Cornerstone Pavers, LLC v. Zenith Tech, Inc.

CourtUnited States Bankruptcy Court, E.D. Wisconsin
DecidedSeptember 7, 2023
Docket21-02044
StatusUnknown

This text of Cornerstone Pavers, LLC v. Zenith Tech, Inc. (Cornerstone Pavers, LLC v. Zenith Tech, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornerstone Pavers, LLC v. Zenith Tech, Inc., (Wis. 2023).

Opinion

By ah ae So Ordered. MOTE Dated: September 7, 2023 Wl. A——~ . Michael Halfenger Chief United States} Bankruptcy Judge

UNITED STATES BANKRUPTCY COURT FOR THE EASTERN DISTRICT OF WISCONSIN

In re: Cornerstone Pavers, LLC, Case No. 20-20882-gmh Chapter 11 Debtor.

Cornerstone Pavers, LLC, Plaintiff,

v. Adv. Proc. No. 21-02044-gmh Zenith Tech Inc., Defendant.

OPINION AND ORDER ON (1) CORNERSTONE PAVERS, LLC’S MOTION FOR SUMMARY JUDGMENT AND (2) WEST BEND MUTUAL INSURANCE COMPANY’S SECOND MOTION FOR SUMMARY JUDGMENT

After Zenith Tech Inc. was hired by the Wisconsin Department of Transportation (DOT) to complete a highway-construction project, it subcontracted with Cornerstone

