Corse v. . Peck

7 N.E. 810, 102 N.Y. 513, 2 N.Y. St. Rep. 493, 57 Sickels 513, 1886 N.Y. LEXIS 873
CourtNew York Court of Appeals
DecidedJune 1, 1886
StatusPublished
Cited by15 cases

This text of 7 N.E. 810 (Corse v. . Peck) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corse v. . Peck, 7 N.E. 810, 102 N.Y. 513, 2 N.Y. St. Rep. 493, 57 Sickels 513, 1886 N.Y. LEXIS 873 (N.Y. 1886).

Opinion

Andrews, J.

The rule that paroi evidence is inadmissible to add to or vary the terms of a written contract, precludes evidence of the negotiation which preceded or conversations which accompanied the making of it in relation to the subject-matter thereof, unless necessary to explain ambiguous provisions, the meaning of which cannot be ascertained with cer *516 tainty by an inspection of the written instrument. We think the trial judge in his refusals to charge, failed to properly enforce this familiar principle in the law of evidence. By the written contract the plaintiff sold to the defendants two million hard brick, to be delivered “ by barge Relief and sloop Clinton, or other boats of equal capacity, in case Relief or Climton is withdrawn, beginning about June Í, 1881, and vessels to run steadily thereafter.” The complaint sets forth the written contract, and alleges that it was subsequently modified by a verbal agreement between the parties to the effect that the plaintiff should not be required to deliver more than five hundred thousand brick per month. It then avers a delivery of five hundred and fifteen thousand three hundred and sixty-six brick prior to J une 30,1881, pursuant to the modified contract; that the defendants on that day refused to pay the balance of $945.99 then due for the brick previously delivered, except on the condition that the plaintiff would give security for future deliveries, and alleges performance on the part of the plaintiff, and demands judgment for the sum of $945.99. The defendants in their answer deny that the contract was modified, or that it had been performed by the plaintiff, and as a counter-claim allege a breach of the contract by the plaintiff in not delivering the remainder of the brick contracted for, resnlting in damage to the defendants.

It was conceded on the trial that the plaintiff delivered on the contract only the five hundred and fifteen thousand three hundred and sixty-six brick mentioned, and it was insisted in her behalf that she was excused from making further deliveries by the refusal of the defendant on the 30th of June, 1881, to pay the $945.99 except on the condition of giving security for future performance, an obligation not imposed by the contract. The defendants on their part denied that they had exacted security as a condition of making the payments required by the contract, and they insisted that under the contract the plaintiff was bound to deliver to them all brick carried by the “ Relief ” and “ Clinton,” or any vessel or vessels substituted therefor, until the whole quantity provided for by the *517 contract was supplied, and that the plaintiff prior to the 30th of June, 1881, had broken the contract by delivering to other parties a cargo carried by the “ Carrie Gurnee' ’ a vessel which had been substituted for the “ Clinton,” withdrawn. In support of their counter-claim the defendants proved that on the 30th of June brick had advanced in price, and that up to the last of September the market price in Hew York was considerably greater than the price fixed in the contract, and that the cargo of the “ Carrie Gurnee ” was delivered to other parties. The plaintiff on the trial anticipated and sought to avoid the defense that deliveries had not been made as fast as required by the contract, by giving proof upon the issue of modification alleged in the answer. In support of this issue she was permitted to show, under objection, that the oral bargain which immediately preceded the signing of the contract, was for the delivery of only five hundred thousand brick in each month, and that immediately after the contract had been presented to and signed by the plaintiff, the plaintiff’s agent read it over a second time and called the attention of Martin, who acted in the transaction for the defendants, to the omission of a provision, limiting the deliveries to five hundred thousand brick a month; that they then figured up the capacity of the two vessels at five hundred thousand a month, and on Martin’s assurance that a delivery of that number each month would be satisfactory to the defendants, nothing further was done, or to use the language of the witness, “we let it go at that.” It does not appear that the written contract had been delivered before this conversation occurred. The oral bargain, the drawing and execution of the written contract, and the conversation alluded to took place at the same interview, the whole transaction occupying but a few moments. The plaintiff’s agent further testified that he saw Martin a few days afterward and said to him that the contract was not drawn according to the agreement, and that Martin replied, “ All you have to do is to send us five hundred thousand brick a month, and we are perfectly satisfied,” to which the plaintiff’s agent responded “ All right.”

