Corbin v. Milward

164 S.W. 974, 158 Ky. 308, 1914 Ky. LEXIS 616
CourtCourt of Appeals of Kentucky
DecidedMarch 27, 1914
StatusPublished
Cited by3 cases

This text of 164 S.W. 974 (Corbin v. Milward) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corbin v. Milward, 164 S.W. 974, 158 Ky. 308, 1914 Ky. LEXIS 616 (Ky. Ct. App. 1914).

Opinion

Opinion of the Court by

Judge Miller

Reversing.

On July 14, 1905, tbe appellant Frank Corbin made a written contract with tbe appellee W. R. Milward for tbe erection of a building to be used as an undertaking establishment on North Broadway, in Lexington, for which Milward was to pay the sum of $25,000.00.

Corbin erected the building, and in doing so he furnished extra labor and material aggregating $1,684.95, making the total amount due Corbin $26,684.95. On this account Milward paid in cash and received credit for old material aggregating $25,397.32, leaving a balance of $1,-287.63, for which Corbin filed this suit and asserted a builder’s lien upon the property.

The answer denied that Corbin had complied with all the terms of the contract; and while it admitted certain extras had been furnished, it denied others and claimed certain credits which had not been given in the petition.

As these small matters have, however, been disregarded by both sides upon this appeal, we will so treat them.

The principal claim set up in the answer was that Corbin did not furnish certain show cases or coffin eases which the answer alleged Corbin had agreed to furnish, and which defendant had caused to be made at a cost of $982.50.

The only issue, therefore, as the case is now presented is this: Did the contract require Corbin to furnish the coffin cases in question?

The decision turns upon the construction to be given the following clause in the specifications, which constituted a part of the contract, to-wit:

“INSIDE FINISH.”
“All inside finish in main and private office and the show room and hall on second floor to have quarter-sawed oak, inside casings, base, stools, and aprons, carpet sills, etc., this also includes the cases, complete, in show room, all as shown by the detail drawings. All to be hand cleaned and put up by experienced workmen; all [310]*310other finish throughout the plastered rooms to be of clear yellow pine as per details.”

In the copy of the specifications used by Corbin and filed herein, the underscored words “this also includes the cases, complete, in show room,” are stricken out by an ink line drawn through them with a pen. Corbin testifies that the clause was marked out on the specifications when they were delivered to him, and before he made his bid; while Stanley Milward, who represented his father throughout this transaction, says the words in question had not been stricken out at any time by him or by his authority, and that the first he knew of the claim that they had been stricken out and did not constitute a part of the contract, was after the work had been about completed.

The plans were made in sections, and also constituted a part of the contract. The room in question was on the second floor, and was to be used for the purpose of exhibiting coffins. It was designated upon the plans as the “show room,” and its general outline or floor plan only was shown.

The only thing shown by the plans, beyond the walls and openings, was a line drawn on the floor plan which indicated that three spaces next to the wall and marked “cases,” were to be used for that purpose. The floor lines, the word “eases,” and the phrase “No hardwood finish under cases,” written upon the face of the plan, constitute everything that appeared upon the original plans furnished Corbin for the purpose of making his bid, and constitute the details of the plan over which this controversy arose. Corbin says the notice “No hardwood finish under cases,” explains why the lines and the word “cases” appear on this plan, and that it was merely to show that there was no hardwood floor to be put in these spaces, since the lines and notice shown by the plan gave no data or information whatever as to the- size, material, or character of the coffin cases, which are a very expensive character of cabinet work.

Corbin finished the building about April 1, 1906. In February, 1906, Stanley Milward, with Giannini, his architect went to Louisville for the purpose of procuring data and information as to latest improvements in undertakers’ show rooms, from which the architect was to prepare elaborate detail drawings for a set of show • cases for coffins in the new building. About March 29, 1906, after the building had been practically completed, [311]*311these detail drawings for the coffin cases were shown to Corbin, for the first time, by Milward who demanded of Corbin that he furnish them. Upon Corbin’s refusal to do so for the reason that they were not embraced in* his contract, Milward had them made at a cost of $982.50, which he seeks to charge as a counterclaim against the balance of $1,287.63 due on Corbin’s contract price.

It will be seen, therefore, that the issue is clear cut and cannot be compromised. The contract either required Corbin to furnish the coffin cases, or it did not require him to do so. Milward is entitled to recover the entire cost thereof, or he is entitled to recover nothing upon that score.

The chancellor being of opinion that the contract upon this point was, under the proof, in inextricable confusion, divided the cost between the parties, charging each with $490.25; and after charging Milward with an admitted balance of $213.80, he gave Corbin judgment for $704.50, Avithout interest. Corbin appeals, and for error insists that the court should have given him judgment for the full amount sued for, without any deduction on account of his refusal to make the coffin cases.

Two questions have been argued upon this appeal: (1) were the words above indicated erased from the specifications at the time Corbin made his bid; and if not, (2) did the clause in the specifications above quoted, treating them as originally written, and without any erasure, bind Corbin to furnish the coffin cases?

We Avill pass the first question and leave it undecided, and dispose of the case upon the second issue discussed, since the result must be the same, whether the disputed Avords be left in the specifications, or erased therefrom.

Corbin and Milward flatly contradict each other as to the erasure. Williamson, a contractor who bid upon this building, is the only other witness upon that question; and in making his bid Williamson used the specifications Avhich were subsequently used by Corbin. Williamson says the erasure had not been made when he made his bid, and finding the disputed clause in the specifications, it became necessary for him to consider the disputed clause in making his bid. The specifications as to the coffin cases were so indefinite that Williamson could not make, and did not undertake to make, an intelligent bid upon that subject. They could not, however, be overlooked.

[312]*312Upon that subject William,son says: “When I read the specifications and referred back again to the plans I found there was no definite statement as to what kind and what character the cases were to be, if there were to be-any; and in order to find out and inform myself, I went to see Mr. Stanley Milward and inquired from him in regard to these cases.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Akins v. City of Covington
97 S.W.2d 588 (Court of Appeals of Kentucky (pre-1976), 1936)
McKenna v. Culton
80 S.W.2d 13 (Court of Appeals of Kentucky (pre-1976), 1935)
Totten v. Houghton
2 S.W.2d 530 (Court of Appeals of Texas, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
164 S.W. 974, 158 Ky. 308, 1914 Ky. LEXIS 616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corbin-v-milward-kyctapp-1914.