Corval Constructors, Inc. v. FPD Power Development, LLC

CourtCourt of Appeals of Minnesota
DecidedMarch 23, 2015
DocketA14-706
StatusUnpublished

This text of Corval Constructors, Inc. v. FPD Power Development, LLC (Corval Constructors, Inc. v. FPD Power Development, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corval Constructors, Inc. v. FPD Power Development, LLC, (Mich. Ct. App. 2015).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A14-0706

Corval Constructors, Inc., Respondent,

vs.

FPD Power Development, LLC, Appellant.

Filed March 23, 2015 Affirmed Larkin, Judge

Ramsey County District Court File No. 62-CV-12-4231

Ernest F. Peake, Patrick J. Lindmark, Leonard, O’Brien, Spencer, Gale & Sayre, Ltd., Minneapolis, Minnesota (for respondent)

Mark J. Heley, John A. Markert, Stephen F. Buterin, Heley, Duncan & Melander, PLLP, Minneapolis, Minnesota (for appellant)

Considered and decided by Halbrooks, Presiding Judge; Johnson, Judge; and

Larkin, Judge.

UNPUBLISHED OPINION

LARKIN, Judge

In this dispute stemming from the construction of a power-generating station,

appellant subcontractor challenges (1) the district court’s grant of summary judgment to respondent general contractor and its summary dismissal of appellant’s counterclaim,

(2) the district court’s imposition of a sanction against appellant for abusing the subpoena

process, and (3) the district court’s award of certain costs to respondent. We affirm.

FACTS

Respondent Corval Constructors, Inc. (Corval) contracted with Northwestern

Energy Corporation to serve as a general contractor for the construction of a power-

generating station in Montana. Corval subcontracted part of the work to appellant FPD

Power Development, LLC (FPD). Under the subcontract, FPD agreed to provide

electrical services and equipment and to install the equipment.

Although FPD agreed to a fixed price, article six of the subcontract provides for

additional compensation in the event that Corval made project changes during

construction. The subcontract refers to these changes as “directed changes” and sets forth

a detailed procedure that FPD had to follow to obtain additional compensation for such

changes. Of note here, FPD had to submit a written request for a “change order” to

Corval within three days of a directed change. The subcontract states that a request for

additional compensation that “does not fully comply with the [subcontract] shall not be

considered a [c]hange [r]equest under the [s]ubcontract.” The subcontract also states that

FPD is not eligible for additional compensation unless FPD received a written change

order from Corval and that if FPD performed work related to a change without a written

change order, “[FPD] shall be deemed to have knowingly and intentionally waived and

released all claims for additional compensation . . . regardless of any written or verbal

protests or claims by [FPD] to the contrary,” and “[Corval] shall be under no obligation

2 to . . . pay or reimburse [FPD] for any cost or expense related to an [u]napproved

[c]hange.”

During the course of the project, substantial changes were necessary. Ultimately,

11 plan revisions became part of the subcontract. FPD submitted nearly 150 change-

order requests, and Corval approved most of them. Approximately one-third of the

change-order requests were approved and paid even though FPD did not adhere to the

three-day notice requirement and the parties did not adhere to other aspects of the

change-order process in the written subcontract.

Weeks after the project was basically complete, FPD submitted several change-

order requests, seeking additional compensation. Many of the items for which FPD

sought compensation had been the subject of dispute and discussion during the project

and some had been partially resolved. Corval denied the change-order requests, partly

because FPD failed to follow the change-order process in article six of the subcontract.

FPD filed a construction lien against the property on which the power station was

built. Later, Corval commenced the present action for breach of contract and declaratory

judgment, seeking a declaration that it does not owe FPD additional compensation under

the subcontract. FPD counterclaimed, asserting breach-of-contract, unjust-enrichment,

account-stated, and declaratory-judgment claims. The breach-of-contract and

declaratory-judgment claims are at issue here.1

1 The district court dismissed FPD’s unjust-enrichment claim under Minn. R. Civ. P. 12. And FPD notified the district court, in summary-judgment proceedings, that the court could dismiss its account-stated claim. FPD does not challenge the district court’s dismissal of those claims.