It is clear that the oral evidence of the bargain and of the *518 conversation accompanying the making of the written contract, was inadmissible to limit the obligation of the plaintiff thereunder to a delivery of five hundred thousand brick per month. The admission of the evidence for this purpose would be in the very teeth of the settled rule to which we have adverted. The contract made the carrying capacity of the vessels steadily employed, and not a specified number of brick per month, the measure of the deliveries until the whole number should be furnished. It is the clear import of the contract that the plaintiff should make deliveries as fast as they could be made by the designated vessels, running steadily from the time the deliveries were to commence. To engraft upon the writing the limitation indicated by the oral bargain, would be to add a new term to the written contract qualifying its plain meaning. The trial judge, in admitting the evidence, recognized the general principle of the inadmissibility of paroi evidence to vary a written contract, but put his ruling upon the ground that the evidence was competent upon the issue of modification. The evidence of what was said when the writing was executed did not per se tend to establish this issue. That a written contract may be modified by a subsequent new and distinct oral agreement, upon a new consideration, is unquestionable. (Greenl. Ev., § 303.) But the oral evidence of the bargain and of the explanation accompanying the execution of the written contract, instead of showing a modification of the writing, tends to show simply that the writing never expressed the real agreement of the parties, and that the plaintiff, knowing the coútents of the writing, assented to let it stand unaltered on the assurance of Martin that a delivery of five hundred thousand brick a month would be accepted in lieu of performance according to its terms. The evidence might, perhaps, be pertinent in an action for the reformation of the written contract, but this relief was not within the scope of the case made by the complaint, and the case was tried by the plaintiff upon the theory that the non-delivery of the cargo of the “ Carrie Gurnee ” was justified by the verbal agreement. The case was presented to the jury in this aspect. *519

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Continental Bank & Trust Co. v. W. A. R. Realty Corp.
265 A.D. 729 (Appellate Division of the Supreme Court of New York, 1943)
German Publication Society, Inc. v. Pichler
97 Misc. 644 (Appellate Terms of the Supreme Court of New York, 1916)
Lese v. . Lamprecht
89 N.E. 365 (New York Court of Appeals, 1909)
Nichols v. New York & Pennsylvania Telephone & Telegraph Co.
126 A.D. 184 (Appellate Division of the Supreme Court of New York, 1908)
Williams v. Gridley
110 A.D. 525 (Appellate Division of the Supreme Court of New York, 1906)
Morris v. Chesapeake & O. S. S. Co.
125 F. 62 (S.D. New York, 1903)
Trustees of Freeholders & Commonalty v. Jessup
64 A.D. 525 (Appellate Division of the Supreme Court of New York, 1901)
Emmett v. . Penoyer
45 N.E. 1041 (New York Court of Appeals, 1897)
In re Bateman
28 N.Y.S. 36 (New York Court of Common Pleas, 1894)
Hennessey v. Volkening
30 Abb. N. Cas. 100 (The Superior Court of New York City, 1893)
Mattes v. Frankel
20 N.Y.S. 145 (New York Supreme Court, 1892)
Woodard v. Foster
18 N.Y.S. 827 (New York Supreme Court, 1892)
Bagley & Sewell Co. v. Saranac River Pulp & Paper Co.
16 N.Y.S. 657 (New York Supreme Court, 1891)
Behrman v. Linde
54 N.Y. Sup. Ct. 530 (New York Supreme Court, 1888)
Torrey v. Balen Agricultural & Mining Co.
2 N.Y. City Ct. Rep. 387 (City of New York Municipal Court, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
7 N.E. 810, 102 N.Y. 513, 2 N.Y. St. Rep. 493, 57 Sickels 513, 1886 N.Y. LEXIS 873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corse-v-peck-ny-1886.