CorPoration v. Tower Contracting Co.

174 So. 2d 852, 1965 La. App. LEXIS 4363
CourtLouisiana Court of Appeal
DecidedApril 12, 1965
DocketNo. 6271
StatusPublished
Cited by3 cases

This text of 174 So. 2d 852 (CorPoration v. Tower Contracting Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CorPoration v. Tower Contracting Co., 174 So. 2d 852, 1965 La. App. LEXIS 4363 (La. Ct. App. 1965).

Opinion

LOTTINGER, Judge.

The Plaintiff-appellee is the owner of the Holiday Inn Motel, located in Baton Rouge, Louisiana. The Defendant-appellant is a general contractor who on the 25th day of July, 1958 entered into a written contract with the above owner whereby it was to construct, in accordance with plans and specifications and the other terms and conditions outlined in the contract, a motel on the premises owned by plaintiff in the above city. The supervising architect of this contract was Eldred Blakewood III of Baton Rouge, Louisiana.

The general contractor undertook and completed the construction of the motel and acceptance for the owner was made on February 4, 1959. Under the terms of the contract there was to be a guarantee period of one year from the date of acceptance, which would have ended on February 4, 1960, but same was extended by the contractor until March 4, 1960. This was accepted by the contractor and his liability was in effect under the guarantee clause. During the course of the guarantee period, numerous defects in the construction were noted by the owner and architect and, as a consequence, the Board of Directors of the plaintiff in accordance instructed their manager to inspect the motel thoroughly and make a list of all apparent defects. This was accomplished by the manager and his maintenance man and this list of apparent defects was submitted to Mr. Blakewood, the architect. Mr. Blakewood, using the owner’s list as a guide, then made a thorough inspection of the motel and prepared a list of defects which he found existing and which, in his opinion, came in the guarantee provisions of* the contract against defects in material, workmanship and construction. Some defects as listed by the owner were deleted by the architect on the apparent theory that it did not come under the apparent [854]*854provisions of the contract. The architect then sent a letter to the general contractor listing all of the defects which he had found, and this letter is dated January 29, 1960, asking that these defects be corrected under the contract. The architect received no reply from the defendant, however the defendant admitted that this letter was received timely and that the general contractor had notice of the defects within the guarantee period. The architect was never advised by the defendant of any objection to the list of defects which he had outlined in his letter, nor was there any compliance to the request for correction of these defects. Due to this refusal by the general contractor to comply with the architect’s decision, it became necessary for plaintiff to file suit against defendant, praying for judgment in an amount sufficient to make the necessary corrections, which claim amounted to $15,-052.00. The defendant filed various and sundry exceptions as a defense to the action brought, but the Lower Court overruled same. The case was then tried on the merits and the transcript involved in this suit consists of eight volumes containing 1859 pages. On August 20, 1963 the Lower Court rendered judgment in favor of plaintiff and against defendant in the full sum of $15,062.00, together with legal interest thereon from date of judicial demand until paid and for all costs of this suit. The defendant has suspen-sively appealed from this judgment and the plaintiff has neither appealed nor filed an answer to same.

We shall first try to dispose of the exception of no cause of action which the defendant has filed to this suit. They have filed two exceptions on two differr ent occasions but the complaint and the grounds of exceptions of no cause of action is predicated on the fact that the specifications and general conditions of the contract sued upon, require that any dispute be referred to arbitration prior to the institution of this suit, and as a result thereof the Lower Court had no jurisdiction. As stated supra the Lower Court overruled these exceptions and tried the case on the merits.

To have a better understanding of the contract, it is necessary that we quote herein certain pertinent portions of said contract. Article 48 of the contract provides as follows:

“ART. 48 GUARANTEE OF WORK:
“Except as otherwise specified all work shall be guaranteed by the contractor against defects resulting from the use of inferior materials, equipment or workmanship for one year from the date of the recorded acceptance of the contract, or from full occupancy of the building by the Owner, whichever is earlier.
"If, within any guaranteed period, repairs or changes are required in connection with guaranteed work, which, in the opinion of the Architect is rendered necessary as the result of the we of materials, equipment or work-menship which are inferior, defective, or not in accordance zvith the terms of the contract, the Contractor shall, promptly upon receipt of notice from-the Ozvner, and wiihoitt expense to-the Owner:
“1. Place in satisfactory condition in. every particular all of such guaranteed work, correct all defects therein, and
“2. Make good all damage to the building or site, or equipment or contents thereof, which, in the opinion of the Architect, is the result of the use-of materials, equipment or workmen-ship which are inferior, defective, or not in accordance with the terms of the contract; and
“3. Make good any work or materials, or the equipment or contents of said building or site disturbed in fulfilling: any such guarantee.
[855]*855"In any case where in fulfilling the requirements of the contract or of any guarantee, embranced in or required thereby, the Contractor disturbs any work guaranteed under another contract, he shall restore such disturbed work to a condition satisfactory to the Architect and guarantee such restored work to the same extent as it was guaranteed under such other contract.
"7/ the Contractor, after notice, fails to proceed promptly to comply with the terms of the guarantee, the Owner may have the defects corrected and the Contractor and his Surety shall he liable for all expense incurred.
“All special guarantees applicable to definite parts of the work that may be stipulated in the specifications or other papers forming a part of the contract shall be subject to the terms of this paragraph during the first year of the life of such special guarantee. Wherever the Specifications require guarantees extending beyond the period of time above specified, such guarantees shall be provided and maintained by the Contractor for the period thus stipulated, in strict accordance with all terms and conditions hereinbefore set forth.” (Emphasis ours).

In addition to the above, the contract provides on Page VII as follows:

“General Conditions
“The General Conditions of the American Institute of Architects, 6th Edition, are hereby made a part of these specifications by reference and shall bind all parties to the contract as fully as if printed and bound herein.
“The aforementioned documents thoroughly explain the relationship between the Architects, Owner and Contractor, and both Owner and Contractor should familiarize themselves with same. A copy of the aforementioned General Conditions are on file at the office of the Architects, and may be examined there.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McKee v. Home Buyers Warranty Corp. II
45 F.3d 981 (Fifth Circuit, 1995)
Armijo v. Armijo
427 P.2d 258 (New Mexico Supreme Court, 1967)
Southern Motels Investment Corp. v. Tower Contracting Co.
176 So. 2d 450 (Supreme Court of Louisiana, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
174 So. 2d 852, 1965 La. App. LEXIS 4363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corporation-v-tower-contracting-co-lactapp-1965.