Cornell & Co. v. First Indemnity of America Insurance (In Re Muratone Co.)

198 B.R. 871, 1996 U.S. Dist. LEXIS 9793, 1996 WL 392554
CourtDistrict Court, E.D. Pennsylvania
DecidedJuly 11, 1996
DocketBankruptcy No. 93-10439F. Civil Action No. 95-5782
StatusPublished
Cited by2 cases

This text of 198 B.R. 871 (Cornell & Co. v. First Indemnity of America Insurance (In Re Muratone Co.)) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornell & Co. v. First Indemnity of America Insurance (In Re Muratone Co.), 198 B.R. 871, 1996 U.S. Dist. LEXIS 9793, 1996 WL 392554 (E.D. Pa. 1996).

Opinion

MEMORANDUM AND ORDER

SHAPIRO, District Judge.

This is an appeal from a bankruptcy court judgment that Muratone Company, Inc., Debtor (“Muratone”), and First Indemnity of America Insurance Company (“First Indemnity”) are not obligated on certain payment and performance bonds which Cornell & Company (“Cornell”), the prime contractor on a construction project, required its subcontractor, Muratone, to provide. For the reasons stated below, the judgment of the bankruptcy court will be affirmed.

*873 FACTUAL AND PROCEDURAL HISTORY

The bankruptcy court made the following findings of fact:

Appellant Cornell is a corporation in the construction business as a general contractor. Finding of Fact (“FOF”) 1. In 1991, Cornell was the successful bidder on a construction contract with the Southeastern Pennsylvania Transportation Authority (“SEPTA”) to perform certain major structural repair work on a portion of SEPTA’s Frankfort elevated railway line. FOF 4. On or about February 14, 1991, Cornell entered into a subcontract for certain painting work with Muratone. FOF 6.

The subcontract required Muratone to provide performance and payment bonds satisfactory to Cornell. Paragraph 13.7 of the subcontract provides:

[Muratone] shall furnish [Cornell], if requested, full and duly executed Performance and Payment Bonds, underwritten by a surety or sureties satisfactory to [Cornell], in the full amount of this Subcontract. [Muratone’s] failure to deliver satisfactory bonds within ten (10) calendar days after demand, may be deemed a material breach of this Subcontract.

FOF 7. Exhibit A to the subcontract further states:

Performance Bond
Muratone will supply a Payment and Performance Bond in the amount of the Subcontract Sum at no additional cost to Cornell.

FOF 9.

Muratone began “site work” on May 26, 1991, and actual work no later than the first week of July, 1991. FOF 10, 13. Cornell had a contractual right to insist on Muratone’s supplying performance and payment-bonds before it allowed Muratone to initiate “site work” or more substantive work but it did not do so. FOF 15. However, between February and September 1991, Cornell did ask that Muratone provide the bonds on numerous occasions. FOF 16.

Muratone attempted to obtain the required bonds without success prior to September, 1991. FOF 17. On or about September 4, 1991, performance and payment bonds were issued by appellee First Indemnity “as surety for the subcontract work Muratone was to perform for Cornell on the project.” Statement of Uneontested Facts 8; FOF 18. Muratone’s proffered bonds were for $1.8 million instead of the full subcontract amount of $2.8 million; Cornell agreed to accept bonds in this lower amount because that was all that Muratone could afford. FOF 20.

In consideration for the issuance of the bonds, Muratone paid a premium of $56,000 to the Stoll Agency (“Stoll”), an entity engaged in the business of providing bonds and insurance to contractors. FOF 22-23. Stoll forwarded $56,000 less its commission (15%) to First Indemnity. 1 FOF 24. Cornell, through an authorized special payment of $56,000, advanced the money to Muratone to pay the bond premium. FOF 26. Cornell delivered this payment to Muratone as Muratone delivered the bonds to Cornell. FOF 27.

The bonds were delivered to Mr. Mitchell of Cornell on or about September 14, 1991. FOF 21. Mitchell forwarded the bonds to McCrea and Gallen, Cornell’s bonding agent, who forwarded them to Cornell’s bond surety on the project, Reliance Insurance Company (“Reliance”), for review. FOF 29-30. On or about September 26, 1991, Relance sent Mitchell a written opinion stating that the bonds were issued by a substandard surety company and they would generally prefer bonds issued by a company “with considerably greater financial strength.” FOF 31-32. Mitchell received the September 26th letter on October 3,1991. FOF 33.

On November 8, 1991, Mark J. Evans, CPA and Chief Financial Officer of Cornell, sent Muratone a letter stating: “Please be advised that this bond is unacceptable to us.... It is our position that you have not complied with the bond requirement provision of your contract and that corrective action must be taken immediately.” FOF 34, 36. Although the letter referred only to the performance bond, both the performance and *874 payment bond were returned. Statement of Uncontested Facts 18; FOF 37. Upon receipt of these bonds, Muratone sent them to Stoll, FOF 38, and “request[ed] that the Stoll Agency and the bonding company either satisfy Cornell or return the premium as requested by Cornell.” FOF 43. Stoll still had possession of the bonds at the time of trial. FOF 38.

Stoll responded by letter stating that it had forwarded “the correspondence” to First Indemnity and that it was waiting for First Indemnity’s response “to the Cornell rejection of their bond.” FOF 44. The letter, referring to telephone conversations of Mary Stoll Walter with the Executive Vice President of the National Association of Surety Bond Producers and a representative of the Surety Association of America, stated:

in their opinion, once performance bonds are issued, they are non-cancelable [sic] documents, and the premium charged for those bonds is earned. The fact that two and one half months went by between the time the bonds were issued, and the time that Cornell rejected the bonds, only adds to the hypothesis that the bonds are still in effect.

FOF 45.

Cornell did not seek a return of the bonds at any time. FOF 38. Cornells November 8th letter stated that Muratone was not in compliance with, its contractual bonding requirement, but Cornell did not declare Muratone in default of the subcontract. FOF 39. Despite dissatisfaction with the First Indemnity bonds, Cornell accepted Muratone’s continued performance. FOF 41.

On November 21, 1991, Muratone’s president, Mr. Tiedeken, telephoned McCrea and Gallen to discuss the bonds; subsequently, McCrea and Gallen sent Muratone a letter explaining the requirements for a satisfactory surety company and stating “industry practice dictates that once the original bonds are returned the appropriate credit should be applied as no outstanding liability exists.” FOF 46.

On November 26, 1991, Cornell wrote Muratone again “[i]n conjunction with [Cornell’s] previous letter to [Muratone] dated November 8, 1991” and stated specific reasons that the First Indemnity performance bond was “unacceptable to us.” FOF 47. Copies of the two letters were forwarded to Stoll. FOF 49. Stoll responded that First Indemnity proposed new bonds with Colonia Insurance Company as the surety “to replace the existing subcontract bonds”. FOF 50. Muratone sent the proposal to Cornell on December 16, 1991; it was understood by Cornell, Muratone, Stoll, and First Indemnity that the $56,000 premium previously paid by Muratone would be used to obtain the new surety bonds. FOF 51. Cornell sent the “Colonia proposal” to McCrea and Gallen for review on December 31,1991. FOF 52.

During November and December, 1991, Muratone continued work under the subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
198 B.R. 871, 1996 U.S. Dist. LEXIS 9793, 1996 WL 392554, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornell-co-v-first-indemnity-of-america-insurance-in-re-muratone-co-paed-1996.