under a written contract whereby the defendants in error agreed to provide all tools and appliances and perform all labor for the completion of an embankment for new main and side-tracks of the Wabash Railroad Company between the stations of Worden and Poag. The contract was dated May 22, 1912, and provided for the commencement of work within ten days from its date and the completion of the work by August 31, 1912. It contained the following provisions:

“It is understood and agreed by and between the parties hereto that the work included in this contract is to be done under the direction of the chief engineer of said receivers and that his decision as to the true construction and meaning of said drawings and specifications shall be final, and he shall also determine and set forth in his final estimate the amount and kind of all work performed and materials furnished by the contractor under this contract, including all extra work, (meaning all work not covered by this contract,) which final measurements and estimates shall be binding on both parties to this agreement. It is also understood and agreed by and between the parties hereto that such additional drawings and explanations as may be necessary to detail and illustrate the work to be done are to be furnished by said engineer, and the contractor agrees to conform and abide by the same so far as they may be consistent with the purpose and intent of the original drawings and specifications referred to in article 1. Whenever in this contract the term ‘engineer’ is used it is understood to mean the chief engineer of the receivers or his duly authorized agents, limited by the particular duties respectively intrusted to them. * * * On or about the first day of each month during the progress of this work an estimate shall be made by the engineer of the relative value of the part of the work done up to such time, and upon his certificate of the amount being presented to the proper official of the receivers, or such disbursing agent as the receivers may appoint, the amount of said estimate, less a retained ten per cent and less previous payments, shall be paid to the contractor on or about the 20th day of each month at the nearest disbursing point of the receivers to the contractor’s office: And provided further, that upon completion and acceptance of the work under this contract a final estimate shall be issued for the same and the ten per cent previously retained paid in full. * * * It is further mutually agreed between the parties hereto that no estimates given or payments made under this contract, except the final certificates or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials. * * * In the foregoing specifications it is understood and agreed that the chief engineer of the Wabash railroad is in charge of the work and he may appoint such assistants as he may select. Whenever the specifications refer to the judgment, direction, decision, approval, etc., of an employee of the Wabash railroad, they design to and mean that the chief engineer or one of his assistants is intended and referred to. The .decision of the chief engineer shall be final as to the intent and meaning of these specifications."

Work was begun under the contract in May, 1912, but on account of the failure of plaintiffs in error to secure the necessary right of way, as alleged in the declaration, its completion was delayed, the time of performance was extended and the work was finally completed in December, 1912.

It is alleged in the declaration that A. O. Cunningham was chief engineer of the plaintiffs in error and as such chief engineer had general charge and supervision of the construction work to be done under the contract; that during the progress of the work he appointed T. P. McDonough, an engineer, as his duly authorized agent and placed him in charge of the work, with full power and authority to direct the manner in which the work should be done under the terms of the contract and instructed defendants in error to carry on the work under the contract in accordance with the directions of McDonough; that the defendants in error built and constructed the road-bed in accordance with the directions of McDonough and fully completed the same as they were directed to do by him; that on or about the first day of each month while the work was being done an estimate was made by McDonough of the relative value of the work done up to that time, and that he issued certificates of the amount of work so done and performed by defendants in error under their contract and presented the same to the proper official of the plaintiffs in error, and the plaintiffs in error from time to time, on such monthly estimates, issued voucher checks to the plaintiffs for the full amount of each estimate, less a retained ten per cent and less previous payments, which amounts were paid by the plaintiffs in error on or about the 20th day of each month, and that all of these monthly estimates made by McDonough were sent by him to Cunningham, the chief engineer, and have since been retained by him. It is further averred that after the work was completed under McDonough’s direction he made a final estimate of the value of all the work done under the contract and deducted therefrom previous payments made by the defendants on the monthly estimates and added thereto the ten per cent retained percentage, and that there is now due and unpaid on such final estimate the sum of $20,000.

The plaintiffs in error filed a plea of the general issue and several special pleas, which denied that McDonough was authorized by the chief engineer to make any final estimate as to the work done under the contract and averred that he made no final estimate on the authority of the chief engineer on which to base a settlement between the plaintiffs and the defendants; that the estimate which he did make was excessive to the extent of 75,000 cubic yards, and that such estimate was fraudulently made, with intent to cheat and defraud the plaintiffs in error. There was a plea of set-off for $5000, which the plaintiffs in error claim to have overpaid the defendants in error on the contract.

The final measurements and estimates of the chief engineer of the plaintiffs in error of the amount and kind of all work performed and materials furnished under the con-

tract, determined and set forth in his final estimate, were by the agreement to be binding upon both parties. The declaration set forth and relied upon the final estimate of T. P. Mcponough for the establishment of the balance due them under the contract, and this document was introduced • in evidence. An important question, therefore, is whether or not this was such a final estimate as the contract contemplated. McDonough was not the chief engineer of the plaintiffs in error. He was the engineer who had immediate supervision of the work of the defendants in error in the performance of their contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keefer Coal Co. v. United Electric Coal Companies
10 N.E.2d 210 (Appellate Court of Illinois, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
274 Ill. 426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/costello-v-delano-ill-1916.