Corridor H Alternatives, Inc. v. Slater

982 F. Supp. 24, 28 Envtl. L. Rep. (Envtl. Law Inst.) 20469, 45 ERC (BNA) 1750, 1997 U.S. Dist. LEXIS 16154, 1997 WL 643727
CourtDistrict Court, District of Columbia
DecidedOctober 8, 1997
DocketCiv. 96-2622 (TFH)
StatusPublished
Cited by8 cases

This text of 982 F. Supp. 24 (Corridor H Alternatives, Inc. v. Slater) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corridor H Alternatives, Inc. v. Slater, 982 F. Supp. 24, 28 Envtl. L. Rep. (Envtl. Law Inst.) 20469, 45 ERC (BNA) 1750, 1997 U.S. Dist. LEXIS 16154, 1997 WL 643727 (D.D.C. 1997).

Opinion

MEMORANDUM OPINION

THOMAS F. HOGAN, District Judge.

Pending before the Court are the parties’ cross motions for summary judgment. The Court has received a voluminous administrative record and extensive briefing from the parties on these issues; the Court has also received briefs from a group of amici curiae. The Court held a hearing on these motions on September 10, 1997. After considering the arguments at the hearing and the submissions of the parties and of amici, the Court will deny plaintiffs’ motion for summary judgment and will grant defendants’ motion for summary judgment.

I. Statutory Overview and Factual Background

This case involves the Corridor H project, which is part of the Appalachian Highway Development System. Congress authorized the AHDS to provide highway access to the region in order to “open up an area or areas where commerce and communication have been inhibited by lack of adequate access.” 40 U.S.C. app. § 201(a). The highway for the Corridor H project was originally scheduled to stretch from Interstate 79, near Weston, WV, to Interstate 81, near Strasburg, VA; the project has since shortened, and would now stop at the West Yirginia-Virginia border.

Federally-funded highway projects such as the Corridor H project must comply with the National Environmental Policy Act of 1969 (NEPA), 42 U.S.C. §§ 4321-4347. The statute does not mandate substantive choices or decisions, but it sets forth procedural requirements for the decision-making process. The statute requires that an Environmental Impact Statement (EIS) be prepared for any “major Federal action significantly affecting the quality of the environment.” 42 U.S.C. § 4332; 40 C.F.R. Part 1501. The statute prescribes the content of the EIS; among other things, it must include a “detailed statement” that discusses (1) the environmental impact of the proposed action, (2) adverse environmental effects that cannot be avoided, and (3) alternatives to the proposed action. 42 U.S.C. § 4332(2)(C). Where an EIS is required, the agency must also prepare a Record of Decision (ROD) that sets forth the chosen action and the analysis behind that decision. 1 40 C.F.R. § 1502.2

The Council on Environmental Quality has established the procedures for preparing and promulgating an EIS. Among other requirements, a draft EIS must be prepared and *27 circulated for comment, and the Final EIS (FEIS) must reflect that consideration was given to the comments. 28 C.F.R. §§ 771.123, 771.125. The FEIS also must document compliance, to the extent possible, with all applicable environmental statutes and executive orders. Id.

When new information or changes in the proposed action create significant environmental impacts that were not evaluated in the FEIS, the agencies must issue a Supplemental EIS (SEIS) to discuss the new impacts. 23 C.F.R. § 771.130(a). However, an SEIS is not necessary where changes do not result in significant impacts or where there are no new impacts not already considered in the FEIS. 23 C.F.R. § 771.130(a),(b).

In addition to obligations under NEPA, federal highway projects often have obligations under Section 4(f) of the Department of Transportation Act, 49 U.S.C. § 303. That statute affects projects that require the “use of publicly owned land ... of an historic national, State, or Local significance (as determined by the Federal, State, or local officials having jurisdiction over the park, area, refuge, or site).” 49 U.S.C. § 303. By statute, such projects may be approved only if (1) there is no prudent and feasible alternative and (2) all possible planning has been taken to minimize harm to the protected land. Id. However, unlike NEPA, which applies to all federal highway projects, this statute is triggered only if a project uses protected lands. 2 If no such protected lands are used by the project, then no Section 4(f) duties are implicated.

The story of the Corridor H project and NEPA compliance is fairly complex. Study and planning for the project began in the late 1970’s and the agencies involved produced a Draft Environmental Impact Statement (DEIS) in 1981. Shortly thereafter, the project was suspended. The project remained suspended until 1990, when defendants Federal Highway Administration (FHWA) and West Virginia Department of Transportation (WVDOT) began collaboration on a Supplemental Draft EIS (SDEIS) to account for new studies, changes in alternatives, and other effects of passing years. They prepared the SDEIS in two stages: first, a Corridor Selection draft (CSDEIS), and second, an Alignment Selection draft (ASDEIS). The CSDEIS, issued in 1992, examines potential corridors (2000 feet wide sections) for improvement or for a new highway. The AS-DEIS, issued in 1994, examines some alternative plans for the project, including the four-lane Build Alternative, the two-lane Improved Roadway Alternative, and the No Action Alternative.

FHWA issued an FEIS in April 1996. The FEIS identifies defendants’ choice of the four-lane Build Alternative as the Preferred Alternative, with a corridor that stretches over 100 miles from Elkins, WV to the West Virginia-Virginia border. The Preferred Alternative provides for the construction of new, four-lane highway segments for much of the length of the project. The FEIS includes two agreements that govern post-FEIS implementation of the program. First, the FEIS includes a Programmatic Agreement, which establishes a procedure for compliance with Section 106 of the National Historic Preservation Act. Second, the FEIS includes a Migration Agreement to deal with potential migration of the corridor placement prior to final FHWA approval of the project. According to defendants, these agreements are intended to ensure compliance with Section 4(f) of the Department of Transportation Act. In order to guarantee this compliance, the ROD — issued August 2, 1996 — conditioned final approval of the project on fulfillment of these agreements. This arrangement essentially recognizes that compliance with Section 4(f) has not yet been achieved, but it makes final approval of the project plans conditional on that compliance.

Plaintiffs’ Complaint raises four alleged defects with defendants’ decision to support the four-lane Build Alternative as the Preferred Alternative. First, in Count One, plaintiffs argue that defendants have violated

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Jewell
177 F. Supp. 3d 91 (District of Columbia, 2016)
Hammond v. Norton
370 F. Supp. 2d 226 (District of Columbia, 2005)
City of Alexandria, Va. v. Slater
46 F. Supp. 2d 35 (District of Columbia, 1999)
Corridor H Alternatives, Inc. v. Slater
166 F.3d 368 (D.C. Circuit, 1999)
Davis v. Latschar
83 F. Supp. 2d 1 (District of Columbia, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
982 F. Supp. 24, 28 Envtl. L. Rep. (Envtl. Law Inst.) 20469, 45 ERC (BNA) 1750, 1997 U.S. Dist. LEXIS 16154, 1997 WL 643727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corridor-h-alternatives-inc-v-slater-dcd-1997.