Cornell v. Standard Oil Co.

91 A.D. 345, 86 N.Y.S. 633
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 15, 1904
StatusPublished
Cited by1 cases

This text of 91 A.D. 345 (Cornell v. Standard Oil Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornell v. Standard Oil Co., 91 A.D. 345, 86 N.Y.S. 633 (N.Y. Ct. App. 1904).

Opinion

Hatch, J. :

In the year 1895 the defendant was the owner of a large building extending from Broadway to New street in the borough of Manhattan. This building is known as 26 Broadway and 71 New street, and measured about 87 feet on Broadway and New street, by about 200 feet deep, and was ten stories high. The defendant decided to put up five additional stories on the top of said building and erect an extension on the north side thereof about 27 by 60 feet deep, fronting on Broadway, fifteen stories high, and a similar extension fronting on New street. It thus became necessary to build up the , extensions from the ground to the level of the top of the old building and then continue the construction, for five stories more, of the extension and old building together. The foundation of the old building rested upon piles, and while there was a sufficient number ef piles in the entire foundation of the old building to bear the weight of the additional stories, yet these piles were not so placed that the weight of the additional structure would be equally distributed upon them. In order to procure equality of sustaining power and thus carry the additional weight, equalizing girders were placed' upon the top of the old. building and the weight thus distributed over the whole foundation. It appeared upon the trial that the plaintiff on or about the 31st day of January, 1896, entered into a contract with the defendant for the construction of all the iron and steel work required in the building and furnish all the material necessary therefor. By the terms of this contract the plaintiff agreed that the work should be finished on or before the 15th day of June, 1896, and the contract contained a clause that for every day’s delay caused by the plaintiff in completing the work after the 15th day of June, 1896, he should forfeit $50 a day to July first following and $100 a day for each day’s delay thereafter. A reciprocal clause was also provided by which for every day’s delay caused by the defendant the plaintiff should be given an [347]*347additional day iii which to complete the contract, and that the plaintiff should not be liable for any delays caused by independent contractors under contract with the defendant for the performance of other parts of the work. It was further provided in the contract that, in case there was any delay caused by the plaintiff in finishing his work, the defendant might deduct from the amount agreed to be paid as the contract price and as liquidated • damages any sum which might be due or owing to the plaintiff at the time of the completion of the work. The entire contract price of performing the work, not, however, including the extra work, was $234,000. It was admitted upon the trial that the contract was fully completed in every particular as required by its terms, save only in the matter of time, and in addition thereto some extra work was performed by the plaintiff, The work, however, was not completed until the 17th day of January, 1898, nearly two years after the time agreed upon for its completion. The sole question presented by the issues raised upon the trial was as to who was. the party responsible for this delay. At the time of completion by plaintiff of his contract there was unpaid on the contract price the sum of $28,900. This amount is not in dispute, but the defendant contends that it has the right not only to withhold this balance due upon the contract price, which it sets up by way of counterclaim, but that it is also entitled to the further sum of $28,750 on account of plaintiff’s delay, for which sum, with interest and costs, it demands judgment. It is the contention of the plaintiff on the other hand that the delay was caused entirely by acts of negligence of the •defendant in unnecessarily occupying the building and thus preventing the plaintiff from fulfilling his contract and also on account of the delays of independent contractors of the defendant, over whom the plaintiff had no control. The case was submitted to the jury under a charge of which the respondent upon this appeal makes no complaint. By consent of parties the court submitted four questions which the jury were directed to answer, and upon which, by consent, the court was to direct the verdict. The submission, therefore, took the form, so far as the jury were concerned, of a special verdict."

These questions were as follows: “ Was the plaintiff delayed in the performance of his work by the acts or omissions of the defend[348]*348ant, its agents or servants ?” To which the jury answered, “Tes.”1 “ If yea, how many days ? ” The jury answered, “ 536 days.”' “Was the contract completed, as plaintiff'claims, February 24th,. 1897, or as defendant claims, January 17th, 1898?” The jury answered, “Completed January 17th, 1898.” “If not upon either date, when ? ” To which the jury returned no answer. The effect, of this verdict based upon a computation showed that there were. 581 days of delay in all, 45 days of which were chargeable to the-plaintiff, which would entitle the defendant to deduct from the-amount due upon the contract price $3,750, and the plaintiff was-entitled to recover the remainder of the contract price, if the answers given to the questions by the jury were to stand. This-, seems to have been conceded by both parties upon the trial, and. had the court exercised its power in favor of the plaintiff, he would have been entitled to the direction of a verdict for $25,150, with interest. The court, however, reserved the question and after hearing argument set aside the verdict as being contrary to the evidence, and from the order entered thereon'this appeal is taken. In the disposition which we make of the case it is not necessary that, we enter upon a discussion of the evidence respecting. particular delays as to particular parts of the work, the causes thereof or who was to blame therefor. The contract was an entire contract for the performance of all of the structural iron work upon this, building.. Such being its character, it is evident that the plaintiff' could not be chargeable for any delays, no matter from what reasons such delay, arose, if he was prevented in finally completing his contract as to any particular part of the work, if such delay was occasioned by the acts of the defendant, its contractors, servants or agents. In other words, if the plaintiff finally completed the contract as soon as he was permitted so to do by the defendant, then it. is of no consequence whether he had prior to that time delayed in the performance of other parts of his contract so long as such delay did not operate to prevent him from fully completing the Contract as soon as he had opportunity. (Weeks v. Little, 89 N. Y. 566.) It could make no difference in time of completion of his contract that: there was delay by reason of neglect upon particular parts of the Work,, if the defendant opposed obstacles preventing its full completion at an earlier date. The penalty provided for in the contract would not [349]*349"begin to run until the plaintiff had full opportunity to complete it according to its terms. This was the right reserved to him by its terms, and he could not be deprived of such right by act of the defendant and be charged with penalty for delay based upon any .theory that he might have performed other parts of the contract with more expedition, so long as delays, if any, arising therefrom did. not ■operate to prevent the final completion. Defendant offered no testimony, but rested its case at the close of plaintiff’s proof. The construction, in accordance with the plans and specifications, required that there should be placed upon the front of the New street side of the building a particular kind of iron front, called

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leopold v. City of New York
184 A.D. 244 (Appellate Division of the Supreme Court of New York, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
91 A.D. 345, 86 N.Y.S. 633, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornell-v-standard-oil-co-nyappdiv-1904.