Pavers, LLC, to perform some of the work. Before the subcontracted work was completed, Zenith terminated Cornerstone and replaced it with another subcontractor. Cornerstone later commenced the underlying bankruptcy case and this adversary proceeding, seeking to recover damages from Zenith for breach of the subcontract and the duty of good faith and fair dealing. Zenith counterclaimed on the same grounds. Zenith also seeks to recover from West Bend Mutual Insurance Company on a bond that West Bend allegedly issued to insure the performance of the subcontract (whether by Cornerstone or, as Zenith maintains became necessary here, by someone else). West Bend denies all liability under the bond. West Bend sought summary judgment against Zenith, and the court denied that motion more than a year ago, concluding that West Bend had failed to show that it was entitled to judgment as a matter of law on any of the stated grounds, based on the uncontested facts. Cornerstone now moves for summary judgment against Zenith, asserting that Zenith materially breached the subcontract when it terminated Cornerstone without giving it notice of default and a full opportunity to cure. And West Bend moves for summary judgment against Zenith for a second time, similarly asserting that Zenith’s failure to comply with certain notice requirements of the bond was either a material breach of the bond’s term or otherwise released West Bend from its obligations under the bond. For the following reasons, both motions for summary judgment are denied. I The same, familiar standard applies to both Cornerstone’s and West Bend’s motions for summary judgment against Zenith. “The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a); see Fed. R. Bankr. P. 7056 (“Rule 56 F.R.Civ.P. applies in adversary proceedings . . . .”). Under this standard, a fact is material if a dispute about it “might affect the outcome of the suit under the governing law”. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). And a factual dispute is genuine “if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Id. “The inquiry performed is the threshold inquiry of determining whether there is the need for a trial—whether, in other words, there are any genuine factual issues that properly can be resolved only by a finder of fact because they may reasonably be resolved in favor of either party.” Id. at 250. II Cornerstone argues that, based on uncontested facts, it is entitled to judgment as a matter of law because Zenith materially breached the subcontract when it terminated Cornerstone and hired another subcontractor to complete the work. In support of this argument, Cornerstone points to an exchange of emails that occurred around the time Zenith terminated Cornerstone in July 2019. Zenith responds that the parties’ emails at most show that there are genuine issues of material fact as to whether it terminated Cornerstone in compliance with the subcontract. A The senders and main recipients of the correspondence in question were Chad Shihata of Zenith, Chris Cape of Cornerstone, and Charles Krummel of the DOT. For the sake of clarity, this opinion refers to these individuals by their respective institutions, rather than by their names. On Thursday, July 18, 2019, the DOT sent Zenith an email, to which the DOT attached a “letter noting . . . numerous concrete pavement and concrete ancillary deficiencies on the project.” ECF No. 133-4, at 5. The DOT’s letter lists fourteen such “deficiencies caused by . . . Cornerstone”, including “[f]requent equipment breakdowns”, “[t]wo separate instances . . . while slip-form paving in which the concrete pavement was installed poorly enough that removal and replacement were completed”, and “[p]avement installed approximately 2" to 3" higher than plan grades”. Id. at 6. The letter states that “[t]he issues are affecting [the] schedule” for the project and that the DOT is “not certain what partnering initiatives the department can offer to advance [the] schedule and lesson [sic] the assessment of liquidated damages . . . [i]f the . . . [listed] deficiencies continue.” Id. The letter concludes, “Per standard specification 105.3.2.2 this is Unacceptable Work. Please have your contractor correct these issues immediately to avoid future engineer ordered suspensions of work and an order to completely remove and replace the work that is unacceptable.” Id. at 7. Later the same day, Zenith sent an email directing Cornerstone to “[s]ee the attached letter received . . . from DOT.” Id. at 4. Zenith’s email then lists eight “locations” where “the department” had requested that concrete work by Cornerstone “be removed and replaced”, noting that “[p]roject staff has photos of deficiencies justifying the request” and detailing the issues with the work at each listed location. Id. Zenith’s letter concludes, “As there are major concerns that conforming material/work can be performed, Zenith Tech is directing you to correct your work immediately under section 3.4 of subcontract agreement, Correction of Work, before commencing with further placement of concrete.” Id. at 5. The following day, Zenith emailed Cornerstone again “to address . . . issues” related to the “subcontract agreement” that had apparently arisen during discussions earlier that day. Id. at 2. That email cites specific provisions of the subcontract—namely, sections 3.4, 12.1, 12.2, and 23.1—and describes how, in Zenith’s view, each applied with respect to the previously identified deficiencies in Cornerstone’s work. The email then notes that, since Zenith’s email the previous day, Cornerstone had “proceeded with placement of concrete . . . after being directed not to”, “made marginal attempt to begin removal operations as directed”, “focused . . . on preparing for placement of concrete on Monday”, and “contacted various parties . . . in an attempt to be relieved of direction provided.” Id. at 3. The email then states that, following a discussion with the DOT and to avoid a “potential . . . suspension of work” due to “concerns” described by the DOT to Cornerstone at a meeting that day, Zenith “committed to removing deficient pavement and curb placed.” Id. The email concludes, in relevant part: Again, for reasons listed below and above, you will not proceed with any placement of concrete until you have removed all concrete outlined by the DOT and directed by both DOT and [Zenith]. You will perform this work vigorously until complete and resume concrete placement as directed by [Zenith] per [sections] 3.3 and 23.1 [of the subcontract].” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
State Bank of Viroqua v. Capitol Indemnity Corp.
214 N.W.2d 42 (Wisconsin Supreme Court, 1974)
Ranes v. American Family Mutual Insurance
580 N.W.2d 197 (Wisconsin Supreme Court, 1998)
Wiegel v. Sentry Indemnity Co.
287 N.W.2d 796 (Wisconsin Supreme Court, 1980)
Danbeck v. American Family Mutual Insurance
2001 WI 91 (Wisconsin Supreme Court, 2001)
Henderson v. State Farm Mutual Automobile Insurance
208 N.W.2d 423 (Wisconsin Supreme Court, 1973)
Appleton State Bank v. Lee
148 N.W.2d 1 (Wisconsin Supreme Court, 1967)
Shy v. Industrial Salvage Material Co.
58 N.W.2d 452 (Wisconsin Supreme Court, 1953)
Entzminger v. Ford Motor Co.
177 N.W.2d 899 (Wisconsin Supreme Court, 1970)
Hull v. State Farm Mutual Automobile Insurance
586 N.W.2d 863 (Wisconsin Supreme Court, 1998)
Management Computer Services, Inc. v. Hawkins, Ash, Baptie & Co.
557 N.W.2d 67 (Wisconsin Supreme Court, 1996)
Ashker v. Aurora Medical Group, Inc.
2013 WI App 143 (Court of Appeals of Wisconsin, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Cornerstone Pavers, LLC v. Zenith Tech, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornerstone-pavers-llc-v-zenith-tech-inc-wieb-2023.