CORLE BUILDING SYSTEMS, INC. v. OGDEN WELDING SYSTEMS, INC.

CourtDistrict Court, W.D. Pennsylvania
DecidedJuly 26, 2023
Docket3:21-cv-00104
StatusUnknown

This text of CORLE BUILDING SYSTEMS, INC. v. OGDEN WELDING SYSTEMS, INC. (CORLE BUILDING SYSTEMS, INC. v. OGDEN WELDING SYSTEMS, INC.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CORLE BUILDING SYSTEMS, INC. v. OGDEN WELDING SYSTEMS, INC., (W.D. Pa. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA

CORLE BUILDING SYSTEMS, INC., ) Plaintiff, Vv. Civil No. 3:21-cv-00104-SLH ) Judge Stephanie L. Haines OGDEN WELDING SYSTEMS, INC., ) Defendant.

OPINION Plaintiff Corle Building Systems, Inc. (“Corle”) commenced this action on June 10, 2021, filing a four-count Complaint against Defendant Ogden Welding Systems, Inc. (“Ogden”). ECF No. 1. Corle’s Complaint was ultimately amended on October 6, 2022. ECF No. 29. Corle alleges the following counts against Ogden: fraudulent inducement (Count I), breach of contract (Count breach of implied warranty of fitness for a particular purpose (Count III), and breach of implied warranty of merchantability (Count IV). /d. In its prayer for relief, Corle also requests punitive damages. /d. at p. 55. Pending before the Court is Ogden’s Motion to Dismiss Pursuant to Fed. R. Civ. P. 12(b)(6). ECF No. 30. Ina Memorandum in Support of its Motion to Dismiss, Ogden requests the Court dismiss Count I’ of Corle’s Amended Complaint under the gist of the action doctrine or, alternatively, “because the allegations of misrepresentation are premised upon future predictions and acts, opinions, and puffery.” ECF No. 31. Corle filed a Brief in Opposition to Ogden’s Motion to Dismiss Count I of the Amended Complaint and Ogden filed a Reply Brief. ECF Nos. 33, 34. This matter is fully briefed and ripe for disposition.

Although Ogden’s Motion to Dismiss would more accurately be referred to as a Partial Motion to Dismiss because it seeks to dismiss only one count of the Amended Complaint, the Court will refer to it as a Motion to Dismiss for continuity with the pleadings.

For the reasons set forth below, the Court will GRANT in part and DENY in part Ogden’s Motion to Dismiss Count I of the Amended Complaint. I. Factual Background In 2019, Corle, a pre-engineered metal building manufacturer, contacted Ogden, a manufacturer of automated welding machines, to inquire whether Ogden would be able to propose machinery which would improve Corle’s fabrication of steel beams later used in the construction of metal buildings. ECF No. 29 at 475, 13, 21, 22. In April 2019, Jeffery Darnell (“Mr. Darnell”), President of Ogden, visited Corle’s facility and thereafter began communicating with Frank Kmetz (“Mr. Kmetz”), Vice-President of Corle, regarding proposals to improve Corle’s welding operations. /d. at { 23, 25. Mr. Darnell proposed utilizing Integrated Cold Electrode (ICE) welding technology and components manufactured by third-party ESAB, who was not a party of the transaction between Corle and Ogden. Id. at {9 25-26, 39. After learning that Corle needed equipment which could weld steel between 9 gauge and up to over 1” thick, Mr. Darnell represented that the proposed equipment “would be capable of effectively welding steel ranging from 9 gauge up to over 1” thick.” Id. at §§ 26, 28-32. Corle later reiterated the necessity of processing the described range of steel and expressed a hesitancy to continue negotiation until the agreed upon tests were completed and confirmation of the machines’ ability was received. Jd. at 34-36. Mr. Darnell confirmed this representation, explaining that Ogden had done a test weld with the last machine, successfully completing a “1” single pass with a prepared edge[,|” and that ESAB “successfully welded 9 gauge ... using the proposed welding equipment.” Jd. at 32, 37. Moving forward, Mr. Kmetz and Mr. Darnell discussed a number of revised proposals throughout August and early September, which included the specification that the Web Welder’s run-off tabs would be no more

