Costello Construction of Maryland, Inc. v. J.D. Long Masonry, Inc.

236 F. App'x 877
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 26, 2007
Docket06-1704
StatusUnpublished

This text of 236 F. App'x 877 (Costello Construction of Maryland, Inc. v. J.D. Long Masonry, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Costello Construction of Maryland, Inc. v. J.D. Long Masonry, Inc., 236 F. App'x 877 (4th Cir. 2007).

Opinion

PER CURIAM:

Costello Construction (Costello) received a substantial contract to build a new administration building for Loudoun County Public Schools (Loudoun County or County). Costello subcontracted the masonry work to J.D. Long Masonry, Inc. (J.D. Long). Four months after J.D. Long commenced its work on the building, Costello terminated the subcontract and hired another masonry company to complete the work. Costello sued J.D. Long in federal district court, seeking indemnification and damages for breach of contract. J.D. Long counterclaimed for wrongful termination and damages caused by Costello’s delays to the construction schedule. The district court granted summary judgment to Costello on J.D. Long’s counterclaims. Following a bench trial, the district court *879 awarded $777,138.41 in damages to Costello. J.D. Long appeals. We affirm the order of partial summary judgment for Costello but reduce its damages award to $489,224.69.

I.

On September 15, 2003, Loudoun County awarded Costello a contract to construct a new administration building for $21,435,200. The contract provided a substantial completion date of January 10, 2005, and a final completion date of February 10, 2005. The contract said that “time was of the essence” and provided that Costello would pay $2,500 per day in liquidated damages for delays to substantial completion and $1,000 per day in delays to final completion. J.A. 1339.

Costello subcontracted with J.D. Long to do the masonry work for a fixed sum of $1,435,000. The subcontract stated that J.D. Long had 50 days to complete the exterior masonry work, which entailed installing “Arriscraft masonry units at the first level, cast stone above the Arriscraft, and above the cast stone brick masonry with cast stone bands.” Appellant’s Br. at 4. J.D. Long was originally scheduled to start work in April 2004, but the start date was delayed by several months due to problems beyond J.D. Long’s control. On August 11, 2004, Costello informed J.D. Long that the new completion date for the exterior masonry work was September 26, 2004. J.D. Long contested the end date, stating that it had 50 working days to complete the work. J.D. Long said that it would be unable to finish the work until the end of October.

Costello expressed concerns about the quality of the masonry work soon after J.D. Long started. Among other problems, Costello complained that the brickwork did not comply with the job specifications, the cast stones were damaged, and the first-floor Arriscraft wall was improperly installed. (J.D. Long’s on-site foreman, Michael Boyd, admitted at trial that he was unaware of the masonry specifications or the 50-day timetable.) On October 29, 2004, Costello told J.D. Long that its “performance on the Project has been and continues to be seriously deficient.” J.A. 1446. Costello then sent a notice-to-cure letter on November 1, 2004, stating that Costello would terminate the subcontract if J.D. Long did not take immediate corrective action. J.D. Long assured Costello that it would correct the problems, but said that it could not finish the work until the end of November. Costello decided not to take any action under the subcontract until that time. J.D. Long failed, however, to correct the deficiencies or complete the work by the promised date. On December 9, 2004, Costello hired another company, Bragunier Masonry, to take over the work on the building’s exterior. J.D. Long continued to work on the interior of the building.

In January 2005 Loudoun County threatened to terminate its contract with Costello, due in part to defects in the masonry work. Loudoun County then hired a masonry consultant, Wiss Janney, Elstner Associates, Inc. (Wiss Janney), to review J.D. Long’s work and identify the corrective action needed. On March 10, 2005, Costello notified J.D. Long of the County’s concerns with the masonry work. Costello stated that it would give J.D. Long another opportunity to cure its breach of the subcontract. J.D. Long denied that it was the cause of the County’s complaints. On May 20, 2005, after receiving the report prepared by Wiss Janney, Costello sent another notice-to-cure letter, which instructed J.D. Long to correct the deficiencies listed in the report. J.D. Long failed to remedy Costello’s and Loudoun County’s concerns, and Costello terminated the subcontract on June 22, 2005.

*880 Costello sued J.D. Long in the district court for breach of contract, seeking $1,767,702 in damages. J.D. Long counterclaimed for wrongful termination, requesting $677,882 in damages for delays caused by Costello and quantum meruit relief for work already performed. The district court granted partial summary judgment to Costello on J.D. Long’s counterclaims. After a bench trial the district court awarded Costello $777,138.41 in damages.

J.D. Long appeals the district court’s order granting partial summary judgment to Costello and the award for damages. We review the summary judgment decision de novo, and, with respect to the bench trial, we review the district court’s factual findings for clear error and its legal determinations de novo. See Williams v. Sandman, 187 F.3d 379, 381 (4th Cir. 1999).

II.

A.

J.D. Long contends that the district court erred in granting - summary judgment to Costello on J.D. Long’s counterclaim for damages caused by Costello’s delays. J.D. Long says that these delays cost it $370,951 for additional scaffolding and $306,881 for additional labor. The district court determined that J.D. Long’s counterclaim for damages was precluded by Articles 4.1.1.1 and 4.1.1.3 of the subcontract.

Article 4.1.1.1 (“Time is of the essence”) of the subcontract states:

The Contractor has the right to direct the manner in which the Subcontractor performs its work. Subcontractor shall proceed with the performance of the work at such time and in such sequence as the Contractor may direct and/or as required by the Schedule of Progress, which may be updated and revised from time to time by the Contractor as working conditions require, including overtime or shift work performance as necessary. Subcontractor shall perform overtime work and/or provide additional shifts and/or increase crews and equipment to assure timely completion of the project at not [sic] cost to Contractor, unless and only if the costs therefore are paid by the Owner for the Subcontractor’s behalf.

J.A. 1391 (emphasis added). Article 4.1.1.3 (“Damages for Delay”) states that “[a] time extension shall be the sole and exclusive remedy of the Subcontractor for delays or suspensions caused by Contractor.” J.A. 1391.

These two provisions unambiguously prevent J.D. Long from recovering monetary damages from Costello, even for delays that Costello caused, unless Loudoun County agrees to pay the costs. Under Maryland law, which governs our interpretation of the contract, “[w]here a contract is plain and unambiguous, there is no room for construction, and it must be presumed that the parties meant what they expressed.” Feick v. Thrutchley, 322 Md. 111, 586 A.2d 3, 4 (1991). We therefore affirm the district court’s grant of summary judgment to Costello on J.D. Long’s counterclaim for damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Willard Packaging Company, Inc. v. Javier
899 A.2d 940 (Court of Special Appeals of Maryland, 2006)
Feick v. Thrutchley
586 A.2d 3 (Court of Appeals of Maryland, 1991)
Air Caledonie International v. AAR Parts Trading, Inc.
315 F. Supp. 2d 1319 (S.D. Florida, 2004)
Williams v. Sandman
187 F.3d 379 (Fourth Circuit, 1999)
Schonfeld v. Hilliard
218 F.3d 164 (Second Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
236 F. App'x 877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/costello-construction-of-maryland-inc-v-jd-long-masonry-inc-ca4-2007.