3 The breach-of-contract count of the counterclaim states, in relevant part, that:

36. FPD complied with the terms of the Contract in all respects, including those terms relating to making a claim for additional compensation. FPD submitted various change order requests to Corval for additional compensation due to the issues listed in the paragraphs above, as well as for other reasons. Corval approved some of FPD’s change order requests[,] but the majority were not approved.

37. Despite repeated demands, Corval fails and refuses to approve and pay FPD for the legitimate change order requests made by FPD and therefore is in breach of the terms of the Contract.

The declaratory-judgment count of the counterclaim states that Corval tendered a

payment bond as substitute security for the construction lien FPD filed and that

FPD is entitled to declaratory relief determining that Corval is in breach of its subcontract agreement with FPD, that FPD is entitled to recover damages under its subcontract agreement[,] . . . and that FPD is entitled to recover under the Bond any portion of its judgment against Corval that remains unpaid following entry of final judgment.

Corval moved to dismiss FPD’s counterclaim under Minn. R. Civ. P. 12.02(e) for

failure to state a claim upon which relief can be granted. As to FPD’s breach-of-contract

claim, Corval argued that “the subcontract is for a fixed price that can only be modified

through written change order requests made prior to completing the work” and that FPD

“failed to provide Corval with any written notice of [the] claimed additional costs until

several months after all of the work was completed.” In a written memorandum

responding to Corval’s motion to dismiss, FPD argued that it had properly pleaded the

elements of breach of contract. FPD also argued that Corval’s argument “is not

supported by the language of the Subcontract” because the “plain language of [sections]

4 6.4.1 and 6.4.2 contradicts Corval’s claim that FPD cannot collect for any additional

work that was not authorized by a change order prior to the work proceeding,” and that

the “plain and ordinary meaning of the language in [s]ection 5.3 states that FPD shall be

provided an equitable adjustment for delays and acceleration.”

At the hearing on Corval’s motion to dismiss, the district court agreed with Corval

that FPD’s pleading did not contain a “common course of dealing” theory. But the

district court denied Corval’s motion to dismiss FPD’s breach-of-contract and

declaratory-judgment claims, stating, “At this point, FPD has pled the [s]ubcontract,

timely compliance with all contractual terms, and Corval’s breach.”

After discovery was complete, Corval moved for summary judgment. Corval

argued that FPD “ignore[d] material terms of the subcontract” and “all of [its] claims for

extra compensation are contractually barred because the requests were not timely and

FPD had already completed the work prior to obtaining written authorization for the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patton v. Newmar Corp.
538 N.W.2d 116 (Supreme Court of Minnesota, 1995)
Dale Ex Rel. Smith v. Pushor
75 N.W.2d 595 (Supreme Court of Minnesota, 1956)
Cybyske v. Independent School District No. 196, Rosemount-Apple Valley
347 N.W.2d 256 (Supreme Court of Minnesota, 1984)
Great American Insurance Co. v. Golla
493 N.W.2d 602 (Court of Appeals of Minnesota, 1992)
Frazier v. Burlington Northern Santa Fe Corp.
788 N.W.2d 770 (Court of Appeals of Minnesota, 2010)
Kellar v. Von Holtum
605 N.W.2d 696 (Supreme Court of Minnesota, 2000)
Fabio v. Bellomo
504 N.W.2d 758 (Supreme Court of Minnesota, 1993)
Marriage of Tarlan v. Sorensen
702 N.W.2d 915 (Court of Appeals of Minnesota, 2005)
Riverview Muir Doran, LLC v. JADT Development Group, LLC
790 N.W.2d 167 (Supreme Court of Minnesota, 2010)
Frazier v. Burlington Northern Santa Fe Corp.
811 N.W.2d 618 (Supreme Court of Minnesota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Corval Constructors, Inc. v. FPD Power Development, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corval-constructors-inc-v-fpd-power-development-llc-minnctapp-2015.