ny

than 3” to 4”, Id. at §90. After this series of proposals, Mr. Kmetz emailed Mr. Darnell on September 6, 2019, requesting the price when ordering five machines at the same time. /d. at { 42-43. Within 10 days, the Parties finalized the purchase price, payment schedule, and delivery schedule. On September 13, 2019, Corle ordered five welding machines for $1,375,000, and Ogden issued a Purchase Order. /d. at 4] 42-47. In addition to scheduling payment and delivery, the Purchase Order identified numerous specifications regarding the welding machines which include, among other things, the following: 1) The Flange Welder machine would “be capable of performing welds on plate sections with lengths up to 18”, plus lead-in and run-off tabs” and would successfully weld a minimum thickness of 1/4” up to 3/4” although a “thicker weld may be welded with edge prep or multiple pass procedures.” ECF No. 29-1, at p. 9. 2) The Web Welder machine would “be capable of performing welds on plate sections with lengths up to 72”, plus lead-in and run-off tabs and would successfully weld a minimum thickness of 9 gauge and a maximum of 34”, although “thicker may be welded with edge prep or multiple pass procedure.” ECF No. 29-1, at p. 19. While Ogden was unable to meet the delivery timeline set forth in the Purchase Order, Corle paid Ogden $1,237,500, 90% of the full contract price, prior to the delivery of any machines to Corle’s facility. ECF No. 29 at 102, 109. By early March 2020, the first two machines had been delivered and installed at Corle’s facility, but Corle alleges that it began experiencing immediate difficulties with their function. Jd. at {§ 110-111. These difficulties included: (1) The Flange Welder was not operational due to the improper feeding of wire, insufficient space because of the oversized run off tabs, and overall improper welds resulting from the wires arcing, burning, or otherwise malfunctioning. Jd. at { 112.

(2) The Web Welder functioned poorly due to inadequate wire delivery system which resulted in “improper and/or inconsistent welds and welding operations[,]” too much power that caused it to burn “through the metal and/or weld and le[ft] holes in the weld or very uneven welds that need[ed] to be reworked[,]” and a faulty flux delivery system that did not put down the correct amount of flux. /d. at § 113. After a long process of trying to rectify the issues and because Corle was not satisfied with the machinery for the reasons listed above, it revoked acceptance of the two delivered welding machines, rejected delivery of the remaining three welding machines, and demanded an immediate refund of payment in addition to compensation for the damages it incurred. /d. at 118-119, 144-146. Ogden did not refund Corle its payments or compensate it for any damages that may have occurred. /d. at § 147. Therefore, Corle brought suit. I. Legal Standard Under Federal Rule of Civil Procedure 12(b)(6), a complaint may be dismissed, in whole or in part, for “failure to state a claim upon which relief can be granted.” See Fed. R. Civ. P. 12(b)(6). In this way, a motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) tests the legal sufficiency of the complaint. See Kost v. Kozakiewicz, 1 F.3d 176, 183 (3d Cir. 1993). “To survive

a motion to dismiss, a complaint must contain sufficient factual matter ... to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Igbal, 556 U.S. 662, 678 (2009) (citing Bell Adlantic Corp. v. Twombly, 550 U.S. 554, 570 (2007)). “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Jd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
EBC, Inc. v. Clark Building System, Inc.
618 F.3d 253 (Third Circuit, 2010)
Burtch v. Milberg Factors, Inc.
662 F.3d 212 (Third Circuit, 2011)
Kost v. Kozakiewicz
1 F.3d 176 (Third Circuit, 1993)
Greg Allen Const. Co., Inc. v. Estelle
798 N.E.2d 171 (Indiana Supreme Court, 2003)
Phillips v. County of Allegheny
515 F.3d 224 (Third Circuit, 2008)
Gall v. Allegheny County Health Department
555 A.2d 786 (Supreme Court of Pennsylvania, 1989)
Sullivan v. Chartwell Investment Partners, LP
873 A.2d 710 (Superior Court of Pennsylvania, 2005)
Eigen v. Textron Lycoming Reciprocating Engine Division
874 A.2d 1179 (Superior Court of Pennsylvania, 2005)
Bortz v. Noon
729 A.2d 555 (Supreme Court of Pennsylvania, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
CORLE BUILDING SYSTEMS, INC. v. OGDEN WELDING SYSTEMS, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/corle-building-systems-inc-v-ogden-welding-systems-inc-pawd-2023.